Edan Presentation - PV Grid

Report 7 Downloads 113 Views
PV GRID – WP3 Technical Solutions for PV Integration Existing Regulatory Barriers to Grid integration Athens, July 4th, 2013

1

Agenda

• DG and PV integration in the distribution network in Italy  Connection activities  Challenges for DSOs

• Identification of the relevant technical solutions in Italy • Barriers      

RES-Curtailment Access to advanced inverter capabilities Storage use Self consumption Control of passive loads by DSOs Information exchange for Demand Response

04/07/2013

2

ENEL DISTRIBUZIONE – DG CONNECTED Up to May 2013 24,5 Non-RES Hydro Bio & Waste

Connected Power (GW), Yearly Data

10,0

2,0 1,0 2,4

4,7 2,7

1,6

1,7

2008

2009

0,8

0,7

Solar 15,5

2007

2010

2011

2012

Connected Power (GW), Cumulative Data Wind

3,6

Connections May 2013 [GW]

Cumulative connections (No.): 488.100

2013

23,8

24,5

2012

2013

19

9,1

2,4

3,1

Ante 2007

2007

6,4

4,7

2008

2009

2010

2011

Most DG is connected to MV network 04/07/2013

3

ENEL DISTRIBUZIONE – REVERSE ENERGY FLOWS HV/MV Substations experiencing “upside-down” operation

04/07/2013

4

ENEL DISTRIBUZIONE – LOAD / DG BALANCE Matching generation and load in MV-LV networks 9.000 10.000 8.000 9.000

50.000

7.000 8.000

40.000

7.000 6.000 6.000 5.000 5.000 4.000 4.000

35.000

3.000 3.000

15.000

2.000 2.000 1.000 1.000 0

10.000

-

45.000

30.000 25.000 20.000

5.000 0 Lombardia

Puglia

Sicilia

Totale nazionale

LOM PUB Potenza richiesta (in corso) suDG rete MT-BT Connected to MV-LV Network Potenza attivata su rete MT-BT Min MV+LV Load (2007) Assorbimento massimo MT-BT (anno 2007) Max MV+LV Load (2007) Assorbimento minimo MT-BT (anno 2007)

Ongoing DG Requests

04/07/2013

5

ENEL DISTRIBUZIONE – INTERFACE WITH HV GRID / 1 Net energy flows: Distribution network as seen by a TSO July 2010

MW

2012

40.000

30.000

20.000

10.000

0

Weekdays

Saturday

Sunday 04/07/2013

6

-200 00:15 01:15 02:15 03:15 04:15 05:15 06:15 07:15 08:15 09:15 10:15 11:15 12:15 13:15 14:15 15:15 16:15 17:15 18:15 19:15 20:15 21:15 22:15 23:15 00:15 01:15 02:15 03:15 04:15 05:15 06:15 07:15 08:15 09:15 10:15 11:15 12:15 13:15 14:15 15:15 16:15 17:15 18:15 19:15 20:15 21:15 22:15 23:15 00:15 01:15 02:15 03:15 04:15 05:15 06:15 07:15 08:15 09:15 10:15 11:15 12:15 13:15 14:15 15:15 16:15 17:15 18:15 19:15 20:15 21:15 22:15 23:15

ENEL DISTRIBUZIONE – INTERFACE WITH HV GRID / 2

Net energy flows: Distribution network as seen by a TSO MW The Puglia Case

Weekdays

May

2010

Saturday 04/07/2013

2011 2012

2.000

1.800

1.600

1.400

1.200

1.000

800

600

400

200

0

Sunday 7

ENEL DISTRIBUZIONE – INTERFACE WITH HV GRID / 3 Net energy flows: Distribution network as seen by a TSO

HV/MV Substation “Ginosa” (Puglia) 20

10

0

-10

-20

MW - Lunedì, 30 Agosto 2010 MW - Lunedì, 29 Agosto 2011

-30

MW - Lunedì, 27 Agosto 2012

04/07/2013

23.00

22.00

21.00

20.00

19.00

18.00

17.00

16.00

15.00

14.00

13.00

12.00

11.00

10.00

09.00

08.00

07.00

06.00

05.00

04.00

03.00

02.00

01.00

00.00

-40

8

MAIN CHALLENGES: VOLTAGE DEVIATIONS

• Slow Voltage Deviations Refer to the voltages in any given point in different load-generation conditions

• Fast Voltage Deviations Refer to the voltage in the connection point of new DG in case of instantaneous disconnection

• Voltage Values In the most critical condition, voltage values in any point of the network must be kept within standards

04/07/2013

9

MAIN CHALLENGES: CONGESTION

• Load Values In the most critical condition, load must be kept within standards

04/07/2013

10

RELEVANT SOLUTIONS – THE CATALOGUE SCADA + direct load control SCADA + PV inverter control (Q and P)

Demand response by local price signals

Network Reconfiguration On Load Tap Changer for MV/LV transformer

Wide area voltage control Advanced Closed-Loop Operation

Prosumer storage Reactive power control by PV inverter Q(U) Q(P)

Active power control by PV inverter P(U)

Static VAr Control

Self consumption by tariff incentives Curtailment of power feed in at PCC

Network Reinforcement

DSO storage Advanced voltage control for HV/MV transformer

Booster Transformer Demand response by market price signals 04/07/2013

11

RELEVANT SOLUTIONS FOR ITALY / 1

DSO-SIDE SOLUTIONS: • Network Reconfiguration • Network Reinforcement • On Load Tap Changer for MV/LV transformer • Advanced voltage control for HV/MV transformer • Static VAr Control • DSO storage • Advanced Closed-Loop Operation.

Complementary solutions (no “killer application”) 04/07/2013

12

RELEVANT SOLUTIONS FOR ITALY / 2

PV-SIDE SOLUTIONS: • Reactive power control by PV inverter Q(U) Q(P) • Active power control by PV inverter P(U) • Curtailment of power feed in at PCC • Prosumer storage.

Less limitations usually imply less effectiveness Solutions must be chosen with graduality 04/07/2013

13

RELEVANT SOLUTIONS FOR ITALY / 3

INTERACTIVE SOLUTIONS: • SCADA + PV inverter control (Q and P) • SCADA + direct load control • Wide area voltage control • Demand response by local price signals.

Solutions are complex and make sense only in case of massive deployment 04/07/2013

14

NOT RELEVANT SOLUTIONS FOR ITALY

• Booster Transformer • Demand response by market price signals • Self consumption by tariff incentives.

Can inevitably help in very limited circumstances 04/07/2013

15

SOLUTIONS’ EVALUATION Qualitative “holistic” evaluation for MV and LV grids

04/07/2013

16

MAIN REGULATORY BARRIERS / 1 RES-Curtailment

PROBLEM STATEMENT: Curtailment only allowed for transmission system security reasons, not in case of local voltage or load constraints (Priority Dispatch). No conditioned connection allowed -> connection solutions become more complicated SOLUTION AFFECTED: All solution implying limitations of RES-injection.

RECOMMENDATION: Curtailment of RES must be allowed to DSOs in National Regulation. Boundary conditions must be defined in technical standards (Transparency and No Discrimination). 04/07/2013

17

MAIN REGULATORY BARRIERS / 2 Self consumption

PROBLEM STATEMENT: No regulation exists prescribing self-consumption for distributed generation. Economical incentives have been defined for self-consumption, but they apply only to new installations and their effect cannot be granted, as it depends on individual behaviors of operators, on voluntary basis. SOLUTION AFFECTED: All solution implying self limitation of RES-injection. RECOMMENDATION: Define (reasonable) self-consumption obligations for newly-connected RES, in order to ensure transparent and non-discriminatory planning criteria. 04/07/2013

18

MAIN REGULATORY BARRIERS / 3 Storage use

PROBLEM STATEMENT: Present Regulation does not foresee DSOs making use of a storage system and does not provide any instruction about how storage energy must be treated within the electrical market structure. SOLUTION AFFECTED: All solution implying a DSO-owned storage. RECOMMENDATION: Roles, rights and limitations of DSOs in the use of storage must be clearly defined by NRA. It can be reasonably expected that local security-related capabilities should be made available to DSO.

04/07/2013

19

MAIN REGULATORY BARRIERS / 4 Access to advanced inverter capabilities

PROBLEM STATEMENT: Some Regulations do not allow DSOs to make use of available capabilities of inverters, even though they have already been included among mandatory requirements. SOLUTION AFFECTED: All solution implying control by DSO on PV-inverters. RECOMMENDATION: Access to inverters and control over their capabilities must be granted to DSOs. Boundary conditions must be defined in technical standards (Transparency and No Discrimination).

04/07/2013

20

Thank you for your attention Riccardo Lama Standardization, Working Practices [email protected]

Disclaimer: The sole responsibility for the content of this presentation lies with the authors. It does not necessarily reflect the opinion of the European Union. Neither the EACI nor the European Commission are responsible for any use that may be made of the information contained therein.