BALLSTON QUARTER PEDESTRIAN BRIDGE MANAGER’S REPORT | 27 SEPTEMBER 2016

introduction 1

2

Project Introduction – Background + History

design

3

4

Project History – Base Concept

5

Public Process – Community Meetings

6

Project Approach – Design Principles

7 Site Development

BALLSTON QUARTER

STAFFORD PLACE

STAFFORD PLACE

BALLSTON QUARTER

8

Bridge Design – Development Study 2

9

Bridge Design – Aerial Image

10

Bridge Design – Street View

11

Bridge Design – Street View

12

Bridge Design – Street View

13

Bridge Design – View toward Mall

14

Bridge Design – View toward Stafford

15 Bridge Design – View of Public Art Opportunities

technical considerations 16

Stafford Place

Ballston Quarter Street Section

17

Wilson Blvd.

Bridge Design – Key Technical Considerations

18

Bridge Design – Key Technical Considerations

19

Bridge Design – Key Technical Considerations

BASE CONCEPT

BRIDGE DESIGN

Cost

$ 2 959 584

Cost

$ 4 102 447*

Features

No Public Involvement, Meets the Minimum Standard Established by the Site Plan Conditions

Features

Design is the Result of an Extensive Public Design Process

Reuses Existing Piers at Stafford Place, No Planters or Benches at the Street Level

New Piers, Planters + Benches Create Place Making at the Street Level

Glass Enclosed Walkway

Glass Enclosed Walkway, Benches Mid-Span Provide Area to Pause and Rest

Maintains 1:12 Ramp into Stafford Place + Handrails

Eliminates Ramp into Stafford Provides Universal Accessibility

Space is Ventilated + Unconditioned

* Cost is Established on a Not to Exceed Basis and Includes a 15% Contingency. Cost Overruns will be Borne by the Developer.

20

Space is Heated and Air Conditioned Provides Memorable Moment, Exceeds Community Expectations for the Project, Provides Redevelopment Benefits for Neighboring Land Owners

Walkway Comparison – Budget + Features

Pedestrian Bridge Pre Closure Messaging Locations 1

Top of metro escalators

2

Bottom of interior escalators

1

2 3

3

North entry to the

4

South1entry to the 9th St. bridge

5

9th

St. bridge

Interior walkway between 9th St. and Wilson Blvd. bridges

6

North entry to the Wilson Blvd. bridge

7

South entry to the Wilson Blvd. bridge

8

Mall interior before Wilson Blvd. bridge (near former FYE space)

4

5 6

7

8

21

ICEPLEX

Wayfinding – Public Messaging

CONSTRUCTION MEANS + METHODS ARE BEING ESTABLISHED FOR:  Ceiling Treatment|Relationship of Steel to the Ceiling|Acoustics|Reveal Condition  Supply Air and Return Air Detail  Lighting (Inside|Outside|Concrete Piers, etc.)  Connection between Piers and Underside of Bridge  Finishes|Material Selections|Colors|Sample Board, etc.  Final Pattern of the Zinc Panels  Connection Condition at Each Building

Standing Seam Zinc

22

Structural Glass Support System

Concrete Support Piers

Development – Design Details

CONSTRUCTION MILESTONES  Bridge Closes Mid-October 2016  Bridge + Mall Demo Begin Late October 2016  Bridge Construction Starts 01 March 2017  Mall + Bridge Open 13 September 2018 NEXT STEPS  Share Designs with the Community (October Event Tentatively Planned)

   

23

Demolition of Existing Bridge Compete Construction Documents Bidding + Permitting Construction 2017-2018

Milestones – Next Steps