EPA's Draft Air Transport and Utility MACT Rules- The Impending ...

Report 2 Downloads 30 Views
Presentation to Lee County Zoning Board of Appeals On Behalf of Local Landowners and Hamilton Township Tom Hewson John Stamberg P.E. Principal Energy Ventures Analysis Inc Arlington Virginia 703-276-8900 November 27, 2011

Decommissioning Costs and Risks  Why should Lee County care?  Paul Gipe estimated that there over 14,000 wind turbines in California alone that were

abandoned by 1997. Abandoned wind turbines have/will continue to adversely affect local property values and character.

 Caithness Windfarm Information Forum (www.caithnesswindfarms.co.uk) tracks wind

turbine accident data that can be confirmed through press reports or official releases. They have documented (through 9/2012) 249 turbine blade failure incidents, 195 turbine fires and 130 structural failures– that can lead to premature unit decommissioning.

 Wind facilities are often developed as limited liability corporations. At the end of the

project life, the LLC may have no equity remaining to fund decommissioning cost.

 Pre-funding future decommissioning costs has become a common requirement for wind

project permitting.  

Intent to have cost paid by wind developer who financially benefits from wind project operation Different approaches available to assign decommissioning cost and risk between wind project operators and local community

Decommissioning Risk

Abandoned Wind Turbines at Kamora Wind Farm (HI)

Decommissioning Risk

130 documented cases of structural failure such this January 2008 accident in Cumbria UK

Decommissioning Risk

Wind turbine foundation failure

Decommissioning Risk

195 Documented Wind turbine fires such as this turbine in Germany. Can be caused by equipment failure or lightning.

Decommission Planning Decommissioning Plan Components  Defining Scope of Work:  Dismantling wind turbines and met towers  Removing turbine foundations (to what depth?) and land reclamation  Removing crane pads  Substation removal (transformers, equipment, foundations, etc..)  O&M building removal  Access Roads- Retain or remove?  Collection system electrical system- Abandon underground lines or remove?  Trigger decommissioning as individual turbines cease operation or wait until entire project is shutdown

Decommission Financing  Financing cost approaches  Project performance bond for a defined scope of work with an approved

highly rated bonding company--- Assigns 100% of project risk to project bonding agency

 Financial bond at a preset amount to be sufficient to cover anticipated

decommissioning costs– Leaves future cost escalation and scrap value risks to local community and property owners

 Other financial assurance – Assigns full financial risks to local community

and property owners if financial assurance entity fails

Decommissioning Costs

Decommissioning Costs Table 1. Decommissioning Cost Known To Wind Turbine Contractors and Items with Insufficient Details to Make Independent Demolition Estimates

Decommissioning Costs Table 2 Net Scrap Salvage Value Dixon Iron and Metal 7/20/12 Verbal Scrap Amounts I. Turbine Metal

Quote

(4)

Per Turbine Received Scrap Value

Truck Delivery

Cost to Disassemble

(5)

(6)

$400 (2 trips)

$1,000

$2,305

$2,895

$400 (2 trips) $200 (1 trip)

Nil

$2,305

$3,070

Nil

$1,153

$6,147

Cost

or Torch

Cost to Load at Wind Farm Crew B-12N

(7)

Net Scrap Value

(1),(3)

A. Rotor 60 Tons 1. Hub Iron/Steel 2. Blades

40 tons

$165/ton

$6,600

20 tons

-

-

35 tons

$165/ton

$5,775

35 tons

$7,500/each

$7,500

(1),(2)

B. Nacelle 82 Tons 1. Gear Box, Transmission, Brakes 2. Generator 3. Non-Metal C. Tower/Bolts 1. Tower

12 tons

-

-

205 tons

$165/ton

$33,825

$4,000 (10 trips)

$5,000

$11,525

$13,300

280 tons

$53,700

($5,000)

($6,000)

($17,288)

$25,412

24,360 tons

$4,671,900

($435,000)

($522,000)

($1,504,056)

$2,210,844

$3,276 at

$66 (3 trips)

Nil

$768

$2,442

($5,742)

Nil

($66,816)

$212,454

$800 (4 trips)

Nil

($2,305)

$59,294

-

-

-

-

$347,412

($6,542)

Nil

($69,121)

$271,748

$5,019,312

($441,542)

($522,000)

($1,573,177)

$2,482,592

(2)

D. Subtotal per Turbine E. Subtotal per 87 Turbines II. Transformers/Miscellaneous A. Turbine Transformer 1. Sheet Steel 2. Core Steel 3. Core Copper 4. Oil

7.48 tons 3.1 tons 1.6 tons 1.6 tons

D. Miscellaneous (in above Section I) E. Subtotal per 87 Turbines III. Total Salvage Value

$0.26/#

(9)

1.15 tons

B. Subtotal per 87 Turbines C. Master Primary Transformer (MPT)

6.3 tons

$285,012 120 tons

(10)

$62,400 $0.26/# -

Decommissioning Costs Table 3 Non-Metal Disposal Costs Item

Amount

1.

Blades

20 tons

2.

Nacelle Non-Metal

12 tons

3.

Transformer and Transmission Oils

500 gal

4. 5.

Landfill Dumping Cost

Trucking

Cost To Load

$200 (1 trip)

$51.00 3/day (Crew B-10-U)

$900

(

$5,542.50

$1,452.60 (Crew Q-20)

$200 (1 trip)

$51.00 3/day (Crew B-10-U)

$450

$2,153.60

$1,200 = 12 barrels @ $100/barrel

$50.00

Nil

$450

$1,700.00

Cost per Turbine

$7,024.10

$450

$102

$1,800

$9,376.10

Cost for 87 Turbines

$611,097

$39,150

$8,874

$156,600

$815,721

Lee County landfill charge at $900 per 20 ton load

Site Process Cost $4,371.50/3 blades (Crew B-7)

Total Cost

Decommissioning Costs Table 4- Foundation Removal and Land Reclamation

Decommissioning Costs

Table 5 --Road Removal Costs

Decommissioning Risk Future Labor Cost Escalation Scrap Market Value Changes Landfill Disposal Costs Land Acquisition Costs Landfill Regulation Changes Heavy Equipment Rental Costs Fuel Costs

Presentation to Lee County Zoning Board of Appeals On Behalf of Local Landowners and Hamilton Township Tom Hewson John Stamberg P.E. Principal Energy Ventures Analysis Inc Arlington Virginia 703-276-8900 November 27, 2011