Question/Description of Issue: Please confirm the clouded dimension in attached SK-01. Because, as per wall to wall dimensions on A1.0 & all the approved joist spacing we get 2'-8 3/4" for this bay. Suggestion: Attachments: SK-01 Potential Cost Impact:
Unknown
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 003
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: We just moved joist substitudes 6" typically for staggering joists in attached SK-02. Suggestion: Attachments: SK-02 Potential Cost Impact:
Unknown
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 004
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: We just moved J19 & J20 joists 6" typically for staggering joists in attached SK-03. Suggestion: Attachments: SK-03 Potential Cost Impact:
Unknown
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 005
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: We just moved joist substitudes 6" for staggering joists in attached SK-04. Suggestion: Attachments: SK-04 Potential Cost Impact:
Unknown
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 006
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: We just moved J40 & J41 joists 6" typically for staggering joists in attached SK-05. Suggestion: Attachments: SK-05 Potential Cost Impact:
Unknown
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 007
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: We just moved J28 & J29 joists 6" typically for staggering joists in attached SK-06. Suggestion: Attachments: SK-06 Potential Cost Impact:
Unknown
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 008
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: Please advise which dimension we need to adjust to fix the dimension 3'-11 3/8" in attached SK-07. Suggestion: Attachments: SK-07 Potential Cost Impact:
Unknown
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 009
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: We already provided deck on the north & south part of the stair in attached SK-08. As per approval return comment it is not clear to us that the deck will be only within clouded part or it will be continuation of the same deck that we provided @ stair. Please advise. Suggestion: Attachments: SK-08 Potential Cost Impact:
Yes
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 010
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: We already provided deck on the north & south part of the stair in attached SK-09. As per approval return comment it is not clear to us that the deck will be only within clouded part or it will be continuation of the same deck that we provided @ stair. Please advise. Suggestion: Attachments: SK-09 Potential Cost Impact:
Yes
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 011
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: Please provide the clouded dimension in attached SK-12. Suggestion: Attachments: SK-12 Potential Cost Impact:
Yes
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 014
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Subject: EOD (End of Deck) Discipline: Secondary Structural Steel Drawing Reference and Drawing Date: Specification Reference:
Question/Description of Issue: Please confirm the clouded end of deck dimension in attached SK-13. Suggestion: Attachments: SK-13 Potential Cost Impact:
Unknown
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 015
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Subject: BOA (Back of Angle) Discipline: Secondary Structural Steel Drawing Reference and Drawing Date: Specification Reference:
Question/Description of Issue: Please confirm the clouded back of angle dimension in attached SK-14. Suggestion: Attachments: SK-14 Potential Cost Impact:
Unknown
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 016
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Subject: Building Code Discipline: Secondary Structural Steel Drawing Reference and Drawing Date: JE1.01 dated 07/19/16 Specification Reference:
Question/Description of Issue: Please provide building code for this project. Suggestion: Attachments: Potential Cost Impact:
Unknown
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 017
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: The clouded approval return comment in attached SK-15 raised some questions. This job was priced based on G60 for deck finish; but, it appears approvaer wants Galvanized w/std gray primer. Please clarify. Suggestion: Attachments: SK-15 Potential Cost Impact:
Yes
Potential Schedule Impact: Yes
Response:
By: Drawing Update Required?
Date: Yes
No
Attachments:
1
REQUEST FOR INFORMATION To: 4G Steel Fab. Attention: Charlie Fleck E-mail /Fax:
Project Name: IWCC Football Wrestling Building Author Name: Amir Khaleghi Author RFI #: 018
Cc: Attention: E-mail /Fax:
Author Job No.: S03884 Date Issued: 08/26/2016 Need Reply By: 8/30/2016
Question/Description of Issue: Please see attached SK-16. Since no fixed & lateral moments were shown on the structural drawings, please confirm that it will be regarded as insignificant to the joist design and Canam will proceed with no end moments considered unless magnitude & load type are provided to Canam. Suggestion: Attachments: SK-16 Potential Cost Impact: