Development of wave energy resources in the South West – where next after Wave Hub.

Robert Rawlinson-Smith Garrad Hassan Job number/BT/ serial number/ page number

Overview Seapower SW Review Development Factors - Wave resource - Availability of assembly, deployment and O&M facilities - Grid connection - Regulatory issues Phasing of Development Next steps (for SWRDA?)

Job number/BT/ serial number/ page number

Seapower SW Review (2004) Identified favourable combination of:

wave energy resource

grid capacity

Job number/BT/ serial number/ page number

Wave resource

Job number/BT/ serial number/ page number

Grid connection

Job number/BT/ serial number/ page number

Grid connection

Job number/BT/ serial number/ page number

National Grid Seven Year Statement

Job number/BT/ serial number/ page number

Regulatory issues

Job number/BT/ serial number/ page number

Phasing of development Short term 2009-15 - Demonstration phase – Wave Hub leading the way - Monitoring of the impacts of first projects - Diversity of technologies - Emerging incentives and regulatory regime

Job number/BT/ serial number/ page number

Phasing of development Medium term 2015-20 - First commercial projects - Value of ROCs clearer - Regulatory framework in place - Increased confidence in technology

Job number/BT/ serial number/ page number

Phasing of development Long term 2020 and beyond - Commercial deployment of large scale arrays

Job number/BT/ serial number/ page number

Next steps Engagement with developing regulatory regime BERR, DEFRA, Ofgem FLOWW, OREEF, RAG, RAB, NOREL, BWEA, COWRIE Fully understand the impacts of first projects Wave Hub and PRIMARE Putting skills and infrastructure in place Assembly, installation and O&M activities

Job number/BT/ serial number/ page number

The South West offers: - Very good wave energy resource - Wide range of installation and O&M bases - Developing capability in research and development (PRIMARE) - Strong grid infrastructure with significant excess capacity