Epstein Presentation at Vendor Outreach Fair - Prestage Farms

Report 6 Downloads 17 Views
Prestage Farms Subcontractor and Vendor Outreach Fair

Architecture Interiors Engineering Construction www.epsteinglobal.com

December 13, 2016

Agenda 

Epstein’s Role



Project Description



Project Location



Building/Site



Project Schedule (Key Dates)



Design Milestones



Major Bid Packages



Pre-qualification Process



Procurement Documents



Contract Structure



Insurance Requirements



Subcontractor Selection Process



Questions and Answers



Breakout Sessions

Epstein’s Role 



Design – Builder Construction Manager



Architectural and Engineering Design (Building and Infrastructure)



Process Equipment Systems Design, Fabrication and installation (by Epstein and Prestage Farms)

3

Project Description 

The Prestage Foods project includes a new 700,000+ square feet pork-processing facility on a 160-acre site on the corner of Highway 17 and 320th Street in Eagle Grove, Iowa.



The facility will initially process 10,000 hogs a day on a single shift, eventually increasing to 20,000 hogs a day when a second shift is added.



The proposed facility is expected to be slab on- grade, consisting of frost depth footings, precast wall panels/insulated metal panels, and metal bar joists for the roof. 4

Project Description (continued)



Rendering Building 20,000 sf  Precast Structure  Air Scrubbers 



Waste Water Pre-treatment Building 10,000 sf  Precast Structure  FEB Tank  Multi-stage DAFs 

5

Project Location



New Pork Processing Plant in Eagle Grove, Iowa

6

Project Site

7

Project Site Intersection

8

Site Plan

9

Overall First Floor Plan

10

Overall First Floor Plan with Equipment

11

Bird’s Eye View

12

1. Civil 

Earthwork and Grading



Soil Stabilization with Concrete



Geopiers



Paving



Site Utilities



Wells / Water treatment

13

2. Wastewater Treatment



Superstructure will be precast concrete



Precast exterior wall



Roofing 60 mil single ply PVC



Space ventilated and heated



Mechanical, Plumbing, and Electrical

14

3. Rendering 

The Superstructure for Rendering will be precast concrete.



Exterior wall at Rendering will be structural precast



Roofing 60 mil single ply PVC



Heated and Ventilated with Air Scrubbers

15

4. Livestock Unloading / Holding Pen 

Exposed Structural Steel shall be galvanized



The Superstructure will consist of a Preengineered Metal Building Frame



Precast Concrete at Livestock Unloading and pens and Insulated Precast concrete at Barn Offices



Roofing will be a Standing Seam Metal Roofing Assembly with insulation and galvanized metal liner

16

5. CO2 Stunning



Waterproofed Concrete CO2 Stunner Pit



Superstructure will be Structural Steel



The exterior wall shall be Precast Concrete



Roofing will be White, 60 mil TPO Roofing Assembly, Fully Adhered System



Mechanical, Plumbing and Electrical

17

6. Wet Kill / Dry Kill



The Superstructure will be Precast Concrete



Walls will be Precast Concrete



Roofing will be White, 60 mil TPO Roofing Assembly, Fully Adhered System



Mechanical , Plumbing and Electrical

18

7. Snap Chill / Equilibrium Bay



The Snap Chill Superstructure will be Structural Steel



The Equilibrium Bay Superstructure will be Precast Concrete



The Exterior Wall shall be white IMP



Roofing will be White, 60 mil TPO Roofing Assembly, Fully Adhered System



Mechanical , Plumbing and Electrical 19

8. Cut Floor 

The Superstructure will be Structural Steel



Columns will be Precast



Floor slabs at Cut Floor will be 8” thick concrete with “chemical resistant” finish.



Box Shop Mezzanine



Roofing will be White, 60 mil TPO Roofing Assembly, Fully Adhered System



Interstitial Space for MEP Systems 20

9. Distribution 

The Superstructure will be Structural Steel



The Battery Room Floor shall have an Acid Resistant Epoxy Finish



Exterior wall will be 6” White IMP



Roofing will be White, 60 mil TPO Roofing Assembly, Fully Adhered System



Fire Protection (Wet System and Dry System)



Mechanical, Plumbing, Electrical and Low Voltage 21

Office

22

11. Office 

The Superstructure will be Structural Steel



Exterior wall will be Insulated Precast Concrete.



Roofing will be White, 60 mil TPO Roofing Assembly, Fully Adhered System



Mechanical, Plumbing, Electrical and Low Voltage

23

Project Schedule (Key Dates)



Breaking Ground

March 2017



Enclosed Building

December 2017



Process Installation Start January 2018



Substantial Completion

October 2018

24

Design Milestones 

Earthwork

January 2017



Geopiers



Foundations

February 2017



Structural

March 2017



Core and Shell MEP

May 2017



Process MEP

June 2017



Core and Shell

May 2017

(Civil/Structural)

January 2017

25

Major Bid Packages

Bid Package

Package Title

Est Release Date

Est Award Date

Contract Type

Est Pkg Size

1

Geopiers

January 2017

February 2017

LS - Design / Build

$2 Million

2

Earthwork - Soil Improvement & Rough Grading

January 2017

February 2017

LS - Hard Bid

$4 Million

3

Pits - Stun & WWT

February 2017

March 2017

LS - Hard Bid

$700k

4

Precast

March 2017

April 2017

LS - Design / Build

$5 Million

5

Steel

March 2017

April 2017

LS - Hard Bid

$9 Million

6

Foundations

February 2017

March 2017

LS - Hard Bid

$3 Million

7

Site Utilities

January 2017

February 2017

LS - Hard Bid

$6 Million

8

Underground Plumbing

February 2017

March 2017

LS - Hard Bid

$3 Million

9

Roofing

May 2017

April 2017

LS - Hard Bid

$3 Million

10

Slab On Grade

May 2017

April 2017

LS - Hard Bid

$7 Million

11

Barn Building

May 2017

April 2017

LS - Hard Bid

$2 Million

26

Major Bid Packages (continued)

Bid Package

Package Title

Est Release Date

Est Award Date

Contract Type

12

Elevators

May 2017

April 2017

LS - Hard Bid

$300k

13

IMP

May 2017

April 2017

LS - Design / Build

$6 Million

14

Glazing

May 2017

April 2017

LS - Hard Bid

$700k

15

Masonry

May 2017

April 2017

LS - Hard Bid

$1 Million

16

Asphalt Paving

May 2017

April 2017

LS - Hard Bid

$4 Million

17

Concrete Paving & Flatwork

May 2017

April 2017

LS - Hard Bid

$2 Million

18

Shell Plumbing

May 2017

April 2017

LS - Hard Bid

$11 Million

19

Shell Electrical

May 2017

April 2017

LS - Hard Bid

$10 Million

20

Fire Protection

May 2017

April 2017

LS - Hard Bid

$1.5 Million

21

Refrigeration Electrical

May 2017

April 2017

LS - Hard Bid

$4 Million

22

Dock Equipment & Levelers

May 2017

April 2017

LS - Design / Build

$500k

23

Doors and Hardware (not in IMP or Glazing)

May 2017

April 2017

LS - Hard Bid

Est Pkg Size

$300k

27

Major Bid Packages (continued)

Bid Package

Package Title

Est Release Date

Est Award Date

Contract Type

Bid Package

24

Overhead Doors

May 2017

April 2017

LS - Hard Bid

$200k

25

Industrial Flooring

May 2017

April 2017

LS - Hard Bid

$2.5 Million

26

Miscellaneous Metals

June 2017

July 2017

LS - Hard Bid

$1 Million

27

Process Electrical

June 2017

July 2017

LS - Design / Build

$9 Million

28

Process Mechanical & Millwrighting

June 2017

July 2017

LS - Hard Bid

$10 Million

29

Interiors

June 2017

July 2017

LS - Hard Bid

$2.5 Million

30

Fine Grading & Landscaping

June 2017

July 2017

LS - Design / Build

$300k

31

Fencing

June 2017

July 2017

LS - Hard Bid

$300k

32

Industrial Painting

June 2017

July 2017

LS - Hard Bid

$800 k

28

Prequalification / Prerequisites for Subcontractors 

All interested subcontractors are invited to visit the public project website: www.prestagefoodsofiowa.com where you can find the “Prequalification Checklist” and the “Vendor/Supplier RSVP”



Contractors that would like the opportunity to bid on the project are required to fill out the Prequalification Checklist to be considered.



If a contractor meets the requirements listed therein, then they will receive a more detailed prequalification form



Contact information for Epstein is: [email protected] www.epsteinglobal.com\prestagevendorinfo

29

Prequalification / Prerequisites for Subcontractors (continued) 

Once this form is received, “selected” contractors and subcontractors will receive an Invitation to Bid.



If a contractor or subcontractor does NOT meet the requirements listed in the Prequalification Checklist, then they will receive an Alternative Subcontractor form in order to be placed in a database of potential subcontractors.



Materials & Equipment vendors as well as operational goods and services providers do NOT need to fill out a Prequalification Checklist. These vendors and service providers need only fill out the RSVP form to be entered into a database of potential providers. 30

Procurement Documents Building Elements Bid Packages

     

Invitation to Bid Schedule A – Bid Tabulation Schedule B – Scope of Work Schedule C – Drawings Schedule D – Specifications Schedule E – Construction Schedule

31

Contractual Documents Subcontract

    

Standard subcontract agreement Schedule G – Epstein Safety Schedule H – Insurance Requirements Schedule I – Equal Employment Opportunity Schedule J – Invoicing Procedures

32

Contractual Documents Purchase Order (PO)    

   

PO Coversheet PO Subcontract Agreement PO Scope of Work (taken from vendor proposal) Schedule B – Scope of Work and Vendor Special Conditions Schedule G – Epstein Safety Manual Schedule H – Insurance Requirements Schedule I – Equal Employment Opportunity Schedule J – Invoicing Procedures

33

Contractual Documents Simplified Purchase Order (Simplified PO)    

PO Coversheet PO simplified terms and conditions rider PO scope of work (taken from vendor proposal) Schedule J – Invoicing Procedures

34

Questions and Answers

35

Breakout Information Sessions

    

General Building Trades Mechanical, Electrical and Plumbing Information Technology and Communications Materials and Equipment Vendors Operational Goods and Service Providers

36

Subcontractor and Vendor Outreach Fair

37