New Jersey Office Of Clean Energy Direct Install Program Project: Township of Chester The total cost of the proposed project is: The NJ Clean Energy Incentive covers: The cost to your municipality is: The EECBG Rebate (not shown in the project details) covers: The total cost to your municipality, including the EECBG Rebate is:
$91,412.18 $54,847.30 $36,564.88 $36,564.88 $0.00
The estimated annual energy savings associated with this project is: Therefore, the estimated payback period for these measures is:
$21,617.93 0 months
Materials Needed For Project Submission: Scope Of Work Attachment - signed - 1 per facility Direct Install Contractor Agreement - signed X
Energy Efficiency and Conservation Block Grant Rebate Program Application Form - 2011
X
2011 Direct Install Program Application and Participation Agreement - signed - 1 per facililty Gas Bill - Winter 2010 - all pages attached Electric Bill - Summer 2010 - all pages attached
(60%) (40%) (40%) (0%)
Savings values are estimates. Actual savings will vary. Incentives and participation subject to program rules and Participation Agreement.
New Jersey Office of Clean Energy Direct Install Program Energy Assessment Tool
TRC Energy Services
General Project Information Participating Customer: Contractor / Project #: Facility Name: Street Address:
Township of Chester RJ Donnelly Municipal Complex 1 Parker Rd
Facility Type: Office- Large Total Facility Square Footage: Avg Weekly Hrs of Operation: # of Full-Time Employees:
City / Zip Code: Chester Will the project receive EECBG funding?:
Year Constructed: Tax Exempt?:
Y
ELECTRIC UTILITY INFORMATION
Y
GAS UTILITY INFORMATION
Electric Provider: <Select Electric Provider> Service Class: Account #: Billing Period Start Date: Billing Period End Date: Billing Period kWh Consumption: 1 Billing Period Total Cost: $0.17 Total Taxes + Fees on Bill:
Gas Provider: <Select Gas Provider> Service Class: Account #: Billing Period Start Date: Billing Period End Date: Billing Period Therm Consumption: 1 Billing Period Total Cost: $1.22 Total Taxes + Fees on Bill:
Project Summary Electric - Average Cost ($/kWh):
Gas - Average Cost ($/Therm):
$0.170 kWh Saved per Year
Annual Savings
Total Measure Estimated Total Cost to Cost Incentive Amount Customer
$1.22 Simple Payback (Yrs)
Refrigeration Measures Total:
15,407 $ $ 3,510 $ $
2,619.19 596.70 -
$ $ $ $
7,756.76 2,142.86 -
$ $ $ $
4,654.05 $ $ 1,285.71 $ $
3,102.70 857.14 -
1.18 1.44 -
TOTAL ELECTRIC MEASURES:
18,917 $
3,215.89
$
9,899.61
$
5,939.77
3,959.85
1.23
3,215.13
$
39,078.86
$
23,447.31
$ 15,631.54
4.86
Lighting Measures Total: Motors & VFD Measures Total: HVAC Electric Measures Total:
$
Therms /yr. TOTAL GAS MEASURES:
2,635 $ Gallons/yr.
TOTAL OIL MEASURES:
-
$
-
$
-
$
-
$
-
-
$
-
$
-
$
-
$
-
-
$
-
$
-
$
-
$
-
-
Oil Gallons/yr. Gas Therms/yr. -
CONVERSION MEASURES:
Gallons/yr.
(OIL TO GAS)
TOTAL PROPANE MEASURES:
-
COMBINED PROJECT TOTALS: $
6,431.02
$
48,978.47
$
29,387.08
$ 19,591.39
PROJECT TRC TEST:
Percentage of Energy Savings Per Measure Category
Lighting
Percentage of Dollar Savings Per Measure Category
HVAC
Lighting
Gas
Gas
2/8/2011
3.05 2.97
Percent Reduction in Total Energy Consumption
50.0%
HVAC
Project Summary
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
New Jersey Office of Clean Energy Direct Install Program Energy Assessment Tool Lighting Measures Default Annual Oper. Hours
Actual Annual Oper. Hrs
Fixture Location
(if different)
1
2,808
Council Chambers / Kitchen
2
2,808
Assistant to Assesor
3
2,808
Front Hallway
5
2,808
Mary's Office
6
2,808
Admin's Office
7
2,808
Copy Room
8
2,808
Bathroom
9
2,808
Closet
10
2,808
Vault
11
2,808
Stairwell (back)
12
2,808
Stairwell (back)
13
2,808
Planning
14
2,808
Planning Office
15
2,808
Bathroom
16
2,808
Construction
19
2,808
Attic
20
2,808
Basement
21
2,808
Basement #2
22
2,808
Basement #2
Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing
Fixture Controlled?
Lighting Measure Description
N Y N Y N N N N N Y N Y N Y N N N Y N N N N N N N Y N Y N Y N N N N N N N
Halogen Incandescent, (1) 50W lamp CF 9-1L SCREW IN CFL Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (4) 48", STD lamp 4' T8 4-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Incandescent, (1) 65W lamp CF 13-1L SCREW IN CFL Incandescent, (1) 65W lamp CF 13-1L SCREW IN CFL Fluorescent, (2) 96", STD lamp 8' T8 2-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Incandescent, (1) 65W lamp CF 13-1L SCREW IN CFL Fluorescent, (4) 48", STD lamp 4' T8 4-lamp with EB Fluorescent, (4) 48", STD lamp 4' T8 4-lamp with EB Incandescent, (1) 100W lamp CF 22-1L SCREW IN CFL Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Incandescent, (1) 100W lamp CF 22-1L SCREW IN CFL Incandescent, (1) 100W lamp CF 22-1L SCREW IN CFL Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (4) 48", STD lamp
Actual # of Default Ceiling Watts per Fix- Watts per Height Fixture (if tures Fixture >12 ft? different)
9 9 2 2 4 4 8 8 1 1 1 1 1 1 1 1 1 1 1 1 1 1 4 4 6 6 1 1 4 4 4 4 6 6 1 1 2 Lighting
2/8/2011
Total Cost
50 11 94 59 94 59 94 59 188 112 94 59 65 15 65 15 173 109 94 59 65 15 188 112 188 112 100 26 94 59 100 26 100 26 94 59 188
Est. Demand Annual kWh Savings Savings (kW)
Lighting Notes:
N
$
288.20
0.3
807
N
$
137.42
0.1
161
N
$
274.83
0.1
460
N
$
549.67
0.2
920
N
$
85.67
0.1
175
N
$
68.71
0.0
80
N
$
32.43
0.0
115
19A
N
$
32.43
0.0
164
19A
N
$
110.41
0.1
147
N
$
68.71
0.0
115
N
$
32.43
0.0
164
N
$
342.67
0.2
999
N
$
514.01
0.4
1,049
N
$
32.83
0.1
170
N
$
274.83
0.1
322
N
$
131.31
0.2
972
N
$
196.96
0.4
1,459
N
$
68.71
0.0
115
N
$
171.34
0.1
499
Municipal Building - MR-16
19A
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
22
2,808
23
2,808
25
2,808
29
2,808
31
2,808
33
2,808
35
2,808
36
2,808
Basement #2
Proposed Existing Basement #2 Proposed Existing Municipal Office - Exit Signs Proposed Existing Squad Room / Kitchen Proposed Existing Cells Proposed Existing Attic Proposed Existing Stairwell Proposed Existing Police Office - Exit Signs Proposed
N N N N N N Y N N N N N N N N
4' T8 4-lamp with EB Incandescent, (1) 100W lamp CF 22-1L SCREW IN CFL EXIT Incandescent, (2) 20W lamp LED EXIT Sign w/ Batt. Backup Incandescent, (1) 65W lamp CF 13-1L SCREW IN CFL Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Incandescent, (1) 100W lamp CF 22-1L SCREW IN CFL Incandescent, (1) 100W lamp CF 22-1L SCREW IN CFL EXIT Incandescent, (2) 20W lamp LED EXIT Sign w/ Batt. Backup
2 5 5 3 3 1 1 2 2 1 1 1 1 2 2
112 100 26 40 2 65 15 151 89 100 26 100 26 40 2
N
$
171.34
0.1
499
N
$
164.13
0.3
1,216
N
$
397.38
0.1
375
N
$
32.43
0.0
115
N
$
154.92
0.1
407
N
$
32.83
0.1
243
Y
$
42.93
0.1
243
N
$
264.92
0.1
250
$
4,503.07
3.2
11,743
TOTALS:
Flood
Lighting Controls Est. # of Annual Fixtures Hours Conw/o trolled Controls
Fixture Location
Est. Actual Annual Annual Hrs. w/ Hours Controls (if different)
Lighting Controls Measure Description
Reduced # of Total # of Annual Add'l Watts ConUnits Lighting Relays trolled Hours Needed
Total Cost
Est. Demand Annual kWh Savings Savings (kW)
1
2,808
9
Council Chambers / Kitchen
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
99
$
171.25
0.0
98
2
2,808
2
Assistant to Assesor
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
118
$
171.25
0.0
116
4
2,808
2
Tax Assesor's Office
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
178
$
171.25
0.0
175
6
2,808
1
Admin's Office
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
112
$
171.25
0.0
110
7
2,808
1
Copy Room
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
59
$
171.25
0.0
58
8
2,808
1
Bathroom
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
15
$
171.25
0.0
15
10
2,808
1
Vault
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
109
$
171.25
0.0
107
14
2,808
6
Planning Office
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
672
$
171.25
0.1
662
15
2,808
1
Bathroom
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
26
$
171.25
0.0
26
16
2,808
4
Construction
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
236
$
171.25
0.1
233
17
2,808
3
Construction Official
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
267
$
171.25
0.1
263
18
2,808
3
Emer. Management
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
267
$
171.25
0.1
263
24
2,808
6
Conference Room
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
534
$
171.25
0.1
526
26
2,808
1
Women's Room
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
62
$
171.25
0.0
61
Lighting 2/8/2011
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
26
2,808
1
Women's Room
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
62
$
171.25
0.0
61
27
2,808
4
Det Bureau
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
356
$
171.25
0.1
351
28
2,808
4
Lt Martini
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
356
$
171.25
0.1
351
29
2,808
1
Squad Room / Kitchen
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
15
$
171.25
0.0
15
32
2,808
2
Conference Room
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
178
$
171.25
0.0
175
34
2,808
1
Women's Locker
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
59
$
171.25
0.0
58
$
3,253.68
0.8
3,664
TOTALS:
Notes:
Lighting 2/8/2011
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
New Jersey Office of Clean Energy Direct Install Program Energy Assessment Tool Gas, Oil, and Propane HVAC Measures Climate Zone
Measure Location
Measure Description
Existing Oil-toAge of Unit Gas # of Existing Capacity Conver- Units Equipment (thousand (Yrs.) sion?
Total Cost
Natural Gas Savings (therms /yr)
BTU/hr)
1
Newark
Municipal - Attic
Gas-Fired Furnace
N
1
115
18
$
6,100.95
185.1
2
Newark
Municipal - Basment
Gas-Fired Furnace
N
2
115
17
$
12,201.90
370.3
3
Newark
Municipal - Basment
Gas-Fired Furnace
N
1
95
19
$
5,720.00
173.3
4
Newark
Police - Furnace Room
Gas-Fired Furnace
N
2
95
19
$
11,440.00
346.6
$
35,462.86
1,075.4
TOTALS
Notes:
HVAC 2/8/2011
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
New Jersey Office of Clean Energy Direct Install Program Energy Assessment Tool HVAC Control Measures Measure Description
Controlled Cooling OperaUnit # of Units Energy tionally Cooling Installed Efficiency Tested? Capacity Ratio (EER)
Measure Location
Annual kWh Savings
Total Cost
(Tons)
$
Measure Description
Annual HVAC Unit Fuel # of Units Capacity HVAC Fuel Usage Installed (thousand Source (therms,
Measure Location
BTU/hr)
1
-
Total Cost
gallons or KWh /yr)
-
Annual kWh Savings
Est. Demand Savings (kW) -
Nat. Gas Savings (therms /yr)
Municipal - Attic
1
115
Gas
2,000
$
602.67
-
260.0
Municipal - Basment
2
115
Gas
4,000
$
1,205.33
-
520.0
Municipal - Basment
1
95
Gas
2,000
$
602.67
-
260.0
4
Police - Furnace Room
2
95
Gas
4,000
$
1,205.33
-
520.0
5
Outside - Muni
3
60
Electric
15,000
$
1,071.43
1,950
Outside - Muni
1
48
Electric
4,000
$
357.14
520
Outside - Police
2
48
Electric
8,000
$
714.29
1,040
# of Units Installed
Annual HVAC Electric Usage (kWh)
Gas, Oil, Primary or LPG Fuel Usage Source for (therms or Heating gal./yr)
Total Cost
Annual kWh Savings
Nat. Gas Savings (therms /yr)
# of Units Installed
Days per Year Facility Operates
Hot Water Current Fuel Flow Rate Source (gal./min)
Total Cost
Annual kWh Savings
Nat. Gas Savings (therms /yr)
Pipe Diameter
Pipe Length
Total Cost
(inches)
(feet)
Annual kWh Savings
Nat. Gas Savings (therms /yr)
1,950
1,560.0
2 3
6
Electronic Fuel-Use Economizers (for Forced Air Heat)
Electronic Fuel-Use Economizers (for AC)
7
Measure Description
Measure Location
Hot Water Demand Control Measures Measure Description
Measure Location
Measure Description
Measure Location
TOTALS
Hot Water Fuel Source
Low or High Temp Piping?
$
4,687.43
Notes:
HVAC & HW Controls Measures 2/8/2011
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
Savings values are estimates. Actual savings will vary. Incentives and participation subject to program rules and Participation Agreement.
New Jersey Office of Clean Energy Direct Install Program Energy Assessment Tool
TRC Energy Services
General Project Information Participating Customer: Contractor / Project #: Facility Name: Street Address:
Township of Chester RJ Donnelly Telcordia Building 100 North Rd
Facility Type: Office- Large Total Facility Square Footage: Avg Weekly Hrs of Operation: # of Full-Time Employees:
City / Zip Code: Chester Will the project receive EECBG funding?:
07930 Y
Year Constructed: Tax Exempt?:
ELECTRIC UTILITY INFORMATION
Y
GAS UTILITY INFORMATION
Electric Provider: <Select Electric Provider> Service Class: Account #: Billing Period Start Date: Billing Period End Date: Billing Period kWh Consumption: 1 Billing Period Total Cost: $0.17 Total Taxes + Fees on Bill:
Gas Provider: <Select Gas Provider> Service Class: Account #: Billing Period Start Date: Billing Period End Date: Billing Period Therm Consumption: 1 Billing Period Total Cost: $1.22 Total Taxes + Fees on Bill:
Project Summary Electric - Average Cost ($/kWh):
Gas - Average Cost ($/Therm):
$0.170 kWh Saved per Year
Lighting Measures Total: Motors & VFD Measures Total: HVAC Electric Measures Total: Refrigeration Measures Total: TOTAL ELECTRIC MEASURES:
Annual Savings
Total Measure Estimated Total Cost to Cost Incentive Amount Customer
$1.22 Simple Payback (Yrs)
76,274 $ 12,966.51 $ $ $ -
$ $ $ $
38,711.80 -
$ $ $ $
23,227.08 $ 15,484.72 $ $ $ -
1.19 -
76,274 $
12,966.51
$
38,711.80
$
23,227.08
$ 15,484.72
1.19
2,220.40
$
3,721.90
$
2,233.14
$
0.67
Therms /yr. TOTAL GAS MEASURES:
1,820 $
1,488.76
Gallons/yr. TOTAL OIL MEASURES:
-
$
-
$
-
$
-
$
-
-
$
-
$
-
$
-
$
-
-
$
-
$
-
$
-
$
-
-
Oil Gallons/yr. Gas Therms/yr. CONVERSION MEASURES:
-
Gallons/yr.
(OIL TO GAS)
TOTAL PROPANE MEASURES:
-
COMBINED PROJECT TOTALS: $
15,186.91
$
42,433.70
$
25,460.22
$ 16,973.48
PROJECT TRC TEST:
Percentage of Energy Savings Per Measure Category
Percentage of Dollar Savings Per Measure Category
1.12 3.33
Percent Reduction in Total Energy Consumption
Gas
50.0%
Gas Lighting
2/9/2011
Lighting
Project Summary
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
New Jersey Office of Clean Energy Direct Install Program Energy Assessment Tool Lighting Measures Default Annual Oper. Hours
Actual Annual Oper. Hrs
Fixture Location
(if different)
1
2,808
Entrance
2
2,808
Reception
3
2,808
Council Room
4
2,808
Council Room
5
2,808
Back Entrance
6
2,808
Water Room
7
2,808
Closet Behind Desk
8
2,808
Hallway
9
2,808
Hallway
10
2,808
Men's Room
11
2,808
Men's Room
12
2,808
Women's Room
13
2,808
Women's Room
14
2,808
NJDEP
15
2,808
Office (rt)
16
2,808
Office (rt 2)
17
2,808
Office (left)
18
2,808
Men's Room
19
2,808
Side Entrance
Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing
Fixture Controlled?
Lighting Measure Description
N N N N N N N N N N N Y N Y N N N N N N N N N N N N N N N Y N Y N N N N N
Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (1) 48", STD lamp 4' T8 1-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (2) U-Tube, STD lamp
Actual # of Default Ceiling Watts per Fix- Watts per Height Fixture (if tures Fixture >12 ft? different)
2 2 6 6 30 30 10 10 1 1 1 1 1 1 13 13 1 1 2 2 2 2 2 2 2 2 8 8 4 4 4 4 8 8 1 1 2 Lighting
2/9/2011
Total Cost
96 31 96 31 96 31 57 31 151 89 96 31 96 31 96 31 151 89 96 31 151 89 96 31 151 89 188 83 151 89 151 89 151 89 96 31 96
62 62 62
62 62 62
62
62
62
Est. Demand Annual kWh Savings Savings (kW)
N
$
157.17
0.1
223
N
$
471.51
0.2
670
N
$
2,357.53
0.8
3,351
N
$
664.97
0.2
854
N
$
77.46
0.0
204
N
$
78.58
0.0
78
N
$
78.58
0.0
78
N
$
1,021.60
0.4
1,452
N
$
77.46
0.0
204
N
$
157.17
0.1
223
N
$
154.92
0.1
407
N
$
157.17
0.1
223
N
$
154.92
0.1
407
N
$
1,114.42
0.7
2,760
N
$
309.83
0.2
570
N
$
309.83
0.2
570
N
$
619.66
0.4
1,630
N
$
78.58
0.0
112
N
$
157.17
0.1
223
Lighting Notes:
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
19
2,808
Side Entrance
20
2,808
Office (rt)
21
2,808
Office (left)
22
2,808
Office (rt 2)
23
2,808
Office (left 2)
24
2,808
Office (left 3)
25
2,808
Office (left 4)
26
2,808
Copy Room
27
2,808
Office (rt 3)
28
2,808
Office (left 5)
29
2,808
Office (rt 4)
30
2,808
Women's Room
31
2,808
End of Office Pool
32
2,808
End of Office Pool
33
2,808
Basement (copy)
34
2,808
Basement (copy)
35
2,808
Kitchen
36
2,808
Stairwell to basement
37
2,808
Boiler Room
38
2,808
Shower
39
2,808
Basement (copy)
40
2,808
Water Treatment
41
2,808
Equip Room
42
2,808
Equip Room
43
2,808
Hallway
44
2,808
Hallway
Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing Proposed Existing
N N Y N Y N Y N Y N Y N Y N Y N Y N Y N Y N N N N N N N N N N N N N N N N N N N N N N N N N N N N N
2' T8 U-Lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (3) 48", STD lamp 4' T8 3-lamp with EB Incandescent, (1) 65W lamp CF 13-1L SCREW IN CFL Incandescent, (1) 120W lamp CF 26-1L SCREW IN CFL Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Incandescent, (1) 120W lamp CF 26-1L SCREW IN CFL Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (2) 96", STD lamp 8' T8 2-lamp with EB Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (2) U-Tube, STD lamp
2 4 4 4 4 4 4 4 4 4 4 4 4 2 2 4 4 4 4 4 4 1 1 2 2 6 6 4 4 12 12 2 2 2 2 3 3 1 1 3 3 2 2 8 8 2 2 2 2 7 Lighting
2/9/2011
31 151 89 151 89 151 89 151 89 151 89 151 89 151 89 151 89 151 89 151 89 151 89 96 31 151 89 65 15 120 28 94 59 94 59 120 28 94 59 188 83 188 83 94 59 173 109 188 83 96
62
62
N
$
157.17
0.1
223
N
$
309.83
0.2
570
N
$
309.83
0.2
570
N
$
309.83
0.2
570
N
$
309.83
0.2
570
N
$
309.83
0.2
570
N
$
309.83
0.2
570
N
$
154.92
0.1
285
N
$
309.83
0.2
570
N
$
309.83
0.2
570
N
$
309.83
0.2
570
N
$
77.46
0.0
204
N
$
157.17
0.1
223
N
$
464.75
0.3
1,222
N
$
129.70
0.2
657
19A
N
$
434.94
0.9
3,627
R30
N
$
137.42
0.1
230
N
$
137.42
0.1
230
N
$
108.73
0.2
907
N
$
68.71
0.0
115
N
$
417.91
0.3
1,035
N
$
278.60
0.2
690
N
$
549.67
0.2
920
N
$
220.82
0.1
421
N
$
278.60
0.2
690
N
$
550.09
0.2
782
Long hallway of offices
R30
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
44
2,808
45
2,808
46
2,808
47
2,808
48
2,808
49
2,808
50
2,808
51
2,808
52
2,808
53
2,808
54
2,808
55
2,808
56
2,808
57
2,808
58
2,808
59
2,808
60
2,808
61
2,808
62
2,808
63
2,808
64
2,808
Hallway
Proposed Existing Room Left Proposed Existing End Room Proposed Existing Room Right Proposed Existing Air Handler Room Proposed Existing Open Room (front) Proposed Existing Closet Proposed Existing Back Room Proposed Existing Generator Room Proposed Existing Generator Room Proposed Existing Side Hallway Proposed Existing Rescue Squad - First Room Proposed Existing Rescue Squad - Office Proposed Rescue Squad - Meeting Existing Rooom Proposed Existing Recscue Squad Garage Proposed Existing Recscue Squad Garage Proposed Existing Rescue Squad - Kitchen Proposed Existing Boiler Room #2 Proposed Existing Parts Room Proposed Existing Food Pantry Proposed Existing Exit Signs Proposed
N N N N N N N N N N N N N N N N N N N N N N N N Y N N N N N N N N N N N N N N N N
2' T8 U-Lamp with EB Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (4) 48", STD lamp 4' T8 3-lamp with EB plus reflector Fluorescent, (2) U-Tube, STD lamp 2' T8 U-Lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (2) 96", STD lamp 8' T8 2-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Incandescent, (1) 120W lamp CF 26-1L SCREW IN CFL Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB Fluorescent, (2) 48", STD lamp 4' T8 2-lamp with EB EXIT Incandescent, (2) 20W lamp LED EXIT Sign w/ Batt. Backup
7 18 18 6 6 16 16 2 2 9 9 1 1 14 14 5 5 1 1 2 2 14 14 4 4 18 18 6 6 17 17 2 2 2 2 21 21 24 24 13 13
31 188 83 188 83 188 83 94 59 188 83 188 83 188 83 188 83 96 31 94 59 94 59 94 59 94 59 94 59 173 109 94 59 120 28 94 59 94 59 40 2
62
62
N
$
550.09
0.2
782
Y
$
2,908.81
1.5
6,209
N
$
835.81
0.5
2,070
N
$
2,228.84
1.3
5,519
N
$
137.42
0.1
230
N
$
1,253.72
0.8
3,105
N
$
139.30
0.1
345
N
$
1,950.23
1.2
4,829
N
$
696.51
0.4
1,725
N
$
78.58
0.0
112
N
$
137.42
0.1
230
Y
$
1,234.63
0.4
1,610
N
$
274.83
0.1
322
N
$
1,236.76
0.5
2,070
Y
$
529.13
0.2
690
Y
$
2,323.44
0.9
3,574
N
$
137.42
0.1
230
N
$
72.49
0.1
605
N
$
1,442.88
0.6
2,415
N
$
1,649.01
0.7
2,760
N
$
1,721.97
0.4
1,623
$
36,143.10
18.1
71,884
TOTALS:
R30
Lighting Controls Est. # of Annual Fixtures Hours Conw/o trolled Controls 6
2,808
1
Fixture Location
Water Room
Est. Actual Annual Annual Hrs. w/ Hours Controls (if different) 1,966
Lighting Controls Measure Description
Reduced # of Total # of Annual Add'l Watts ConUnits Lighting Relays trolled Hours Needed
Dual Tech Occ. Sensor Wall Switch
1 Lighting
2/9/2011
842.40
62
Total Cost
$
171.25
Est. Demand Annual kWh Savings Savings (kW) 0.0
61 Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
6
2,808
1
Water Room
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
62
$
171.25
0.0
61
7
2,808
1
Closet Behind Desk
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
62
$
171.25
0.0
61
15
2,808
4
Office (rt)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
356
$
171.25
0.1
351
16
2,808
4
Office (rt 2)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
356
$
171.25
0.1
351
20
2,808
4
Office (rt)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
356
$
171.25
0.1
351
21
2,808
4
Office (left)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
356
$
171.25
0.1
351
22
2,808
4
Office (rt 2)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
356
$
171.25
0.1
351
23
2,808
4
Office (left 2)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
356
$
171.25
0.1
351
24
2,808
4
Office (left 3)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
356
$
171.25
0.1
351
25
2,808
4
Office (left 4)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
356
$
171.25
0.1
351
26
2,808
2
Copy Room
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
178
$
171.25
0.0
175
27
2,808
4
Office (rt 3)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
356
$
171.25
0.1
351
28
2,808
4
Office (left 5)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
356
$
171.25
0.1
351
29
2,808
4
Office (rt 4)
1,966
Dual Tech Occ. Sensor Wall Switch
1
842
356
$
171.25
0.1
351
56
2,808
4
Rescue Squad - Office
1,966
Dual Tech Occ. Sensor Wall Switch
1
842.40
236
$
171.25
0.1
233
$
2,568.70
1.0
4,390
TOTALS:
Notes:
Lighting 2/9/2011
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.
New Jersey Office of Clean Energy Direct Install Program Energy Assessment Tool HVAC Control Measures Measure Description
Controlled Cooling OperaUnit # of Units Energy tionally Cooling Installed Efficiency Tested? Capacity Ratio (EER)
Measure Location
Annual kWh Savings
Total Cost
(Tons)
$
Measure Description
Annual HVAC Unit Fuel # of Units Capacity HVAC Fuel Usage Installed (thousand Source (therms,
Measure Location
BTU/hr)
1 2
Electronic Fuel-Use Economizers (for Hot Water Heat)
Measure Description
-
-
Annual kWh Savings
Total Cost
gallons or KWh /yr)
Est. Demand Savings (kW) -
Nat. Gas Savings (therms /yr)
Boiler Room
1
1,281
Gas
8,000
$
1,860.95
-
1,040.0
Boiler Room #2
1
980
Gas
6,000
$
1,860.95
-
780.0
# of Units Installed
Annual HVAC Electric Usage (kWh)
Gas, Oil, Primary or LPG Fuel Usage Source for (therms or Heating gal./yr)
Total Cost
Annual kWh Savings
Nat. Gas Savings (therms /yr)
# of Units Installed
Days per Year Facility Operates
Hot Water Current Fuel Flow Rate Source (gal./min)
Total Cost
Annual kWh Savings
Nat. Gas Savings (therms /yr)
Pipe Diameter
Pipe Length
Total Cost
(inches)
(feet)
Annual kWh Savings
Nat. Gas Savings (therms /yr)
Measure Location
Hot Water Demand Control Measures Measure Description
Measure Description
Measure Location
Measure Location
TOTALS
Hot Water Fuel Source
Low or High Temp Piping?
$
3,721.90
-
1,820.0
Notes:
HVAC & HW Controls Measures 2/9/2011
Direct Install Energy Assessment Tool (ver. 5.0) ©2010 TRC Energy Services. Property of TRC. Contractor granted limited license.