Ponds for Wastewater Treatment

Report 48 Downloads 269 Views
Ponds

for Wastewater Treatment

Gilles Altner Global Environmental Engineering Ltd

The Pond System

Pre Treatment

Anaerobic Pond

Facultative Pond

Maturation Pond

Rock Filter

Sand Filter

Wetland

Membranes

UV

g2e

Overview 1. Facultative & aerated ponds: How do they work? (Facultative, aerated, media ponds)

2. design aspects aspects & & upgrade upgrade technologies technologies. 2. Pond Pond design (Sludge, inlet, outlet, buffering, hydraulic, aeration, mixing, curtain, media)

3. Consents for for ponds. ponds 3. Resource Resource Consents (Ponds versus high rate treatment plants)

4. Other pond issues.

5. the pond will not do anymore. 5. When Other pond issues (Turning the pond into something else)

g2e

Overview 1. Facultative & aerated ponds: How do they work? (Facultative, aerated, media ponds)

g2e

Waste Stabilization Ponds The Facultative Pond Sunlight Wind (mixing & aeration) O2 (daylight hours)

O2 Re-aeration

Settleable solids Bottom sludge Organic wastes

CO2

1.2 to 5 m

Algae

New Cells

Wastewater

If oxygen is not present in upper layer of pond, odorous gases can be released H2S

NH3, PO43, etc O2

NH3, PO43, etc

Dead Cells

T (temperature)

CO2 H2S + 2O2

Bacteria

H2SO4

New Cells • ANAEROBIC PONDS Dead Cells

• FACULTATIVE PONDS CO + NH + H S + CH

Organic acids, alcohols

2

3

2

• MATURATION PONDS

4

Aerobic Aerobic Zone Zone 0.3 to 0.6m Facultative / Anoxic Facultative Zone 0.5 to 0.8m Anaerobic Anaerobic Zone Zone 0.1 to 0.3m

g2e

Waste Stabilization Ponds • FACULTATIVE PONDS: For domestic and mixed loading Depth 1.5 to 2m, HRT 20 to 60 days, in NZ up to 90 days Up to 80% BOD, in theory up to 80% Am-N reduction (T !!) In theory up to 90% TN reduction, not in New Zeand At temperatures 20 to 25 dgrC, BOD load 100 - 400 kgBOD/ha/day

• Sludge AEROBIC, FLOW about THROUGH PONDS 3/yr/l/sec or about 10mm/yr production 5 to 7 m 2 to 5 m deep, HRT 3 to 5 days, partially / completely mixed

High TSS & BOD loading, no Am-N or TN reduction Temperature dependant, BOD load 100 to 350 kgBOD/m3/day

• AEROBIC PONDS WITH SOLIDS RECYCLE Depth 1 to 1.5m, HRT 5 to 10 days Some BOD, some Am-N reduction, some TN reduction, but mainly TSS (algae) reduction and disinfection

g2e

Waste Stabilization Ponds • AERATED PONDS, with or without solids return Generally 3m+ deep, HRT 1 to 3 d, 1d, 1d, 1d to limit algae growth MLSS of about 400 mg/l, no algae, TN reduction only if recycle Power for aeration and mixing 6W/m3 first, 1 to 1.5 W/m3 others Sludge production +/- 40m3/yr/l/sec (= 6 to 7 times normal pond)

Treatment BOD < 20 mg/l TSS < 30 mg/l

Aerated & partially / complete mixed Lagoon

Series of low power aerated Lagoons

Am-N < 5 mg/l TN < 15 mg/l

g2e

Waste Stabilization Ponds • PONDS with GROWTH MEDIA: Advanced treatment 1.5 to 3m+ deep, HRT 20 days+, less possible MLSS low, but high TSS (biomass growth), aeration required

BOD5< 15mg/l, Am-N< 1 mg/l, TN< 10 mg/l Sludge production 5 to 7 m3/yr/l/sec (10mm/year) Algae

New Cells

NH3, PO43, etc O2

NH3, PO43, etc

Dead Cells

CO2

Biomass

Aerobic Zone

T (temperature)

Bacteria New Cells Dead Cells

O2

O2

O2

Facultative Zone Anaerobic Zone

g2e

Overview 1. Facultative & aerated ponds: How do they work? (Facultative, aerated, media ponds)

2. Pond design aspects & upgrade technologies (Sludge, inlet, outlet, buffering, hydraulic, aeration, mixing, curtain, media)

4. Other pond issues.

5. the pond will not do anymore. 5. When Other pond issues (Turning the pond into something else)

g2e

The Typical New Zealand Pond  

0 0

Sludge Level Two pond system Up to 1.3m 100m x 90m x 1.4m (90% waterx depth) 100m of x 60m 1.8m

WETLANDS 10

10

20

20

30

30

50

50

60

60

70

70

POND 1

80

80 90

10

10

POND 1

0

0

Inlet

20

20

150m x 60msolids plus with pond 110m x 80m and plant overgrowth

40

40

Wetlands  Wetland clogged

Aerator

30

30

40

50 60 70

90

  

POND 2

80

 Odours Poor flow conditions  Algae blooms

40

Aerator

Wetland failure HRT Discharge out of RC Theoretical: 25 days True : 8 days

g2e

Outlet

Simple Pond Improvements Maintaining & Improving Biological / hydraulic load

Reduce shock loads & hydraulic peaks Costs, community & industry input

Desludging

Regain HRT Costs, damage, disposal, verification

Inlet / outlet design

Increase HRT, use flow buffering Available freeboard, waveband material

Dividing curtains / barriers

Prevent short-circuiting Design, quality of materials used

Aeration / mixing / DO

Reduce odours and overloading

Basic improvements

Type, Get them water right depth, ! purpose, power

g2e

Simple Pond Improvements

g2e

Advanced Pond Improvements What has to be achieved? Dividing ponds

Improve treatment efficiency What type of pond? HRT

Heighten the embankment

Increase HRT, prepare for the future What for? Costs

Rockfilter (aer/non-aer)

Improve TSS, BOD5, Am-N and TN Costs, design, references !!

Growth media

Increase BOD5, Am-N, TN treatment Costs, aeration required, HRT

Floating wetlands

Improve TSS, BOD5 (TN, TP), ((Am-N)) Site data, site specific, costs, quality

g2e

Growth Media Carbon black sleeve with floatation tube. Mats are connected to stainless steel wires attached on each side of the treatment pond

Lower UltraWeave layer Upper UltraWeave layer promotes growth of promotes bacterial sessile algae and higher biofilms & acts as hydraulic barrier for organisms for uptake of DRP and ammonia BOD5 and TSS removal

g2e

Growth Media Installed

Aerobic Zone

Air release at >200 mbar dP Biomass Support Media

Air flow

g2e

Typical results at start-up

g2e

Floating Wetlands

Floating wetlands 2012 fits all ’’ Floating wetlands installation Know what you need –shortly avoidJanuary ’’after one system

g2e

Example 1: Ponds not achieving RC 

Domestic & Industriel Flow: 680  960 m3/d Peak: 1,600 m3/d BOD5 175 kg/d TKN 43 kg/d

WETLANDS

POND 1

Inlet



Treatment Required TSS/BOD5 < 20 mg/l TKN < 6 mg/l Am-N < 3 mg/l TP < 3 mg/l

POND 2

g2e

Outlet

Example 1: Ponds not achieving RC > Insufficient HRT

2.6m

2.3m 1.4m

1.6m

POND 1

POND 2

g2e

Example 1: Pond not achieving RC > Improve treatment 

Improve flow at inlet, transfer & outlet WETLANDS



Automatic screening & flow metering

 Aeration

& mixing in inlet area



Biological growth media & aeration



Alkalinity dosing & Fe dosing for TP reduction

g2e

Overview 1. Facultative & aerated ponds: How do they work? (Facultative, aerated, media ponds)

2. design aspects aspects & & upgrade upgrade technologies technologies. 2. Pond Pond design (Sludge, inlet, outlet, buffering, hydraulic, aeration, mixing, curtain, media)

3. Resource Consents for ponds (Ponds versus high rate treatment plants)

4. Other pond issues.

5. the pond will not do anymore. 5. When Other pond issues (Turning the pond into something else)

g2e

Resource Consents for Ponds Ponds Versus High Rate Treatment Plants HRT

Pond: 20 – 80 days, HRTP: hours  Increase sampling frequency

Discharge Quality

Pond: day/night, season, HRTP: stable  Time / season related requirements

Discharge Flows

Pond: precipitation, HRTP: no influence

Floating wetlands

Increase treatment  Weather / streamcapacity level dependent

(Rockfilter Capacity aer./non-aer.) Treatment

Target Incrementally TN and TP reduction Pond: upgradable HRTP: Built for T0 + 20 yrs Target TSS & organics discharge  Staged upgrade consents Reduce TSS & organics loading Review overseas experience Reduce BOD TN, TP specific 5, TSS,be Conditions should pond

Install Ultrasound Install trickling filter Disposal to land Install interm. sandfilter Resource Consents

g2e

Pond System Upgrades It is possible !

Questions ? g2e