750 NORTH GLEBE ROAD SPRC MEETING #3 MARCH 7, 2016

Existing Metro Station

Future Metro Entrance

750 N. Glebe Road – SP #440

Context Aerial

2

Existing Tazewell View

EXISTING CURB CUT

750 N. Glebe Road – SP #440

Transit Context Plan

Proposed Tazewell View 3

750 N. Glebe Road – SP #440

Ground Floor (as proposed with modifications)

4

Retail Parking: 227 Spaces

Parking Level 1

Parking Space Tabulations Level Retail Resid Total P1 227 0 227 P2 47 210 257 P3 0 273 273 Total 274 483 757

Retail Parking: 47 Spaces

Residential Parking: 210 Spaces

Parking Level 2 NOTE: Parking Level 3 will contain the balance of the residential spaces.

5

Findings/Conclusions: •

Some intersections and/or turning movements have unacceptable levels in background conditions



Mitigation Measures:



1.

Install a Traffic Signal at N Glebe Road and 7th Street N

2.

Signal Timing Adjustments at N Glebe Road and Wilson Boulevard

At County’s request, Traffic Impact Study included two scenarios for N. Tazewell Street (1-way Northbound and 2-way)

Results: Studied intersections’ levels of service remain the same •

Supplemental analysis was prepared with a 25% Mode Split Reduction for Grocery (increased grocery trips compared to the original 50% Mode Split Reduction for Grocery) Results: Studied intersections’ levels of service remain the same 6

• •



Original Analysis Assumed 50% Mode Split Reduction Supplemental Analysis Assumed 25% Mode Split Reduction (Higher Grocery Auto Trips) Mode split reductions are taken against standard ITE¹ trips for supermarkets.

------

Weekday

AM Peak Hour

------

------

PM Peak Hour

Daily

S aturday

SAT Peak Hour

-----Daily

Mode Split Reduction

In

Out

Total

In

Out

Total

Total

In

Out

Total

Total

Residential

60%

22

48

70

46

33

79

700

38

29

67

869

Retail

50%

7

5

12

11

14

25

273

15

15

30

250

Restaurant

50%

32

28

60

31

18

49

632

39

37

76

844

Grocery

50%

45

28

73

106

102

208

2,138

117

112

229

3,826

106

109

215

194

167

361

3,743

209

193

402

5,789

68

42

110

160

154

314

3,207

175

169

344

5,739

129

123

252

248

219

467

4,812

267

250

517

7,702

Land Use

Total Site Trips (50% Grocery) Grocery

25%

Total Site Trips (25% Grocery)

Note: Includes Internal Capture and Mode Split Reduction

_________________________________________

¹ ITE stands for Institute of Transportation Engineers. It publishes the ITE Trip Generation Manual, the industry standard for determining trip rates.

7

8



Two Curb Cuts:

70’ (7th) - 24’ (Tazewell)



25% Mode Split ADT:

Glebe = 2,647 7th = 4,812 Tazewell = 516



50% Mode Split ADT:

Glebe = 2,059 7th = 3,743 Tazewell = 409



Pedestrian Impacts:

Glebe = None 7th = High Tazewell = Low



Loading:

ORIGINAL PROPOSAL

a) Large maneuvering space req’d b) Indoor truck maneuvering c) Indoor truck queueing d) Trucks can go N or S at new light e) No impact on Glebe traffic lanes

9

10

11



Three Curb Cuts:

40’ (Glebe) - 60’ (7th) - 24’ (Tazewell)



25% Mode Split ADT:

Glebe 7th Tazewell

Alt 1 2,550 4,445 1,378



50% Mode Split ADT:

Glebe 7th Tazewell

2,069 3,376 1,111



Pedestrian Impacts:

Glebe = High 7th = High Tazewell = Low



Loading:

ALTERNATE 1 & 1B

Alt 1B 2,962 4,602 761 2,374 3,533 654

a) Smaller loading area req’d b) Easier indoor truck maneuvering c) Less space for indoor queueing d) Trucks can only go south upon exiting e) Trucks cross 3 lanes of Glebe to exit

12

13

14



Three Curb Cuts:

24’ (Glebe) - 70’ (7th) - 24’ (Tazewell)



Average Daily Trips:

Same as Alternates 1 & 1B



Pedestrian Impacts:

Glebe = High 7th = High Tazewell = Low



Loading:

Same as Original Proposal

ALTERNATE 2 & 2B

15

16

ALTERNATE 3



Three Curb Cuts:

20’ (Glebe) - 60’ (7th) - 40’ (Tazewell)



25% Mode Split ADT:

Glebe = 2,200 7th = 4,672 Tazewell = 1,728



50% Mode Split ADT:

Glebe = 1,719 7th = 3,603 Tazewell = 1,461



Pedestrian Impacts:

Glebe = Moderate 7th = High Tazewell = Moderate



Loading:

Same as Alternates 1 and 1B 17

18

ALTERNATE 4



Two Curb Cuts:

70’ (7th) - 40’ (Tazewell)



Average Daily Trips:

Same as Alternate 3



Pedestrian Impacts:

Glebe = None 7th = High Tazewell = Moderate



Loading:

Same as Original Proposal

19

20

ALTERNATE 5



Three Curb Cuts:

14’ (Glebe) - 70’ (7th) - 24’ (Tazewell)



25% Mode Split ADT:

Glebe = 2,647 7th = 3,231 Tazewell = 516



50% Mode Split ADT:

Glebe = 2,059 7th = 2,509 Tazewell = 409



Pedestrian Impacts:

Glebe = High 7th = High Tazewell = Low



Loading:

Same as Original Proposal

21

22

ALTERNATE 6



Three Curb Cuts:

24’ (Glebe) - 70’ (7th) - 24’ (Tazewell)



25% Mode Split ADT:

Glebe = 3,266 7th = 2,612 Tazewell = 516



50% Mode Split ADT:

Glebe = 2,544 7th = 2,024 Tazewell = 409



Pedestrian Impacts:

Glebe = High 7th = Moderate Tazewell = Low



Loading:

Same as Original Proposal

23

24

Eliminate L-shaped loading dock alternatives. VDOT will not approve.

25

Eliminate alternatives with RI/RO ramp off Glebe. VDOT will not approve.

26

Remaining Viable Alternatives

27

THANK YOU

28