September 30, 2015 Dave Kirschner, P.E. Arlington County Department of Environmental Services

Crystal City Redevelopment

2

Crystal City Sector Plan - Transportation • Sector Plan calls for phased development of Street Network • Streets Program organized into 5 phases

3

Crystal City Area Projects

4

Completed Projects – Crystal Drive Phase 1

5

Completed Projects – Crystal Drive Phase 1

6

Completed Projects – Crystal Drive Phase 1

7

Completed Projects – Crystal Drive Phase 1

8

Completed Projects – Crystal Drive Phase 2

9

Completed Projects – Crystal Drive Phase 2

10

Projects - S Eads St Pilot Program

11

Projects - S Eads St Pilot Program

Slide of options from charette

Projects - S Eads St Pilot Program

Projects - S Eads St Pilot Program

Projects - S Eads St Pilot Program

In Progress – Crystal City Multimodal Center Convert S Bell St to two-way operation

New street lighting

Repair and replace sidewalks throughout Rebuild Intersection of 18th St S & S Bell St

Concrete paving through bus bays

New street trees

New bus shelters

16

In Progress – ART House Streetscape • Improving streetscape on S Eads St and Route 1 in partnership with the ART House project • New bike lanes, street lighting, sidewalks, and landscaping • Status: Under Construction

17

South Clark Street Demolition (CC09) • South Clark Street between 12th St S and 20th St S is to be removed • New space created for development and re-use • Status: 90% Design Plans in October

18

15th St S/S Clark St Extension (CC08) • South Clark Street to be realigned to meet 15th St S at 4-way intersection • Will create 15th St S “Garden Park” envisioned in Sector Plan • Status: 60% Design Plans in October

19

27th St S Two-way Conversion (CC05) • Conversion from one-way to two-way operation of 27th St S and part of Crystal Drive • Includes new streetscape with street lighting, sidewalks, and landscaping • Status: Design complete, awaiting easements

20

18th St S Realignment (CC10) • • • •

Rebuild streetscape along 18th St S between S Bell St and Crystal Dr Realign intersection to meet with new 18th St S west of S Bell St New bike lanes, street lighting, sidewalks, and landscaping Status: Concept Design

21

18th St S Streetscape (CC20) • Rebuild intersection of 18th St S and S Fern St • Excessively large, fatal collision • Rebuild 18th St S between S Fern St and S Eads St • Protected bike lanes, new street lighting, new landscaping • Status: Concept Design

22

Rt 233 Viaduct Ramp Removal & Ped Connection (CC15/CC20)

• Remove off-ramp from Route 233 to NB Crystal Drive • Create new space for development • Rebuild streetscape at pedestrian-scale • Retain pedestrian connection from Crystal Drive to National Airport • Add pedestrian connection across Route 1 from National Airport • Status: Concept Design

23

Rt 233 Viaduct Ramp Removal & Ped Connection (CC15/CC20)

24

12th St S Streetscape (CC16) • Rebuild 12th St S between S Fern St and S Eads St • New sidewalks, new street lighting, new landscaping • Design to accommodate future alignment of CCPY Transit Lanes • Status: Concept Design

25

23rd St S between S Eads St and Crystal Dr (CC11) • Rebuild 23th St S between S Eads St and Crystal Dr • Shift northbound lanes south to allow for future development • Rebuild intersections of 23rd St S and Eads, US 1, and Clark Streets • Status: Planning

26

Crystal Drive Two-Way Conversion Phase 4 (CC06) • Convert Crystal Drive to two-way operation between 27th St S and US1 • Status: Planning