Construction, Fire, Mechanical, Electrical, and ... AWS

Report 0 Downloads 70 Views
    

Construction, Fire, Mechanical, Electrical, and Plumbing

Council Work Session | March 06, 2018

City of Arlington, Texas

• • • • • • • • •

Benbrook Kennedale Fort Worth Hurst Euless Bedford Southlake Dallas Irving

• • • • • •    

Carrolton Richardson Garland Plano Trophy Club West Lake Grand Prairie Cedar Hill University Park Farmers Branch

1. 2. 3. 4.

International Residential Code International Building Code International Energy Conservation International Existing Building Code

 Carbon monoxide alarms now require connection to the

house wiring system with battery backup.  In existing buildings - exterior work such as roofing,

windows, doors, and decks and porch additions no longer trigger the carbon monoxide alarm provisions.  Dwelling Unit Requires Carbon Monoxide Alarms if:  Attached garage; or  Contains fuel-fired appliance.

 Combination smoke and carbon monoxide alarms are allowed



Storm Shelters required in: 



educational structures

Local amendment – to apply only to new educational buildings



Exempted:  When the building housing the facility or occupancy type meets the

shelter design criteria in the ICC 500 manual  When the campus has an existing storm shelter that can

accommodate the occupancy



Envelope leakage and duct leakage testing are required



Duct and envelope testing requirements are more stringent than in the 2009



Improved window performance; .35 U factor & .25 SHGC



Wall/ceiling insulation; R20 walls & R38 ceiling



Efficient lighting requirement has gone from 50% to 75%



Whole house mechanical ventilation is required



R3 hot water piping insulation is required:      

For pipes ¾” and larger Pipes outside of conditioned space Pipes under a floor slab Supply and return piping in a recirculation system Buried pipe Piping from a water heater to a manifold system



Commissioning- HVAC, water heating, lighting and envelope commissioning by 3rd party



HVAC – new equipment efficiencies, additional requirements for ventilation systems and lighting



Water heating – improved efficiency and controls



Lighting – occupancy sensors and daylighting controls



Additional Efficiency Packages – requires choosing 1 of 6 above code options for compliance

Comparing a new house under the 2009 IECC to the 2015 IECC: 



The average homeowner in our climate zone (3A) will save: 

$385.36 per year in energy costs (or a cost savings of 22.1%)



$5,517.37 or more will be the average life-cycle (30 years) cost savings, adjusted with anticipated inflation rate

The average increase in construction costs: 

For a slab-on-grade house is $2,209.52, which will increase the average mortgage by $69.37/year



It will take 3.7 years to pay back the extra cost of construction (cost increase vs energy savings)





International Existing Building Code (IEBC) is a new stand alone document to address the redevelopment of existing structures IEBC provides alternative approaches to achieve compliance on repairs, alterations, change of occupancy, additions and relocations of existing structures.

1. International Fire Code



Fire Safety and Evacuation Plans 

Required for Group A, other than church with OL < 2,000



Buildings with both Group A and atrium



Group B, F, M with OL >500, or >100 on floor other than LED



Groups R-1, R-4, R-2 college/univ dormitories



High-rise



Mall buildings >50,000 ft2



Occupant evacuation elevators





Definition Clarification of Combustible Materials in Plenums Abandoned wiring is deemed to be storage  It must be removed in the accessible areas  Unless the wiring is tagged for future use

 Storage is prohibited  It must be removed



Co2 Systems for Beverage Dispensing within enclosed spaces



Accidental releases can fill an enclosed space 

Odorless and colorless gas that is heavier than air



Systems >100 pounds (»9.5 gallons) are regulated



Operational permit are required for tanks >100 lbs



Protection required  

Continuous gas detection system, or Mechanical ventilation

External fill connections

 

These requirements are designed to be installed when a system is placed inside an enclosed structure.

1. 2015 International Mechanical Code 2. 2017 National Electrical Code 3. 2015 International Plumbing Code & 2015 International Fuel Gas Code

 No new significant changes to the IMC  Changes are primarily to clarify or modify existing standards  Most construction projects should see little to no impact  Local amendments do not add any new regulations. Only clarify or add additional methods for compliance.

 The 2017 National Electrical Code was adopted as the state code effective September 15, 2017.  Arc-fault circuit interrupters are now required in guest rooms and suites in hotels and motels.  Meeting rooms of 1,000 sq. ft or less must have wall receptacles spaced approximately every 12 feet and at least one floor receptacle.  Tamper resistant receptacles now required in preschools and schools, business and professional offices, corridors, and gymnasiums.  Used equipment that is to be relocated must be certified through a third-party testing agency.

 Public restrooms are not required in quick-service occupancies such as takeout-only restaurants, dry cleaners and ATM lobbies when public area is 300 sq. ft. or less.  Local amendment exempts drinking fountains when occupant load is 30 or less. (IPC states 15 or less.)  Drain pans are not required under replacement water heaters when a drain pan was not previously required.