Dilley ISD 2015 Bond

Report 4 Downloads 139 Views
Dilley ISD 2015 Bond

6/15/2016

May 16, 2016 Update

1

Dilley ISD - 2015 Bond

Project Process

Concept

6/15/2016

Schematic

Design

TM

Bidding

Construction

2

Completed Tasks

Dilley ISD - 2015 Bond

Approved Champion Environmental Services for the asbestos consultant for abatement on the project (1/18/2016) All construction partners have access through Krueger’s ProCore system for monitoring project (1/18/2016) Selected A/C for elementary gym (3/9/2016) 6/15/2016

3

Completed Tasks

Dilley ISD - 2015 Bond

DD set documents approved – March 10th Project sent out for advertisement – April 21st

Final CDs of the project completed – April 21st 6/15/2016

4

Completed Tasks

Dilley ISD - 2015 Bond

Selected asbestos contractor for removal May 10th – Camacho Demolition for $21,780 Held pre-bid mtg – May 16th @ 10:00am Permit approved with the city – May 16th board meeting 6/15/2016

5

Completed Tasks

Dilley ISD - 2015 Bond

 Approved GMP of $ 11,847,223 at the June 1st board meeting  Krueger received keys for buildings as needed (June 14th)

Pre-construction mtg held – June 16th

6/15/2016

6

On-Going Tasks

Dilley ISD - 2015 Bond

 Asbestos abatement continuing – Completed at gym. Still working at high school and 3rd/4th grade building.  Plan right now is for Krueger to stage out of the vacated high school building

6/15/2016

7

Upcoming Tasks

Dilley ISD - 2015 Bond

Will continue to revise schedule (from Krueger & BWA) First day construction work will begin – June 20th (Krueger)

Utilities shut-offs will begin in the buildings to be demoed/remodeled 6/15/2016

8

Upcoming Tasks

Dilley ISD - 2015 Bond

 Temporary fencing will go up around the construction areas  Receive first pay application from Krueger

Elem A/C scheduled for delivery – July 17th 6/15/2016

9