La Parrilla Mine update

Report 6 Downloads 12 Views
7/20/2016

W Resources PLC | La Parrilla Mine update | FE InvestEgate

W Resources PLC

La Parrilla Mine update RNS Number : 6705E W Resources PLC 20 July 2016  

                20 July 2016      

W Resources Plc ("W" or the "Company")      

La Parrilla Mine to operate at 90% higher production rate from Mid 2017 Initial mining from existing plant to start Q4 2016

W Resources Plc (AIM:WRES), the tungsten, copper and gold, exploration and development company with  assets  in  Spain  and  Portugal,  has  completed  the  mine  optimisation  plan  of  the  initial  La  Parrilla open pit mine. Initial  mining,  plant  commissioning  and  tungsten  concentrate  production  and  sales  to  customers  will commence, as previously expected, in Q4 2016 using the existing on­site plant and facilities. The results of the mine optimisation plan have been evaluated, leading W to start mining at a higher rate of  1.95  mtpa.  The  optimised  mine  plan  completed  over  the  last  4  months  results  in  lower  mine  strip ratios, lower mining costs and increases tungsten and tin concentrate production rates. The processing plant capacity will now be twice as large as previously designed and construction is to be completed in mid­2017. Summary of the key metrics: Optimised Plan

Previous Plan

Design Feed Rate

1.95 mtpa

0.875 mtpa

Tungsten Production (66% WO3)

2,500 tpa

1,300 tpa

ROM Feed Grade W03%

0.121%

0.135%

  Please click for stages of development: http://www.wresources.co.uk/projects/la­parrilla/  Mining  will  commence  in  Q4  2016  in  the  FTM  area  around  the  high­grade  Hole  IRC1­40  using  an upgrade of the existing concentrator and site infrastructure with existing approvals. During the next 12 http://www.investegate.co.uk/ArticlePrint.aspx?id=201607200700076705E

1/2

7/20/2016

W Resources PLC | La Parrilla Mine update | FE InvestEgate

months  it  is  planned  that  the  process  plant  which  will  operate  at  1.95  mtpa  will  be  installed  and commissioned with production at the large plant ramping up from mid­2017. Process plant engineering design at the higher mine production capacity of 1.95 mtpa is now advanced with preliminary engineering complete on the crusher, jig, mill and concentrate plant circuits. Ramp­up to full production is expected within 6­12 months from commencement of production. Based on initial work, W does not expect material increases in the total plant capital costs. Grade control drilling and drilling of the lateral extension of the FTM mine to the north and south has commenced which could potentially increase size of initial pits and extend the mine life. Michael Masterman, Chairman of W Resources commented: "A lean start­up of the FTM mine in Q4 2016 will get concentrate production underway allowing W to deliver a saleable product to customers. In addition to the significant improvements highlighted by the optimisation plan, there remains scope for further substantial increases in the size of the existing open pit mine. Trenching around the FTM south discovery Hole IRC1­40 has clearly shown bands of outcropping tungsten and tin in quartz veins to the south  of  the  current  pit  area.  These  outcrops  are  expected  to  be  high­grade,  accessible  with  minimal waste movement and are not included in the current FTM pit develop plans outlined above. Drilling of these outcrop areas and lateral extensions has commenced and will be completed in July 2016. "Financing  discussions  are  advanced  to  reach  the  production  targets  for  2016,  which  we  expect  to  be financed  by  initial  customer  off­take  contracts  and  negotiations  are  progressing  well  with  regard  to financing the 1.95 mtpa development in 2017 by either a Joint Venture or a debt facility."     Enquiries: W Resources Plc Michael Masterman T: +44 (0) 20 7193 7463 www.wresources.co.uk SI Capital ­ Joint Broker Andy Thacker / Nick Emerson T: +44 (0) 1483 413500 www.sicapital.co.uk

Grant Thornton UK LLP Colin Aaronson / Jen Clarke / Harrison Clarke T: +44 (0) 20 7383 5100

Gable Communications Justine James T: +44 (0) 20 7193 7463 M: +44 (0) 7525 324431

About La Parilla The La Parrilla project site is situated in the Extremadura region of southwest Spain, in the Provinces of Caceres­Badajoz, approximately 310 km southwest of Madrid. The site has exceptional infrastructure in place,  which  is  accessed  directly  from  the  highway  along  a  3  km  asphalt  road  and  is  serviced  by electricity and water. The project comprises a tungsten mine and a tungsten tailings project. The mineral resource  estimated  by  Golder  in  February  2016  at  0.04%  WO3  cut­off  grade  is  51  million  tonnes  at 0.096% WO3 and 0.108 Sn, making it one of the largest tungsten deposits in the western world. Technical information in this report and on the W website has been prepared in accordance with the JORC Code and approved for inclusion by Mr Fernando de la Fuente, is a 'qualified person' in respect of the AIM Rules for Companies with  over  41  years'  experience  in  the  Exploration  and  Mining  Geology  industry.  Mr  de  la  Fuente  holds  a  B.Sc.  in Geology and an MSc in Geology from the University of Granada in Spain. He is also a member of the Spanish College of Geologists (Number 49), the Spanish Society of Mineralogy, founder member of the Spanish Society of Geology, member  of  the  Spanish  Association  of  Applied  Geology  to  Mineral  Deposits,  member  of  the  Society  for  Mining, Metallurgy and Exploration, Inc., member of PDAC.

 

 

This information is provided by RNS The company news service from the London Stock Exchange   END     UPDGGUUUMUPQPGB

http://www.investegate.co.uk/ArticlePrint.aspx?id=201607200700076705E

2/2