CRRMA BOARD PRESENTATION OLD HUECO TANKS ROAD PROJECT David Head, PE September 14, 2016
Old Hueco Tanks Road Project
• • • •
AGENDA Project Purpose, Location and Scope Timeline Bids Received Requested Board Action
2
Project Purpose • The Old Hueco Tanks Road Project is one of the 2013 El Paso County Comprehensive Mobility Plan projects, which was to be let in 2016 • Project budget comes from the El Paso County Vehicle Registration Fee bond proceeds ($72M Bond Issuance), State and Federal Funds ($9.9M Advance Funding Agreement) • This is a jointly developed project: TxDOT completed design, Socorro provided right of way and CRRMA managed construction, construction engineering, inspection and testing • TxDOT’s completed designs were advertised and let, per Board direction, and the CRRMA now seeks to award the contract and manage construction 3
Project Location
4
Project Location
5
Project Scope • 4 lane divided roadway with raised median • Concrete pavement & curb, 6 ft. bike Lane, sidewalks, landscaping, continuous illumination, storm drainage, signing and striping.
6
Project Scope • Role of TxDOT Provide completed design plans and design services during construction
• Role of the County Provide construction funding for the project Provide Owner decisions/guidance for project issues that need resolution and/or input
• Role of the CRRMA Prepare and let project for construction bids Provide construction management services consisting of oversight, engineering testing, inspection and record keeping
7
Procurement Timeline
• • • • • •
May 11, 2016 – Board Authorizes Project to be Advertised for Bid July 31, 2016 – Advertised for Bid August 19, 2016 – Q&A Posted to CRRMA Website August 25, 2016 – Bids Opened September 14, 2016 – CRRMA Board Awards Project (proposed) September 14, 2016 – CRRMA Board Authorizes Executive Director to begin negotiations (proposed) • September 14, 2016 – CRRMA Board Authorizes Executive Director to issue a Notice to Proceed (proposed)
8
Construction Timeline
• • • • •
Contractor possible start in November 2016 240 days to complete (approx. 12 months) 5 Day work week Weather days Possible completion in Fall 2018
9
Bid Results
Engineers Probable Cost of Construction - $9.7M 10
Requested Board Action
MOTION to approve a CRRMA Board Resolution to: • Select International Eagle Enterprises, Inc. as the lowest responsive bidder for the Old Hueco Tanks Road Project; and • Authorize the Executive Director to negotiate and execute a contract with International Eagle Enterprises, Inc. for the Old Hueco Tanks Road Project.
11
Questions?