ORANGE COUNTY GREAT PARK INTERIM INFRASTRUCTURE CAPITAL IMPROVEMENT PROJECT
2
Presentation Topics • Amended and Restated Master Implementation Agreement (ARMIA) Backbone Infrastructure Projects • Adjacent Landowner Agreement I modified three roadway project schedules • Adjacent Landowner Agreement II (Great Park Improvement Area – 688-acre project) • Interim Infrastructure Capital Improvement Project (today’s item 2.1)
3
ARMIA Backbone Infrastructure Projects Project
Status/Project Impact
Reach “A” Sewer Construction
Affects Marine Way Entrance
Raceway Storm Drain Construction
Affects Marine Way Entrance
Continuation of Reach “B” Sewer and Storm Drain Construction
Affects Access to Park via 5th Street
4
6
7
Trabuco Road 5th Street
C Street
Runway Access
Taxiway Access
8
Runway Access
Trabuco Road 5th Street
XX C Street
Taxiway Access
9
Adjacent Landowner Agreement I Projects Project
Status/Project Impact
Trabuco Road Construction
Currently Provides Park Access for Large Park Events
“O” Street Road construction
Will Affect Marine Way Entrance
First Phase of Marine Way Road Construction
Will Affect Marine Way Entrance
10
Adjacent Landowner Agreement II Great Park Improvement Area Project (688-acre Park Plan) 1. Upper Bee Canyon 2. Bosque 3. Agriculture/Golf Course 4. Sports Park 5. Wildlife Corridor
11
UPPER BEE CANYON 36 AC
BOSQUE 41 AC
AGRICULTURE/ GOLF COURSE 259AC
SPORTS PARK 176AC
WILDLIFE CORRIDOR 178AC
12
Construction Phases Phase One (June 2014) • Upper Bee Canyon • Bosque • Sports Park
Phase Two (June 2016) • Agriculture/Golf Course
13
Proposed Interim Infrastructure CIP Proposed Great Park Interim Infrastructure CIP will include the following six improvements: 1. 2. 3. 4. 5. 6.
Alternative Access Construction Fence Water Relocation Sewer Holding Tank Reclaimed Water Relocation Storm Drain Relocation
14
X
X
X
X
15
Alternate Access
16
17
Special Event Parking
7L
7R
Alternative Access
18
Alternate Access to Taxiway
“L” Street
Phase One Construction Fence Existing Construction Fence
New Construction Fence
19
Potable Water Relocation Potable Water Relocation
20
Sewer Holding Tank
Sewer Holding Tank
21
Reclaimed Water Relocation Temporary Irrigation Water Connection
Reclaimed Water Relocation
22
Storm Drain Relocation
Storm Drain Relocation
23
24
CIP Objectives Approval of Proposed Great Park Interim Infrastructure CIP will accomplish the following: • Keep Great Park utilities operational along with Park ingress and egress access during FivePoint Communities demolition, grading and construction of the 688-acre Park Plan • Facilitate FivePoint Communities demolition, grading and construction projects for the 688acre Park Plan
25
Recommended Action 1. Recommend that the City Council establish a new Capital Improvement Project and approve the attached budget adjustment appropriating $150,000 for design services from the Orange County Great Park Fund 180 balance, for design services for interim infrastructure at the Orange County Great Park.