Approved Champion Environmental Services for the asbestos consultant for abatement on the project (1/18/2016) All construction partners have access through Krueger’s ProCore system for monitoring project (1/18/2016) Selected A/C for elementary gym (3/9/2016) 6/15/2016
3
Completed Tasks
Dilley ISD - 2015 Bond
DD set documents approved – March 10th Project sent out for advertisement – April 21st
Final CDs of the project completed – April 21st 6/15/2016
4
Completed Tasks
Dilley ISD - 2015 Bond
Selected asbestos contractor for removal May 10th – Camacho Demolition for $21,780 Held pre-bid mtg – May 16th @ 10:00am Permit approved with the city – May 16th board meeting 6/15/2016
5
Completed Tasks
Dilley ISD - 2015 Bond
Approved GMP of $ 11,847,223 at the June 1st board meeting Krueger received keys for buildings as needed (June 14th)
Pre-construction mtg held – June 16th
6/15/2016
6
On-Going Tasks
Dilley ISD - 2015 Bond
Asbestos abatement continuing – Completed at gym. Still working at high school and 3rd/4th grade building. Plan right now is for Krueger to stage out of the vacated high school building
6/15/2016
7
Upcoming Tasks
Dilley ISD - 2015 Bond
Will continue to revise schedule (from Krueger & BWA) First day construction work will begin – June 20th (Krueger)
Utilities shut-offs will begin in the buildings to be demoed/remodeled 6/15/2016
8
Upcoming Tasks
Dilley ISD - 2015 Bond
Temporary fencing will go up around the construction areas Receive first pay application from Krueger
Elem A/C scheduled for delivery – July 17th 6/15/2016