Parkridge Neighbourhood Traffic Review

Report 4 Downloads 233 Views
Parkridge Neighbourhood Traffic Review Thursday, April 21, 2016 7:00pm - 9:00pm

transportation division

1

Outline • • • • •

Neighbourhood Traffic Review Process Parkridge Review Schedule Sources of Information Past Concerns Received Description of Traffic Calming & Pedestrian Safety Devices • Blairmore Concept Plan • Corridor Reviews & Major Intersection Reviews 2

Neighbourhood Traffic Review Process • August 2013 – New process • Mandate – Reduce and calm traffic, improve safety within neighbourhoods • 2014 – 11 neighbourhoods • 2015 – 8 neighbourhoods • 2016 – Parkridge, Sutherland, Willowgrove, Stonebridge, Hampton Village, Grosvenor Park, Silverspring, Lakeridge 3

Parkridge Review Schedule • Stage 1 – Identify issues and possible solutions through community consultation (April to Fall 2016) • Stage 2 – Develop a draft traffic plan • Stage 3 – Present draft traffic plan to community for feedback (Fall 2016) • Stage 4 – Implement changes over time (Beginning Spring 2017)

4

Sources of Information • • • •

Past Studies Collision Analysis Feedback from Public Consultation Traffic Counts & Assessments

5

Past Concerns Received • • • • •

Speeding – McCormack Road, Gropper Crescent Fairlight Drive & McCormack Road / Pendygrasse Road 22nd Street & Diefenbaker Drive 22nd Street & Confederation Drive Lack of access into Blairmore

6

Recommendations

7

Speed Display Board

8

Curb Extension

9

Raised Median Island

10

Roundabout

11

Diverter 12

Right In / Right Out Island

13

Directional Closure

14

Raised Median Through Intersection

15

Full Closure 16

Standard Crosswalk

17

Zebra Crosswalk

18

Active Pedestrian Corridor

19

Pedestrian Actuated Signal

20

Blairmore Concept Plan • In September 2005, City Council approved Blairmore Concept Plan o o

April 2005 Public Meeting June 2005 Open House

• In December 2013, City Council approved Blairmore Concept Plan Amendment (Parkridge Extension) o

June 2013 Public Information Meeting 21

Corridor Reviews & Major Intersection Reviews • Created to address issues at intersections along arterial streets as Neighbourhood Traffic Reviews addresses local and collector streets • Recommendations will be identified and projects will be prioritized for funding approval • Report will be presented to City Council 22

Traffic Issues in Parkridge Seeking Your Ideas and Solutions!

23

Table Group Discussions 1. What ideas or solutions do you have to improve traffic flow/safety in your neighbourhood (what’s working or not working)? 2. Identify additional traffic issues and solutions in Parkridge.

24

Next Steps 1. 2. 3.

Continue monitoring traffic issues in your neighbourhood Mail-in or email comments no later than May 20, 2016 Additional public input via City on-line Community Engagement webpage no later than May 20, 2016 http://shapingsaskatoon.ca/discussions/parkridgeneighbourhood-traffic-review

4. 5. 6. 7. 8.

Traffic & pedestrian data collection, analysis Develop recommendations and prepare draft Traffic Plan Follow-up public input meeting to provide input on draft Determine revisions and finalize Traffic Plan Present Traffic Plan to City Council for approval

25

For more information and status updates visit: www.saskatoon.ca Search “Neighbourhood Traffic Reviews”

26

Thank You!

transportation division

27