Nutana Slope Failure

Report 2 Downloads 10 Views
2012 to Present:

2012

2013

Causes of the Failure 1

GEOLOGY

Weak soil

2

GEOMETRY

Steep slope

3

GROUND WATER

High water table due to increased precipitation

Causes of the Failure:

11th St Cherry Lane

1

GEOLOGY

2

GEOMETRY

3

GROUND WATER

Sask Cres GROUND WATER LEVEL

SLIP PLANE

10 Year Average Rainfall - Saskatoon

Groundwater Levels - Saskatoon

Status of Slope

• Not stable

Movement Possible

• Continued movement toward Sask Cres

Remediation Options

• Conceptual only •

Target: 50% MORE stabilizing force

• 4 general options evaluated No Movement

Option 1 • Do Nothing • Continued movement • Risk increases as groundwater increases

• Slide area will expand in time

Option 2 • Address

3

GROUND WATER

• Install dewatering trenches (11th St & Cherry Lane)

Option 2

GROUND WATER LEVEL

SLIP PLANE GROUND WATER LEVEL

Option 2 • Address

3

GROUND WATER

• Install dewatering trenches (11th St & Cherry Lane)

• Doesn’t meet stability target (only 20%)

Option 3: • Address

3

GROUND WATER

• Flatten the slope • Meets 50% stability target

AND

2

GEOMETRY

FORCES PULLING SLOPE DOWN FORCES HOLDING SLOPE UP

Option 3:

SLIP PLANE GROUND WATER LEVEL

Possible Remediation OPTION 3 Affected area

Option 3: • Address

3

GROUND WATER

• Flatten the slope • Meets 50% stability target

AND

2

GEOMETRY

FORCES PULLING SLOPE DOWN FORCES HOLDING SLOPE UP

• Significant disruption to private lots

Option 4: • Address

3

GROUND WATER

• “Shear zone replacement” • Meets 50% stability target

• Keeps houses in place

AND

1

GEOLOGY

FORCES PULLING SLOPE DOWN FORCES HOLDING SLOPE UP

Option 4:

Possible Remediation OPTION 4 Affected area

Option 4: Possible Remediation OPTION 4:

• Address

3

GROUND WATER

• “Shear zone modification” • Meets 50% stability target

• Keeps houses in place

AND

1

GEOLOGY

FORCES PULLING SLOPE DOWN FORCES HOLDING SLOPE UP

Remediation Summary: OPTION 1) Do Nothing

PROS

3) Re-Grade Slope



Does not meet target stability

$4.5M

Meets stability target • Reduced long term • risk

Significant disruption Removal of structures

$6.5 – 10M

Meets stability target Maintains structures

Difficult to construct Costly

$10 – 20M



Minimal disturbance Lowers “wet year” risk

(and lower water table)



4) Shear Zone Modification



(and lower water table)

HIGH risk of continued failure

No cost





ESTIMATED COST





2) Lower Water Table •

CONS

• •

$0

Independent Review: Clifton Associates

• Independent analysis of the data • Purpose: To confirm remediation options • Conclusions: •

Agree on methodology

Verified  the problem is large and • Differing interpretation of data  even less stable costly to resolve • Remediation options feasible but may be even more costly

Public Safety Continues to be primary focus of the

• Continue detailed monitoring

• Provide residents with everything we know • Evacuation Alert