green mountain power kingdom community ...

Report 1 Downloads 84 Views
Erosion Prevention and Sediment Control Plan  Narrative for Individual Discharge Permit for  Stormwater Runoff from Construction Sites 

GREEN MOUNTAIN POWER  KINGDOM COMMUNITY WIND PROJECT       

Lowell, Vermont 

   

 

Prepared for 

     

  Prepared by 

Green Mountain Power Corporation    Vanasse Hangen Brustlin, Inc.  

    7056 U.S. Route 7      North Ferrisburgh, VT 05473                                                                          November 12, 2010

GREEN MOUNTAIN POWER CORPORATION / KINGDOM COMMUNITY WIND EROSION PREVENTION AND SEDIMENT CONTROL PLAN NARRATIVE

i

Table of Contents 

  1.0  Introduction ............................................................................................................................. 1  2.0  Project Description .................................................................................................................. 2  3.0  Location Map ......................................................................................................................... 10  4.0  Preconstruction, Construction, and Stabilization Plan .................................................... 10  References ..................................................................................................................................... 11 

GREEN MOUNTAIN POWER CORPORATION / KINGDOM COMMUNITY WIND EROSION PREVENTION AND SEDIMENT CONTROL PLAN NARRATIVE

1.0 

1

Introduction 

On behalf of the applicant, Green Mountain Power Corporation, this Erosion Prevention  and Sediment Control (EPSC) Plan narrative and EPSC Plan Summary Forms prepared  by  Vanasse  Hangen  Brustlin,  Inc.  (VHB)  and  associated  EPSC  Plan  sheets,  details,  and  notes  prepared  by  VHB  and  Krebs  and  Lansing  Consulting  Engineers,  Inc.  (Krebs  and  Lansing)  comprise  an  application  for  the  planned  construction  of  the  Kingdom  Community  Wind  Project  located  in  the  Town  of  Lowell,  Orleans  County,  Vermont.1   For the purpose of this application filing, the project area comprises the following major  project components, as shown on the Site Map on the cover sheet of the EPSC Plan.    1. Wind  farm  site,  including  the  access  road,  crane  paths,  laydown/staging  areas, substation, O&M building, and turbine pads  2. Underground collector lines  3. Overhead collector lines  4. Operational phase stormwater management system2    Separate  construction  stormwater  discharge  permit  applications  will  be  filed  with  the  VT  Department  of  Environmental  Conservation  (VT  DEC)  for  the  transmission  line  upgrade  project  and  the  Jay  Tap  substation  project  given  that  there  are  different  applicants  for  these  other  projects  and,  therefore,  they  are not  considered  to  be  part  of  the Kingdom Community Wind project.  Completion of the Risk Evaluation determined  that  the  Kingdom  Community  Wind  Project  is  not  eligible  for  coverage  under  General 

 A petition for Section 248 approval of the Kingdom Community Wind Project from the  Vermont Public Service Board (VT PSB) was filed on May 21, 2010 and is currently pending.  2 An application for an Individual Stormwater Discharge Permit (INDS) for the Kingdom  Community Wind Project was filed with VT DEC on September 21, 2010; pending VT DEC  review and approval.   1

GREEN MOUNTAIN POWER CORPORATION / KINGDOM COMMUNITY WIND EROSION PREVENTION AND SEDIMENT CONTROL PLAN NARRATIVE

2

Permit  3‐9020  as  a  Moderate  Risk  construction  activity  (see  pages  1  through  3  of  the  Appendix).    Therefore,  the  project  seeks  construction  stormwater  discharge  authorization from the VT DEC through the issuance of Individual Discharge Permit for  Stormwater  Runoff  from  Construction  Sites.    This  EPSC  Plan  Narrative  and  the  associated EPSC Plan (attached separately) have been prepared in conformance with the  most recent edition of The Vermont Standards and Specifications for Erosion Prevention and  Sediment Control (2006).  The EPSC Plan Summary Forms have been included on pages 4  through 14 of the Appendix.  

2.0 

Project Description 

The  EPSC  Plan  has  been  prepared  using  General  Permit  3‐9020,  Part  4.1(C)  and  Appendix B of the General Permit 3‐9020, as guidance (in the absence of guidance that is  specific  to  Individual  Permit  applications).    The  following  sections  (a)  through  (m)  of  this narrative address required EPSC Plan Narrative elements in the order that they are  presented in Appendix B of General Permit 3‐9020.     a. Project Type and Description  The  Kingdom  Community  Wind  Project  is  a  high  elevation  renewable  energy  project  comprising twenty‐one 2.5 to 3.0 MW turbines, associated turbine pads, an 18‐foot wide  gravel and/or stone access road that extends approximately 2.5 miles from Route 100 to  the ridgeline, 34‐foot wide gravel and/or stone crane paths extending approximately 4.0  miles  along  the  ridgeline,  laydown/staging  areas,  an  O&M  building,  an  electrical  substation,  underground  and  overhead  collector  lines,  and  a  permanent  stormwater  management  system.  In  addition  to  the  permanent  access  road  and  crane  paths,  the  project will temporarily utilize an existing road (Meek Road / Town Highway 25) during 

GREEN MOUNTAIN POWER CORPORATION / KINGDOM COMMUNITY WIND EROSION PREVENTION AND SEDIMENT CONTROL PLAN NARRATIVE

3

the  initial  construction  period  in  order  to  transport  construction  equipment,  workmen,  fuel, etc. to the site.      b. Major Project Components  As  outlined  in  the  Introduction,  major  project  components  consist  of  the  wind  farm,  including  the  access  road,  crane  paths,  laydown/staging  areas,  substation,  O&M  building,  and  turbine  pads;  underground  collector  lines;  overhead  collector  lines;  and  the  operational  phase  stormwater  management  system.    An  overview  of  the  general  approach  to  construction  and  stabilization  of  these  major  project  components  is  provided  below,  with  more  detailed  sequencing  provided  in  the  Construction  and  Stabilization Sequence on pages 16 through 22 of the Appendix.      Wind Farm and Underground Collector Lines Sequencing   Construction of the wind farm and underground collector lines will be conducted with  four separate earthwork crews. In addition to each separate earthwork crew, there will  be  several  specialized  sub‐crews  supporting  the  earthwork  crews,  which  will  be  attending to the different, orderly and repetitive, construction activities (such as survey  layout, tree cutting, blasting, erosion control, etc.). Each earthwork crew foreman will be  the  On‐Site  Plan  Coordinator  (OSPC)  and  will  inspect,  monitor  and  coordinate  all  earthwork  crew  and  sub‐crew  activities  to  ensure  performance  in  accordance  with  the  EPSC  Plan  requirements  of  site  stabilization  and  drainage  work  (e.g.,  redirecting  of  upslope  run‐on)  whenever  and  wherever  it  may  be  required.    These  four  work  earthwork  crews  will  conduct  construction  activities  concurrently  within  each  of  their  designated work areas (see Illustrative Sequencing Concept Map on EPSC Plan Sheet C‐ 134).  For any one individual earthwork crew, transition from one work area to the next  will  be  in  the  orderly  sequencing  of  the  construction  activities  performed  by  the  earthwork  crew  and  the  support  sub‐crews.  It  is  proposed  for  any  one  individual  earthwork crew working in one or more of the designated work crew areas that the total 

GREEN MOUNTAIN POWER CORPORATION / KINGDOM COMMUNITY WIND EROSION PREVENTION AND SEDIMENT CONTROL PLAN NARRATIVE

4

allowable area of non‐stabilized exposed earth surfaces be limited to 7.5 acres at any one  time.  This  limiting  requirement  of  each  separate  earthwork  crew  could  translate  to  a  maximum  total  for  all  four  earthwork  crews,  of  30  acres  of  concurrent  non‐stabilized  exposed earth surfaces at any one time.  Transition from one work area to the next will  be  coordinated  with  the  earthwork  crew’s  OSPC,  using  the  Illustrative  Sequencing  Concept  Map  on  EPSC  Plan  Sheet  C‐124,  as  guidance.    Estimated  total  areas  of  disturbance within each work area and associated with each work crew are summarized  in Tables 1 and 2, respectively, below: 

Table 1: Wind Farm and Underground Collector Line  Estimated Area of Disturbance  Work Area ID  Area of Disturbance (acres)  #1  28.8  #2  26.5  #3  33.0  #4  35.3  Total Area of Disturbance  123.6 

Table 2: Work Crew Estimated Area of Disturbance  Work Crew ID  Area of Disturbance (acres)  #1  27.6  #2  31.9  #3  34.5  #4  29.6  Total Area of Disturbance  123.6    Overhead Collector Lines  Construction  of  the  overhead  collector  lines  will  be  constructed  concurrently  with  construction of the wind farm project and underground collector lines.  The work area  associated with the overhead collector lines is defined by the 10‐foot wide access routes  and 20‐ by 20‐foot work boxes around each structure, as shown on the EPSC Plan.  For  the purpose of estimating the total area of disturbance associated with installation of the 

GREEN MOUNTAIN POWER CORPORATION / KINGDOM COMMUNITY WIND EROSION PREVENTION AND SEDIMENT CONTROL PLAN NARRATIVE

5

overhead  collector  lines,  the  entire  work  area  (3.35  acres)  as  defined  above  has  been  included  as  a  maximum  in  the  overall  total  area  of  disturbance.    However,  it  is  anticipated that the actual earth disturbance associated with the overhead collector lines  will be less than 3.35 acres due to the nature of the work and via utilization of specific  EPSC measures (e.g., timber mats, stone on fabric, installation during frozen conditions),  as  well  as  limiting  access,  where  possible,  to  those  areas  that  are  less  susceptible  to  erosion.    c. Total Earth Disturbance  Based on the construction and stabilization sequencing provided in Section 2(b) of this  EPSC Narrative and on pages 16 through 22 of the Appendix, the estimated total area of  earth  disturbance  associated  with  the  Kingdom  Community  Wind  Project  is  approximately  127  acres  (see  Table  3  below).      The  Construction  and  Stabilization  Sequence outlines how the earth disturbance will be minimized to the extent practicable  in those areas (see pages 16 through 22 of the Appendix).  In addition, the project design  includes an erosion control zone, which is an approximately 10 foot buffer area located  adjacent  to  earthwork  areas,  where  vegetation  will  be  cleared  but  not  stumped  or  grubbed.    Throughout  the  project  area,  this  erosion  control  zone  equals  approximately  20 acres in area.  Although certain EPSC measures such as silt fence and erosion control  mix  berms  may  be  placed  on  the  downslope  side  of  the  erosion  control  zone,  it  is  not  anticipated  that  this  area  will  be  disturbed  but  rather  left  intact  with  stumps  in  place.   For the purposes of this plan, the 20‐acre erosion control zone has been included in the  overall total area of disturbance (147 acres) associated with this project.             

GREEN MOUNTAIN POWER CORPORATION / KINGDOM COMMUNITY WIND EROSION PREVENTION AND SEDIMENT CONTROL PLAN NARRATIVE

6

Table 3: Estimated Total Area of Disturbance  Major Project Component  Area of Disturbance (acres)  Wind Farm and Underground  123.6  Collector Lines  Overhead Collector Lines  3.35  Erosion Control Zone  20  Estimated Total Area of  147  Disturbance    Oversight of construction and stabilization sequencing will be  conducted by the OSPC  and the EPSC Specialist.  In the event of visibly discolored discharge from the site, the  OSPC  will  follow  protocols  provided  by  VT  DEC  for  EPSC  measure  implementation,  turbidity  monitoring,  and  reporting,  as  required  (see  EPSC  Plan  Sheet  C‐131).   Furthermore,  it  is  expected  that  the  OPSC  and  EPSC  Specialist  may  modify  the  Construction and Stabilization Sequence and associated EPSC measures provided on the  EPSC  Plan,  as  needed,  throughout  the  construction  of  the  project.    Modifications  will  be made in response to actual construction conditions and/or limitations encountered.  It  is  the  responsibility  of  the  OPSC  and  EPSC  Specialist  to  report  significant  plan modifications  and  to  review  those  modifications  and  any  updates  of  the  Construction  and  Stabilization  Sequence  with  VT  DEC  throughout  the  construction  of the Project, as required, and as such modifications and updates occur.    d. Sequence of Major Project Components  Sequencing and timing of major project components is described in detail in Section 2(b)  of this EPSC Narrative and in the Construction and Stabilization Sequence on pages 16  through 22 of the Appendix.    e. Maximum Concurrent Earth Disturbance  Based on the construction and stabilization sequencing provided in Section 2(b) of this  EPSC Narrative and as outlined in the Construction and Stabilization Sequence on pages 

GREEN MOUNTAIN POWER CORPORATION / KINGDOM COMMUNITY WIND EROSION PREVENTION AND SEDIMENT CONTROL PLAN NARRATIVE

7

16 through 22 of the Appendix, the site construction of the Kingdom Community Wind  Project  will  be  conducted  with  four  earthwork  crews  each  being  designated  four  work  areas. The foremen of the earthwork crews will be the OSPC and will have the control  and support of the specialized sub‐crew that will attend to EPSC Plan requirements, site  stabilization,  and  drainage  work  (e.g.,  redirecting  of  upslope  run‐on).    These  four  earthwork  crews  will  conduct  construction  activities  concurrently  within  each  of  the  four  designated  crew  work  areas  (see  Illustrative  Sequencing  Concept  Map  on  EPSC  Plan  Sheet  C‐134).    For  any  one  individual  earthwork  crew,  transition  from  one  work  area to the next will be in the orderly sequencing of the construction activities performed  by the earthwork crew and the support sub‐crews. It is proposed for any one individual  earthwork crew working in one or more of the designated work crew areas that the total  allowable area of non‐stabilized exposed earth surfaces be limited to 7.5 acres at any one  time.  This  limiting  requirement  of  each  separate  earthwork  crew  could  translate  to  a  maximum  total  for  all  four  earthwork  crews,  of  30  acres  of  concurrent  non‐stabilized  exposed earth surfaces at any one time. Transition from one work area to the next will be  coordinated  with  the  earthwork  crew’s  On‐Site  Plan  Coordinator  (OSPC),  using  the  Illustrative Sequencing Concept Map on EPSC Plan Sheet C‐124, as guidance.      f.

Vegetated Buffers 

Vegetative buffers will be utilized to the extent possible to supplement structural EPSC  measures, as outlined in the Natural Resource Assessment Report and associated buffer  matrix  (Exh.  Pet.‐JAN‐2),  which  was  filed  as  a  component  of  the  project’s  Section  248  petition to the VT PSB.  Also, to the extent possible, existing vegetative buffers between  down slope receiving waters and the construction site will remain.  However, due to the  linear  layout  of  the  proposed  project  and  the  resultant  buffer  width  variability,  use  of  vegetative buffers was not used to score this project in the Risk Evaluation (see pages 1  through 3 of the Appendix).   

GREEN MOUNTAIN POWER CORPORATION / KINGDOM COMMUNITY WIND EROSION PREVENTION AND SEDIMENT CONTROL PLAN NARRATIVE

8

g. Duration of Exposed Soils  The Kingdom Community Wind Project will not have exposed earth surfaces in any one  location  for  more  than  14  consecutive  calendar  days  without  temporary  or  permanent  stabilization, as indicated in the scoring of the project in the Risk Evaluation (see pages 2  through  4  of  the  Appendix).    The  EPSC  Plan  and  Construction  and  Stabilization  Sequence  provide  specific  measures  for  achieving  temporary  and  permanent  stabilization.    h. Receiving Waters  There are numerous potential receiving waters located within the Kingdom Community  Wind  Project  area,  as  shown  on  the  Post‐Development  Subwatershed  Map  (see  map  pocket) and as reported in the Natural Resources Assessment Report (prepared by VHB  and dated February 26, 2010, Exh. Pet.‐JAN‐2).  The seven major drainage areas include:  Ace  Brook,  East  Branch  Missisquoi  River,  McCleary  Brook,  Rogers  Branch,  Seaver  Branch, Shalney Branch, and Truland Brook (see Pre‐Construction Subwatershed Map in  map pocket).  To the extent practicable, stormwater runoff will flow overland from the  construction  site  with  maximum  potential  for  infiltration,  dispersal,  settling,  and/or  containment by select EPSC measures prior to discharge to receiving waters (see EPSC  Plan).      i.

Drainage Areas and Soil Types 

For  this  large,  generally  linear  project,  drainage  areas  have  been  determined  by  major  watershed areas, as outlined in section 2(h) above.  A summary table on page 15 of the  Appendix  provides  the  required  information  for  each  major  watershed  area,  including  name,  drainage  area  size,  area  of  disturbance  within  each  drainage  area,  Natural  Resources Conservation Service (NRCS) erodibility index, and average slope.  Soil types  are listed in the EPSC Plan Summary Forms (see page 5 of the Appendix) and shown on  the Soils Map included on page 23 of the Appendix.  Of the approximately 147 acres of 

GREEN MOUNTAIN POWER CORPORATION / KINGDOM COMMUNITY WIND EROSION PREVENTION AND SEDIMENT CONTROL PLAN NARRATIVE

9

potential  soil  disturbance  that  has  been  estimated  for  this  project,  8.08  acres  has  an  erodibility  rating  of  K  0.36*













High High High High High High Medium Low Medium High g High High High High High Low Medium Low High High High High High Medium Medium High High High Medium High High High High High High High High High High High High High Medium High High High High High Medium Medium High High High Medium High

Risk2







ABC ABC ABC ABC ABC ABC ABC ABC A AB AB AB ABC ABC ABC A A A AB ABC AB AB AB A A ABC AB AB ABC AB AB ABC AB ABC ABC ABC ABC ABC ABC AB ABC AB AB ABC ABC ABC ABC ABC AB A AB ABC ABC A ABC

EPSC  Standards3

\\VTDATA\Projects\57346.00\GIS\vector\shape\Stormwater\Geoprocesses\RiskEval\SoilImpactSheet.xlsxSummary Table11/8/2010

Area Weighted 2 Low, Medium, or High. Refer to Table 3.2 in VT Standards and Specifications for Erosion Prevention and  3 Refer to Table 3.3 A = Limit Disturbed Soil, Temporary Stabilization, Small Area Sediment Control B = Slope  Protection, Runoff Control, Flow Protection C = Large Area Sediment Control *K factors for collector line and erosion control zone assigned as K>0.36 to remain conservative.

1

20.0

>  0.36*

3.1 Approximate Area within  Erosion Control Zone



6.9 5.4 2.2 8.2 6.4 6.8 2.3 5.3 0.6 0.8 0.8 0.9 1.7 2.1 1.1 0.5 0.5 0.7 0.5 1.4 1.0 1.0 0.6 0.6 0.5 1.0 0.7 0.8 1.2 0.9 0.9 1.7 0.6 6.5 1.5 6.3 6.5 5.0 1.2 0.8 3.4 0.6 1.1 3.1 2.1 1.1 1.5 2.5 1.3 0.7 0.7 1.8 1.7 1.0 1.6

A1 A3 A4 A9 EBMR1 EBMR3 EBMR4 EBMR5 EBMR6 LS/DP‐A4 LS/DP‐C10 LS/DP‐C15 LS/DP‐C19 LS/DP‐C4 LS/DP‐D2 LS‐A1 (Infiltration) LS‐A15 LS‐A2 LS‐A22 LS‐A23 LS‐A24 LS‐A25 LS‐A3 LS‐A7 LS‐A9 LS‐C1 LS‐C11 LS‐C18 LS‐C2 LS‐C3 LS‐C5 LS‐C7 LS‐D1 M1 M2 R1 R2 S1 Sh1 Sh2 Sh3 T1 WP‐A WP‐B WP‐C WP‐D WP‐E WP‐F WP‐G WP‐H WP‐I WP‐J WP‐K WP‐L WP‐M Total area beyond  subwatersheds with  greater than 0.5 acres of  disturbance Approximate Area  disturbed due to Collector  Line

Weighted  Average  Soil K  Slope      1 (%) factor 0.44 22 0.37 20 0.25 16 0.46 23 0.49 26 0.49 25 0.28 14 0.17 6 0.24 13 0.28 16 0.49 18 0.49 27 0.49 23 0.49 24 0.49 15 0.17 5 0.24 12 0.17 10 0.24 28 0.40 30 0.49 16 0.49 16 0.21 17 0.26 13 0.28 15 0.41 15 0.49 17 0.49 24 0.35 12 0.48 15 0.49 19 20 0.31 0.49 15 0.41 29 0.31 26 0.49 29 0.47 20 0.48 30 0.49 28 0.49 28 0.40 27 0.49 23 0.24 13 0.49 17 0.49 19 0.49 9 0.49 10 0.49 18 0.28 12 0.32 12 0.49 27 0.49 16 0.49 18 0.32 8 0.49 15 5.6

Disturbance  (Acres)

Drainage Area #  (Subwatershed ID)

For each drainage area with disturbance of 0.5 acres or more

Discharge Area Summary

Kingdom Community Wind Discharge Area Summary Table Prepared by VHB/Vanasse Hangen Brustlin, Inc. 11/8/2010

15

16

 

  KINGDOM COMMUNITY WIND PROJECT  LOWELL, VERMONT    CONSTRUCTION AND STABILIZATION SEQUENCE    November 8, 2010       1.0  INTRODUCTION    The  primary  intent  of  the  Construction  and  Stabilization  Sequence  is  to  provide  a  thorough  understanding of the following:    • The project’s intended sequence of construction and earth disturbing activities  • The extent of estimated earth disturbance associated with each major activity (or in this case,  each work area)  • Means of minimizing the amount of disturbed area that is open at any one time  • Means of minimizing the potential for erosion  • Means of providing sediment control in the event of stormwater runoff and erosion  • Means and timing of conducting temporary and permanent stabilization    The  target  audience,  with  regard  to  review  and  implementation  of  the  Construction  and  Stabilization  Sequence, includes regulators (e.g., VT DEC), the project’s On‐Site Plan Coordinator (OSPC), the Erosion  Prevention  and  Sediment  Control  (EPSC)  Specialist(s),  and,  perhaps  most  importantly,  the  contractors.   The content of the Construction and Stabilization Sequence includes:     • Sections  2.1  and  2.2,  which  provide  an  overview  of  construction  and  stabilization  sequencing  associated  with  the  two  major  project  areas:  (1)  Wind  Farm  and  Underground  Collector  Line  areas, and (2) Overhead Collector Line areas.  • Sections  3.1  through  3.5,  which  provide  an  overview  of  construction  and  stabilization  sequencing associated with each of the major construction activities (building of roads, building  of turbine pads, building of the substation, etc).    Where appropriate, references have been made to specific EPSC Plan sheets, notes, and details of the  EPSC  Plan  set;  Civil  Site  Design  Drawings;  and  operational  phase  Stormwater  Plan  Set,  as  a  means  of  limiting potential for contradiction between the three project plan sets.       2.0 GENERAL CONSTRUCTION AND STABILIZATION SEQUENCES    2.1  Wind Farm and Underground Collector Lines    The wind farm portion of the project, as described herein, encompasses the access road,  crane  paths,  laydown/staging  areas,  substation,  O&M  building,  turbine  pads,  and  underground collector lines.  Construction of the wind farm and underground collector  lines  shall  be  constructed  with  four  separate  earthwork  crews  that  are  supported  by  Page 1 of 7 

17

  sub‐crews, one of which will be attending to EPSC Plan requirements, site stabilization,  and  drainage  work  (e.g.,  redirecting  of  upslope  run‐on).    These  four  earthwork  crews  will  conduct  construction  activities  concurrently  within  each  of  their  designated  work  areas,  and  will  be  guided  by  the  Illustrative  Sequencing  Concept  Map  on  EPSC  Plan  Sheet C‐134.  For any one individual earthwork crew, transition from one work area to  the  next  will  be  in  the  orderly  sequencing  of  the  construction  activities  performed  by  the  earthwork  crew  and  the  support  sub‐crews.  It  is  proposed  for  any  one  individual  earthwork  crew  working  in  one  or  more  of  the  designated  work  crew  areas  that  the  total allowable area of non‐stabilized exposed earth surfaces be limited to 7.5 acres at  any one time. This limiting requirement of each separate earthwork crew could translate  to  a  maximum  total  for  all  four  earthwork  crews,  of  30  acres  of  concurrent  non‐ stabilized exposed earth surfaces at any one time.  Transition from one work area to the  next  will  be  coordinated  with  the  earthwork  crew’s  OSPC,  using  the  Illustrative  Sequencing Concept Map on EPSC Plan Sheet C‐124, as guidance.  Estimated total areas  of  disturbance  within  each  work  area  and  associated  with  each  work  crew  are  summarized  in  Tables  1  and  2,  respectively.    These  areas  do  not  include  the  erosion  control  zone  of  approximately  20  acres,  which  is  anticipated  to  remain  intact  with  stumps left in place to the extent practicable.      Table 1: Wind Farm and Underground Collector Line Estimated Area of Disturbance  Work Area ID  Area of Disturbance (acres)  #1  28.8  #2  26.5  #3  33.0  #4  35.3  Total Area of Disturbance  123.6    Table 2: Work Crew Estimated Area of Disturbance  Work Crew ID  Area of Disturbance (acres)  #1  27.6  #2  31.9  #3  34.5  #4  39.6  Total Area of Disturbance  123.6    Within each work area, the sequence of construction activities shall typically involve:    1. Flag centerline of work area (e.g., centerline of access road and crane path, as  depicted on Civil Site Design Drawings)   2. Clear trees necessary for surveying extent of the centerline of access road and  crane path with the VT ANR Acceptable Management Practices for Maintaining  Water Quality on Logging Jobs (1987), at a minimum; no stumping and grubbing  at this time  3. Flag extent of work area limits  4. Installation  of  initial  EPSC  measures  (e.g.,  construction  barrier  flagging,  stabilized construction entrance)  Page 2 of 7 

18

 

2.2

5. Tree clearing in accordance with the Vermont Agency of Natural Resources (VT  ANR)  Acceptable  Management  Practices  for  Maintaining  Water  Quality  on  Logging Jobs (1987), at a minimum; no stumping and grubbing at this point  6. Installation  of  additional  EPSC  measures  as  needed  (e.g.,  silt  fence,  filter  logs,  etc.)  7. Stumping and grubbing, with installation of additional EPSC measures as needed  (e.g., wood chips, erosion control mix berms, etc.)  8. Earthwork  pursuant  to  specific  construction  activity  (access  road,  crane  path,  turbine pad, etc.)  9. Temporary or permanent stabilization of all exposed soil; see EPSC Plan Sheet C‐ 131 for temporary and permanent stabilization measures    Overhead Collector Lines    Construction  of  the  overhead  collector  lines  shall  be  constructed  concurrent  with  construction of the wind farm project and underground collector lines.  The work area  associated  with  the  overhead  collector  lines  is  defined  by  the  approximately  10‐foot  wide access routes and approximately 20‐ by 20‐foot work boxes around each structure,  as shown on EPSC Plan set.  For the purpose of estimating the total area of disturbance  associated  with  installation  of  the  overhead  collector  lines,  the  entire  work  area  (3.35  acres)  as  defined  above  has  been  included  as  a  maximum  in  the  overall  total  area  of  disturbance.    However,  it  is  anticipated  that  the  actual  earth  disturbance  associated  with  the  overhead  collector  lines  will  be  less  that  3.35  acres  due  to  the  nature  of  the  work  and  via  utilization  of  specific  EPSC  measures  (e.g.,  timber  mats,  stone  on  fabric,  installation during frozen conditions), as well as limiting access, where possible, to those  areas that are less susceptible to erosion. 

  Installation of the overhead collector lines shall be conducted, as follows:    1. Structure locations are to be accessed via collector line access routes within the  right‐of‐way, as shown on EPSC Plan set  2. Equipment  is  to  remain  within  the  approximately  10‐foot  wide  access  routes  and  approximately  20  x  20  foot  work  boxes;  access  outside  of  these  areas  requires prior approval by the OSPC  3. Construction demarcation is to be conducted per Table 1 on EPSC Plan Sheet C‐ 130 prior to tree clearing and earth disturbing activities  4. Tree  clearing  is  to  be  conducted  in  accordance  with  the  VT  ANR  Acceptable  Management Practices for Maintaining Water Quality on Logging Jobs (1987), at  a minimum  5. EPSC measures are to be installed as needed prior to earth disturbing activities;  see Table 2 on EPSC Plan Sheet C‐130  6. Equipment  is  not  to  cross  a  wetland  without  the  use  of  matting  without  prior  approval by the OSPC, following a Dry Evaluation or Frozen Ground Evaluation  (see EPSC Plan Sheet C‐133)  7. The OSCP may direct that equipment and materials are to be stored in upland  locations      Page 3 of 7 

19

  3.0   

MAJOR CONSTRUCTION AND STABILIZATION ACTIVITIES  3.1 

3.2 

Access  Road,  Crane  Path,  Underground  Collector  Lines,  and  Permanent  Stormwater  Management System Construction and Stabilization Sequence    1. Flag centerline of access road and crane paths  2. Clear  trees  necessary  for  surveying  of  access  road  and  crane  path  centerlines  in  accordance  with  the  VT  ANR  Acceptable  Management  Practices  for  Maintaining  Water Quality on Logging Jobs (1987), at a minimum; no stumping and grubbing at  this time  3. Flag  extent  of  access  road  and  crane  path  clearing  limits,  including  modifications  allowed by the Variable Road Location Detail (see EPSC Plan Sheet C‐129)  4. Install  EPSC  measures,  including  construction  demarcation  and  perimeter  erosion  controls (see EPSC Plan Sheet C‐130)  5. Cut, stump, and grub areas within demarcated clearing limits  6. Stockpile material for chipping and grinding to use for EPSC measures  7. Remove  overburden  necessary  for  road  building;  stockpile  material  in  designated  area with appropriate EPSC measures  8. Conduct  drilling  and  blasting;  use  mobile  crushers  to  process  material  for  use  in  road building  9. Conduct  earth and ledge excavation with cuts and fills pursuant to Civil Site Design  Drawings;  concurrently,  install  sediment  traps  (level  spreaders,  dry  ponds)  and  sediment  basins  (wet  ponds)  located  immediately  downslope  of  active  areas  of  earthwork per details provided on the EPSC Plan Sheets C‐127, C‐128, and C‐133  10. Construct access roads and crane paths, including vehicle pull‐over lanes, pursuant  to Civil Site Design Drawings  11. Concurrent  with  construction  of  crane  paths,  install  underground  collector  lines  pursuant to Civil Site Design Drawings   12. Continuously apply EPSC measures to limit the amount of earth disturbance at any  one time; apply temporary or permanent stabilization per the EPSC Plan set  13. Repair/replace/refresh EPSC measures (e.g., silt fence, erosion control mix, etc.), as  needed to maintain their effectiveness until areas are fully stabilized  14. As  needed  to  maintain  proper  performance,  remove  accumulated  sediment  from  sediment traps and sediment basins; deposit in an appropriate upslope location and  stabilize   15. Once upslope area  is fully stabilized, reconstruct sediment traps as level spreaders  or  dry  ponds  and  sediment  basins  as  permanent  stormwater  basins  per  the  EPSC  Plan set and pursuant to operational phase Stormwater Plan Set  16. Remove all temporary EPSC measures (e.g., silt fence, etc) once upslope area is fully  stabilized; apply seed and mulch to remaining exposed soils, as needed    Laydown/Staging Area Construction and Stabilization Sequence    1. Flag extent of laydown/staging area to be cleared of trees   2. Clear  trees  within  laydown/staging  area  footprint  in  accordance  with  the  VT  ANR  Acceptable  Management  Practices  for  Maintaining  Water  Quality  on  Logging  Jobs  (1987), at a minimum; no stumping and grubbing at this time 

Page 4 of 7 

20

  3. Install  EPSC  measures,  including  construction  demarcation  and  perimeter  erosion  controls (see EPSC Plan Sheet C‐130)  4. Cut, stump, and grub areas within demarcated clearing limits  5. Stockpile materials for chipping and grinding  6. Remove  overburden;  stockpile  material  in  designated  area  with  appropriate  EPSC  measures  7. Conduct drilling and blasting, as needed; use mobile crusher to process material as  needed  8. Conduct earthwork with cuts and fills pursuant to Civil Site Design Drawings  9. Construct laydown/staging area pursuant to Civil Site Design Drawings  10. Continuously apply EPSC measures to limit the amount of earth disturbance at any  one time; apply temporary or permanent stabilization per the EPSC Plan set  11. Repair/replace/refresh EPSC measures (e.g., silt fence, erosion control mix, etc.), as  needed to maintain their effectiveness until area is fully stabilized  12. Remove all temporary EPSC measures (e.g., silt fence, etc.) once upslope area is fully  stabilized; apply seed and mulch to remaining exposed soils, as needed    3.3 

Substation and O&M Building Construction and Stabilization Sequence 

  1. Flag extent of substation area to be cleared of trees   2. Clear  trees  within  substation  area  footprint  in  accordance  with  the  VT  ANR  Acceptable  Management  Practices  for  Maintaining  Water  Quality  on  Logging  Jobs  (1987), at a minimum; no stumping and grubbing at this time  3. Install  EPSC  measures,  including  construction  demarcation  and  perimeter  erosion  controls (see EPSC Plan Sheet C‐130)  4. Cut, stump, and grub areas within demarcated clearing limits  5. Stockpile materials for chipping and grinding  6. Remove  overburden;  stockpile  material  in  designated  area  with  appropriate  EPSC  measures  7. Conduct drilling and blasting, as needed; use mobile crusher to process material as  needed  8. Conduct geotechnical borings for O&M building design  9. Conduct earthwork with cuts and fills pursuant to Civil Site Design Drawings  10. Construct substation, O&M building, and related infrastructure pursuant to Civil Site  Design Drawings  11. Continuously apply EPSC measures to limit the amount of earth disturbance at any  one time; apply temporary or permanent stabilization per the EPSC Plan set  12. Repair/replace/refresh EPSC measures (e.g., silt fence, erosion control mix, etc.), as  needed to maintain their effectiveness until area is fully stabilized  13. Remove all temporary EPSC measures (e.g., silt fence, etc.) once upslope area is fully  stabilized; apply seed and mulch to remaining exposed soils, as needed    3.4 

Turbine  Pad  and  Permanent  Stormwater  Management  System  Construction  and  Stabilization Sequence 

  1. Flag extent of turbine pad area to be cleared of trees  

Page 5 of 7 

21

 

3.5 

2. Clear trees within turbine pad footprint in accordance with the VT ANR Acceptable  Management Practices for Maintaining Water Quality on Logging Jobs (1987), at a  minimum; no stumping and grubbing at this time  3. Conduct geotechnical borings for foundation design  4. Install  EPSC  measures,  including  construction  demarcation  and  perimeter  erosion  controls (see EPSC Plan Sheet C‐130)  5. Cut, stump, and grub areas within demarcated clearing limits  6. Stockpile materials for chipping and grinding  7. Remove  overburden;  stockpile  material  in  designated  area  with  appropriate  EPSC  measures  8. Conduct drilling and blasting, as needed; use mobile crusher to process material as  needed  9. Conduct  earthwork  with  cuts  and  fills  pursuant  to  Civil  Site  Design  Drawings;  concurrently,  install  sediment  traps  (level  spreaders,  dry  ponds)  and  sediment  basins (wet ponds) located immediately downslope of active areas of earthwork per  sediment details provided on EPSC Plan Sheets C‐127, C‐128, and C‐133  10. Excavate for turbine foundations; install foundations  11. Continuously apply EPSC measures to limit the amount of earth disturbance at any  one time; apply temporary or permanent stabilization per the EPSC Plan set  12. Repair/replace/refresh EPSC measures (e.g., silt fence, erosion control mix, etc.), as  needed to maintain their effectiveness until area is fully stabilized  13. As  needed  to  maintain  proper  performance,  remove  accumulated  sediment  from  sediment traps and sediment basins; deposit in an appropriate upslope location and  stabilize per Temporary and Final Stabilization Notes on EPSC Plan Sheet C‐131   14. Once upslope area  is fully stabilized, reconstruct sediment traps as level spreaders,  and dry ponds and sediment basins as permanent stormwater basins per EPSC Plan  Sheets C‐127 and C‐128 and pursuant to operational phase Stormwater Plan Set  15. Remove all temporary EPSC measures (e.g., silt fence, etc.) once upslope area is fully  stabilized; apply seed and mulch to remaining exposed soils, as needed    Overhead Collector Line Construction and Stabilization Sequence 

  1. Flag extent of overhead collector line right‐of‐way (ROW) to be cleared of trees   2. Clear  trees  within  ROW  footprint  in  accordance  with  the  VT  ANR  Acceptable  Management Practices for Maintaining Water Quality on Logging Jobs (1987), at a  minimum; no stumping and grubbing at this time  3. Demarcate extent of ROW to be used for installation of approximately 10‐foot wide  access routes and approximately 20‐ by 20‐foot work areas surrounding each pole.  4. Install  EPSC  measures,  including  perimeter  erosion  controls,  where  needed  (see  EPSC Plan Sheet C‐130)  5. Stockpile  materials  for  chipping  and  grinding  (note  that  other  areas  of  the  project  may be used for this operation, such as the access road)  6. Install  poles  pursuant  to  collector  design  drawings;  holes  for  poles  are  approximately 2 feet in diameter and approximately 8 feet in depth  7. Spread  drill  spoils  material  adjacent  to  hole  in  non‐wetland  areas  then  seed  and  mulch when required  8. Conduct wire installation and any other collector line installation activities pursuant  to collector design plans  Page 6 of 7 

22

  9. Continuously apply EPSC measures to limit the amount of earth disturbance at any  one time; see Temporary and Final Stabilization Notes on EPSC Plan Sheet C‐131   10. Repair/replace/refresh EPSC measures (e.g., silt fence, erosion control mix, etc.), as  needed to maintain their effectiveness until areas are fully stabilized  11. Remove all temporary EPSC measures (e.g., silt fence, etc.) once upslope area is fully  stabilized; apply seed and mulch to remaining exposed soils, as needed    3.6 

Changes in Work 

  It  is  expected  that  the  OPSC  and  EPSC  Specialist  may  modify  the  Construction  and  Stabilization  Sequence  and  associated  EPSC  measures  provided  on  the  EPSC  Plan,  as  needed,  throughout  the  construction  of  the  project.    Modifications  will  be made  in  response  to  actual  construction  conditions  and/or  limitations  encountered.    It  is  the  responsibility  of  the  OPSC  and  EPSC  Specialist  to  report  significant  plan modifications  and to review those modifications and any updates of the Construction and Stabilization  Sequence  with  VT  DEC  throughout  the  construction  of the Project,  as  required,  and  as  such modifications and updates occur.      \\VTDATA\Projects\57346.03 GMP KCW SW Permitting\tech\KCW Const Phasing Plan_110810.doc

 

Page 7 of 7 

YR D

TH

Indirect Study Area

not rated

D

C

B

A

NRCS Soil Hydrogroup

500 ft. Contour

100 ft. Contour

Wind Farm Direct Study Limits

Town/County Boundary

Parcel Boundaries

Vermont State Highway

Local Road

12D K Factor 0.24

12D K Factor 0.24

247C K Factor 0.26

247B K Factor 0.2

LyE K Factor 0.26

100

"

RD

26C K Factor 0.17

EK ME

0 250

Legend

26C K Factor 0.17

0

Y

RD

November 4, 2010

N BA L A

RD

0

Scale - 1" = 2000'

1,000

2,000 Feet

0 15

0

0 15

0

23 Prepared by: SEM/JAT

Sources: Town/County Layer (2004), roads layer (2009), Soils (2008) provided by VCGI (2010); Direct Study Limits and Indirect Study Area by VHBP (2009).

Soil Description Lyman-Tunbridge fine sandy loams, very rocky, 25 to 60 percent slopes Londonderry-Stratton complex, 25 to 60 percent slopes Monadnock fine sandy loam, 15 to 35 percent slopes, very stony Cabot silt loam, 0 to 8 percent slopes, very stony Sheepscot gravelly fine sandy loam, 3 to 8 percent slopes Adams loamy fine sand, 25 to 60 percent slopes Adams loamy fine sand, 8 to 15 percent slopes Adams loamy fine sand, 3 to 8 percent slopes Colonel-Cabot complex, 8 to 15 percent slopes Colonel-Cabot complex, 3 to 8 percent slopes Dixfield sandy loam, 15 to 35 percent slopes, very stony Tunbridge-Lyman complex, 35 to 60 percent slopes, very rocky Tunbridge-Lyman complex, 15 to 35 percent slopes, very rocky Hogback-Rawsonville complex, 35 to 60 percent slopes, very rocky Hogback-Rawsonville complex, 15 to 35 percent slopes, very rocky Tunbridge-Dixfield complex, 15 to 35 percent slopes, very stony

112D K Factor 0.49

12E K Factor 0.24

EDEN RD

RD LL HI

F:\57346.00\GIS\project\Stormwater\KCW_Site_soils_reformat_11x17.mxd

Soil ID LyE LoE 93D 59B 31B 26E 26C 26B 247C 247B 16D 12E 12D 112E 112D 101D

SH IRI

12E K Factor 0.24

112E K Factor 0.49

Kingdom Community Wind Lowell, Vermont Soils Map - Wind Farm

LoE K Factor 0.46

U

L

U IE

101D K Factor 0.26

LO RL WE L EA NS L (L CO AM EDE .) N OI LL E C O. ) (O

A BE

93D K Factor 0.28

59B K Factor 0.32

12E K Factor 0.24

16D K Factor 0.28

0 15

0

16D K Factor 0.28

31B K Factor 0.17

TH 3

RD W

E

26E K Factor 0.17

SO

U

G PA

D ER

CH EN E

26C K Factor 0.17

26B K Factor 0.17

1500 FID

RD

RD MINK FARM RD DL ER S EL BO W

0 10 0

BOU

250 0

0 25 0

D ET R S QU

0

2 TH 5

(O LOW RL E E AN LL S (O ALB C R O. LE AN ) AN Y S CO .)

ER

200 0

1500

0

1500

HAZEN

10 0

FARM RD

RD

15 0

Y BAILE

W CO S LE