GDOT PowerPoint Template - 2015 AWS

Report 1 Downloads 88 Views
Emergency Response Clayton Bennett, PE State Bridge Inspection Engineer, GDOT [email protected]

Procedure 1. Determine if damage to bridge warrants an emergency. 2.Notify Management of the bridge Damage. 3. Director of Finance issues Emergency P.I. Number. 4. Develop Emergency Contract. 5. Send Emergency Contract to a minimum of three Contractors. 6. Allow the Contractor 4 to 7 days to send in Bids. 7. Award contract the same day bids are received.

Contract

Emergency Response Clayton Bennett, PE State Bridge Inspection Engineer, GDOT [email protected]