Fire Station #8 Relocation – Siting Process Community Meeting #1
St. Mary’s Episcopal Church June 25, 2015 from 7-9pm
Agenda Introductions (Doug Sarno) Opening Remarks (Mary Hynes, Arlington County Board) Relocating Fire Station #8 (Chief Schwartz, ACFD) Project Budget & Siting (June Locker, DES) Q&A Breakout Session – (Group Table exercise) Summary of Observations (Doug Sarno) Next steps (June Locker, DES) Wrap Up (Doug Sarno) 2
Community Engagement Sessions
Meeting #1 June 25th & July 9th (reprise)
• • • •
Overall issues & approach Clarify constraints and criteria Decision making process & timelines Feedback on potential sites, community concerns, constraints, values, and interests
Meeting #2 July 30, 2015
• Review previous meeting results • Additional input on potential site and opportunities and constraints to choosing alternative sites • Outline process for review of the sites
Meeting #3 September 9, 2015
• Review process & Present meeting results • Present recommendations to be submitted to the Board
3
Arlington County Fire Station System
3
8 6
10
4 2 1 5 9
7 4
Fire Station #2 4805 Wilson Blvd Arlington, VA 22203
5
Fire Station #3 4100 Old Dominion Dr Arlington, VA 22207
6
Fire Station # 5 1750 S Hayes St Arlington, VA 22202
7
Fire Station #7 3116 S Abingdon St Arlington, VA 22206
8
Fire Station #8 (current location) 4845 Lee Hwy Arlington, VA 22207
9
Fire Station Location Study Original study undertaken in 1999 by Gordon Routley to determine optimum location of fire stations That study was reviewed by Tri-Data as part of a larger Fire Department Management study in 2000 Updated study conducted in 2012 due to changes in population, service demand and planning and development Goal of 4 minutes National Standard – NFPA 1710 (National Fire Protection Association) 4 minutes for Fire and Basic Life Support EMS (90% of incidents) 8 minutes for Advanced Life Support (Paramedic) Measured from time of dispatch to time of arrival Response activity is driven almost entirely by population Vertical Response Time The time it takes responders to reach actual location of an incident after arriving at the street address 10
Fire Stations – Current 4 & 6 minute travel times
11
Why Relocate FS#8 Replacement identified in 2015-2024 CIP Does not meet current standards, major capital investment needed, space requirements not being met Relocating FS8 would enable Fire and EMS to reach many more North Arlington properties within the preferred response time of four minutes, resulting in improved safety and a more equitable emergency response time across the County. Medical attention within 4-6 minutes – example. cardiac arrest Approximately 1400 additional households would have response time of four minutes.
Arlington County Fire Trucks
12
Current Conditions of FS#8
Locker rooms
2 Bay Fire Station
Kitchen 13
Fire Station #8 Program Requirements 4 Bay stations Drive-through arrangement New program standards Decontamination & storage Workforce gender mix 24 hour shift
Fire Station #5 Template Building footprint & apron – 0.8 Acres Site – 0.7 Acres Wrap around drive aisle Surface parking for 12 spots 30 ft setback/buffer
14
Site Selection Criteria Criteria for relocating FS#8 is based on an independent analysis by TriData and guidance from Arlington County Board: An increase in the number of households reached in 4-6 minutes 1.5 acre site already owned by the County (or likely to come into the County's control expeditiously and at a feasible cost) Proximity to major arterial street(s) An appropriate distance from the Fairfax County line. The County seeks to assure, to the greatest extent possible, that the majority of service from any new location is to Arlington residents and the volume of work is distributed reasonably as to not effect volume of work within the existing Arlington County Fire Department Fire Station System.
15
Arlington County Fire Station System
3
8 6
10
4 2 1 5 9
7 16
2015-2024 CIP
Relocation of Fire Station #8 = $13M
20152024 CIP $21.1M
Relocation of Office of Emergency Management = $12.1
17
Relocation of OEM Program Requirements: ~ 12,000 SF of office space for County Staff Staff parking County will be evaluating a number of alternative location County Board has decoupled the two projects and will be evaluating the relocation of FS#8 first.
18
Potential Sites
The TriData study identified three potential sites meeting travel time criteria
19
Fire Station – Proposed 6-minute travel time
20
Breakout Session - Questions Are there any additional sites that the County should consider relocating FS#8 to which also meet the siting criteria: An increase in the number of households reached in 4-6 minutes 1.5 acre site already owned by the County (or likely to come into the County's control expeditiously and at a feasible cost) Proximity to major arterial street(s) An appropriate distance from the Fairfax County line. The County seeks to assure, to the greatest extent possible, that the majority of service from any new location is to Arlington residents and the volume of work is distributed reasonably as to not effect volume of work within the existing Arlington County Fire Department Fire Station System.
Are there other considerations /criteria the County should take into consideration when evaluating the relocation of FS#8?
21
Group – Siting Exercise
22
Observations from Table Discussion
What are we going to do with what we hear? Staff will conduct preliminary review of suggested sites & criteria. Share Results and request more feedback at Meeting #2, June 30th Please provide any additional feedback/suggestions by July 15th Suggestion Box @ the sign in table
23
Proposed Community Engagement Process
Process Kickoff June 2015
Community Engagement sessions June – September 2015
Summary of Findings with the Community Session Early September 2015
Recommendation to the Board Fall 2015
Site Specific Master Planning Process, Public Facilities Review Committee (PFRC)
Design & Construction Process
24
FS#8 Planning & Design Process Significant Community Review of development involvement impacts to include: Apply applicable County transportation, neighborhood, and plans & Policies to site environmental impacts Review by Public Facilities Review Committee (PFRC)
25
Key Takeaways Relocate FS8 to a site further north to increase response times to more households Community engagement process Inform citizens on the issues & challenges the County faces Obtain feedback on viable sites for FS8
26
Wrap up Upcoming meetings: Meeting #1 (reprise) on July 9th. Meeting #2 on July 30th
For latest project updates & Information: http://projects.arlingtonva.us/projects/fi re-station-8/ Please sign up for email alerts 27