Potential Conflict – CMAR And Design Professionals Competition/Self-Performed Work – Collusion Potential Single Source Responsibility/Fewer Checks and Balances Transparency/Requires Expertise to Effectively Use Administrative Costs of Oversight Use of Allowances Shift Risk Back Project Delivered at “Actual Cost”??
COST OF WORK AND GENERAL CONDITIONS Cost of The Work includes Everything That Goes Into The Construction of the Project and the Persons Who Put Them There… e.g. The Bricks and Bricklayer, the Stones and Stone Mason etc.
General Conditions: The Contractor’s Costs at the Job Site e.g. Job Site Trailer, toilet facilities and dumping, Superintendent, on site Secretarial, office supplies etc.
PROCUREMENT & CONTRACTING BEFORE ISSUING PROCUREMENT DOCUMENTS Establish Written Procedures for:
Approval of Contingency Use and Change Orders Bidding of Self-Performed Work to Assure Actual Competition; Requirements to Assure “Apples to Apples” Comparison and Transparency Bidding And Project Bid Review and Performance of “Excluded Tasks” in Bids Decide on Criteria and Weight of Criteria What are District’s Priorities? What is Required? What Do You Need to Know Specific To this Project? Use of Savings Realized At Buyout and During Project
PROCUREMENT & CONTRACTING CMAR PROCUREMENT – TX GOV’T CODE SEC. 2269.251 Complete Construction Documents Not Required One Or Two Step Procurement ONE STEP: RFQ With Pricing Requested GC’s -> Percentage Of Cost Of Work or Monthly Fee Fee -> Percentage of Cost of Work
TWO STEP: Step One: Request For Qualifications - Short List (Optional) Step Two: Pricing As In One Step
PROCUREMENT & CONTRACTING CMAR PROCUREMENT – TX GOV’T CODE SEC. 2269.251 Proposals Opened – Names Read Aloud Proposals Evaluated and Ranking Recommended To Board Contract Negotiations With First Ranked (As Approved) If No Contract Reached -> Cut Off In Writing and Move To
Normally Pre-Construction Fee is Part of Construction Phase Unless Construction Does Not Commence
Public Advertisement For Bids and Evaluation (with Owner) Guaranteed Maximum Price Proposal
Detailed Summary Based On Schedule of Values Exclusion and Assumptions (Check for Contract Modifications) List of Drawings and Specifications on Which GMP Based Substantial Completion Date and Liquidated Damages Names of Subs and Self-Performed Work Identified
GMP PROPOSAL AND AMENDMENT GMP = Cost of Work + CMAR Fee + General Conditions (if NOT included in Cost of Work
Written Amendment Signed Establishing the GMP and Incorporating All Information On Which It Is Based
Construction Phase Does Not Begin Until GMP is Approved and GMP Amendment Signed by All Parties. Any Procedures Not Included in Master Contract Should Be Added Into GMP Amendment