2014 Integrated Resource Plans Duke Energy Carolinas and Duke ...

Report 52 Downloads 71 Views
2016 Integrated Resource Plans Duke Energy Carolinas and Duke Energy Progress

1/23/2017

1

Resource Planning Overview

Growth in Customer Consumption

Resource Retirements

Resource Need

 Changes in Load Forecast  Impacts of Energy Efficiency (EE)

 Plant Retirement  Purchase Contract Expiry

 Load Resource Balance  Reserve Margin

 Non-conventional Resources  Remaining Resource Gap

2016 Resource Plans 1/23/2017

 Base Plan w/ Carbon Tax  Base Plan w/ Carbon Mass Cap 2

DEC Load Resource Balance (Including Reserve Requirements)

 Peak demand growth and asset retirements are largest drivers for resource needs in DEC  First need in DEC occurs in winter of 2023 1/23/2017

3

DEP Load Resource Balance (Including Reserve Requirements)

 Peak demand growth, asset retirements, and purchase contract expirations are the largest drivers for resource needs in DEP  First need in DEP occurs in winter of 2022

1/23/2017

4

Resource Adequacy Study

1/23/2017

5

Conclusions

 Load response in cold weather and solar penetration have transitioned DEC/DEP systems to winter capacity planning utilities  Based on 1 day in 10 year criteria  DEC: 16.5% winter reserve margin  DEP: 17.5% winter reserve margin

 Adopted a 17% minimum winter reserve margin target for DEC and DEP based on the consensus of the two studies  Economics support the 17% winter reserve margin

1/23/2017

6

Solar Sensitivities

1/23/2017

7

Key Inputs

1/23/2017

8

Load Forecast - System Winter Peaks Before and After EE

1/23/2017

9

Key Inputs: Energy Efficiency & Demand Side Management

1/23/2017

10

DEC Base Case EE

1/23/2017

11

DEP Base Case EE

1/23/2017

12

Key Inputs: Renewables

1/23/2017

13

Process for Forecasting Renewable Generation

Identify Key Drivers NC REPS and SC DERP Targets

PURPA & other Incentives

Customer Demand

Operational Consideration; Jurisdictional Differences

Interest in customer programs

Least Cost, System Benefits

Evaluate main variables

Economic Factors

Markets, Policy and Regulatory Developments

Produce Renewable MW & MWH forecasts

• • •

Multiple internal reviews with subject matter experts Alignment with recent trends and other studies Assessment of market environment to determine base case or most likely outcome

1/23/2017

14

14

Forecast Results: DEC Renewable MW by Category

1/23/2017

15

Forecast Results: DEP Renewable MW by Category

The renewable projection for DEP shows a different mix between solar PURPA and NC REPS compliance vs. DEC due to two factors: a) much larger pipeline of solar projects in the queue and b) lower compliance needs relative to MWH targets

1/23/2017

16

Solar Generation Capacity – North Carolina vs Other States

1/23/2017

17

NC REPS

DEC

DEP

2020 System Load Forecast

2020 System Load Forecast

99,132 GWh

65,869 GWh

2020 NC Load Forecast

2020 NC Load Forecast

71,347 GWh

58,586 GWh

2020 NC Retail Load Forecast 62,760 GWh

12.5% of 2020 NC Retail Load 7,845 GWh (DEC) 5,058 GWh (DEP)

2020 NC Retail Load Forecast 40,460 GWh

* 7,845 GWh (DEC) and 5,058 GWh (DEP) only represents the projected amount of Renewables and EE required to meet REPS compliance in 2021 based on the NC Retail load forecast for the year 2020. The cumulative EE and renewables energy on the DEP system is expected to be greater than what is represented here. Additionally, NC REPS allows 65% of the 2021 target to be met by EE and Out of State Renewable Energy Certificates (RECs). 1/23/2017

18

Technology Screening

1/23/2017

19

Technology Screening

1/23/2017

20

Economic Screening

Technologies Screened During Economic Screening1 Baseload

Peaking/Intermediate

Renewable

782 MW Ultra-Supercritical Pulverized Coal with CCS

166 MW 4 x LM6000 CT

2 MW / 8 MWh Li-ion Battery

557 MW 2x1 IGC with CCS

201 MW 12 x Reciprocating Engine Plant

5 MW Landfill Gas

2 x 1,117 MW Nuclear Units (AP1000)

870 MW 4 x 7FA.05 CT2

150 MW Wind – On-Shore (NonDispatchable)

576 MW 1x1x1 Advanced CC (Inlet Chiller & Fired)

5 MW Solar PV (Non-Dispatchable)

1,160 MW 2 x 2 x 1 Advanced CC (Inlet Chiller & Fired) 20 MW CHP

Notes 1: Units highlighted in Red font were screened into the quantitative analysis as potential supply-side resource options to meet future capacity needs 2: A 2x7FA.05 version was also included based upon the cost to construct 4 units

1/23/2017

21

Analytic Analysis

1/23/2017

22

IRP Process – Drivers

 Key drivers were varied in System Optimizer (SO) to assess impacts on resource plans  Potential Carbon Constraints 1. Carbon Tax on existing coal and gas units 2. System Carbon Mass Cap (System Mass Cap)

 Nuclear license extensions  All units relicensed in sensitivity

 Coal and natural gas fuel prices (high / low sensitivities)  Capital costs (high / low sensitivities)  All assets (nuclear, CC/CT, Renewables)  Renewables Only

 Solar penetration (high / low sensitivities)  In all cases, SO was able to select “economic” solar

 Energy Efficiency (high sensitivity)  Peak demand (high / low sensitivities) 1/23/2017

23

IRP Process – Portfolios (DEP)

 Six portfolios were developed based on the results of the SO sensitivity analysis

1/23/2017

24

IRP Process – Portfolios (DEC)

 Six portfolios were developed based on the results of the SO sensitivity analysis

1/23/2017

25

IRP Process – Portfolio Analysis

 The six portfolios were evaluated under several “world view” scenarios using an hourly production cost model called PROSYM Carbon Tax/No Carbon Tax Scenarios1

Fuel

CO2

CAPEX

1

Current Trends

Base

CO2 Tax

Base

2

Economic Recession

Low Fuel

No CO2 Tax

Low

3

Economic Expansion

High Fuel

CO2 Tax

High

System Mass Cap Scenarios2

Fuel

CO2

CAPEX

Current Trends - CO2 Mass Cap

Base

Mass Cap

Base

4

 Portfolios #1 - #4 were run under the Carbon Tax/No Carbon Tax Scenarios  Portfolios #5 & #6 were run under the System Mass Cap Scenario  Portfolios #1 - #4 would not meet the system mass cap constraints

1/23/2017

26

IRP Process – Portfolio Carbon Emission Profiles

 Portfolio #4 (High CC) has the highest CO2 emissions over the long term

 The system CO2 mass cap constraint is not met without nuclear relicensing, or new nuclear generation, in the late 2020s.

1/23/2017

27

IRP Process – Conclusions

DEP  Portfolio #1 (CT Centric) is the least cost portfolio under a Carbon Tax paradigm  The short-term build plan in Portfolio #1 would keep the Company on track if a system CO2 mass cap were implemented

DEC  Portfolio #4 (High CC) is the least cost portfolio under a Carbon Tax paradigm, however its carbon foot print would not be sustainable under a System Carbon Mass Cap  With Lee Nuclear included, Portfolio #1 (CT Centric) is the least cost portfolio followed by high EE and high renewable portfolios

1/23/2017

28

Results

1/23/2017

29

2016 IRP - DEP Expansion Plan – Base Case Duke Energy Progress Resource Plan (1) Base Case - Winter Resource Nuclear Uprates

Year 2017 2018

Sutton Blackstart CT

2019

Nuclear Uprates

2020

Nuclear Uprates

2021 2022

100 14 CHP

12

CHP Nuclear Uprates

2023 2024

CHP Asheville CC

2025 2026 2027 2028 2029 2030 2031 Notes:

22 560

22

22 New CC

6

New CT Nuclear Uprates

MW 8

Potential Asheville CT

1221 468

4

186

New CT

468

New CT New CT

468 468

New CT

1404

(1) Table includes both designated and undesignated capacity additions Future additions of renewables, EE and DSM not included

1/23/2017

DEP Base Case Resources Cumulative Winter Totals - 2017 - 2031 44 Nuclear 1781 CC 3562 CT 66 CHP 5453 Total

30

2016 IRP - DEC Expansion Plan – Base Case Duke Energy Carolinas Resource Plan (1) Base Case - Winter Resource Nuclear Uprates

Year 2017

MW 25

2018

Lee CC

CHP

683

43

2019

Hydro Refurb Return to Service Nuclear Uprates CHP

CHP

10

22

2020 2021

Bad Creek Uprate

2022 2023

Hydro Refurb Return to Service CHP

60

22 46.4

Bad Creek Uprate

46.4 New CC

Bad Creek Uprate

1221

46.4

2024

Bad Creek Uprate

46.4

2025 2026 2027 2028 2029 2030 2031

New CT

468

New Nuclear

1117

New Nuclear

1117

Notes:

6 22

(1) Table includes both designated and undesignated capacity additions Future additions of renewables, EE and DSM not included (2) Lee CC capacity is net of NCEMC ownership of 100 MW (3) Rocky Creek Units currently offline for refurbishment; these are expected return to service dates (4) Lee Nuclear in service dates are assumed to be Nov 2026 and May 2028

1/23/2017

DEC Base Case Resources Cumulative Winter Totals - 2017 - 2031 Nuclear 2319 CC 1904 CT 468 Hydro 202 CHP 109 Total 5002

31

2016 IRP - Joint System Energy by Resource Type

Carolinas Energy by Fuel Type - 2017

1/23/2017

Carolinas Energy by Fuel Type - 2031

32

Key Takeways

1/23/2017

33

Key Takeaways

 Short Term  Completion of 1,250 MWs of CC, 100 MWs CTs and 185 MWs Pumped Storage  System impact of increasing amounts of Solar  T&D, Unit Flexibility, Storage

 Winter Planning  Based on the LOLE study new generation need is driven by winter peaks.

 First need best met with CC in DEC and DEP  2022 in DEP, 2023 in DEC  New Gas Capacity and associated Infrastructure

 Long Term  Pursue 80 year license life for existing nuclear  COL for Lee Nuclear

1/23/2017

34

Q&A

1/23/2017

35