Request for PO #01 Insulated Metal Panels VEROBLUE URBAN FARM Webster City, IA Scope of work: Insulated Metal Walls and Ceilings system all labor, materials, and equipment to unload, furnish and install a complete IMP system enclosure as noted and per manufacturer requirements including shipping costs Sales tax status: Sales tax exempt Subcontractor: Midwest Cold Storage 5417 Garden Hills Lane St. Cloud, MN 56301 Contact: Rob Olson Terms: No down payment Bills for materials on site and work in place submitted every week Payment 15 days following 2% discount on Insulated Metal Panel (Metl-Span) material portion of invoice ~ to be noted on each invoice with 15 day payment terms Lien waivers with each invoice PO Amount: US DOLLARS $ 2,335,686
BID PACKAGE #01 Insulated Metal Panels VEROBLUE URBAN FARM Webster City, IA Addendum #1 Bid date: unchanged 1) Need to add bump out at each barn see attached drawing 1 2) provide cost for 1 hr Thermalsafe mineral wool panels as additional ceiling in boiler room mounted to angle to block wall at 10 feet high- sig 200 coating both sides- see drawing 2 3) Need to plan to leave two openings in each barn demising wall approx. 12x12 to bring tanks in and close up after tank –see drawing 3 4) Can 45” panel be used? a. yes but provide manufacturers letter stating they are equal in performance to the 42” in all applications on this project 5) Hanger rods materials question a. Please quote as base bid all rods zinc coated (no rust on ceiling) b. Can provide alternate for carbon rods prime painted except at plenum with assurance that no rust will appear on ceiling 6) Is plenum sealing as critical as fish grow areas a. Yes- plenum must be airtight
BID PACKAGE #01 Insulated Metal Panels VEROBLUE URBAN FARM Webster City, IA Bid due: Monday Jul 18 @ 5 PM Company name: __Midwest Cold Storage________________ Submitted by: _Rob Olson___________________ Bid shall include all labor, materials, and equipment to unload, furnish and install a complete IMP system enclosure as noted and per manufacturer requirements including shipping costs and sales tax. BID: Breakdown Grow Ceilings and Walls Plenum Walls and Cap WWTP walls and Ceiling Boiler room 1hr extra ceiling TOTAL BID
$_2,087,057_____________ $ __206,523____________ $ __134,406____________ $_____5,700_________ $ _2,433,686_____________
Breakout of sales tax in bid above $ +/- 98,000 on mat _____________ Confirm Schedule dates __5 wk____ Lead time on first panel delivery Metl-span_______ Name of panel manufacturer __yes_____Confirm completion dates noted in bid package Email to:
[email protected] Amended 7-22-16: 2% discount on Metl Span panels materials with weekly invoice payment terms 15 days following invoice to claim discount Quote excluding sales tax $ $2,335,686