RFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT Cincinnati Streetcar Project June 2015

O&M timeline March 2015 - O&M RFP proposals due April-May 2015 – Proposal evaluation and negotiations June 2015 – City Council selects preferred method

July 2015 - SORTA Board approves contract award July-August 2015 – O&M contractor mobilization Sept. - Dec. 2015 - vehicle delivery April 2016 - completion of civil construction September 2016 - start of passenger service

SORTA’s objectives • Competitively procure an Operations & Maintenance contractor for the streetcar using Federal procurement guidelines • Use the level of service established in the FTA grant applications and funding established by City

• Assure the best value for the City in terms of quality and price

Roles

• City selects the method of service delivery (turn-key or management contract) • SORTA conducts the procurement and awards the contract

The two methods All proposers were required to submit two methods: Turn-key contract – contractor provides all employees; fixedprice contract. Contractor assumes financial risks for operating based on contract scope. Management contract - contractor manages operations and maintains the system for a fixed price. At an additional cost, SORTA provides certain employees (streetcar operators, facility maintenance/janitorial). Total cost of operating the streetcar would change based on several factors including negotiations with new bargaining unit. Risk is shared.

Strict Federal procurement process • Not a simple Invitation for Bid process -- low price • Request for Proposal (RFP) -- best overall value • Same model SORTA uses for other O&M procurements, including Access paratransit operator • Evaluation committee: SORTA and City representatives • Multi-step rating process, interviews and negotiations

Timeline for procurement process • RFP issued in January; proposals received by end of March • Evaluation of proposals in April; all proposers interviewed • Best and final offers requested from all firms and negotiations with top firms in May • City Council selection of preferred method in June • SORTA contract award in July to keep project on schedule

Evaluation criteria RFP evaluation criteria, in order of importance: • Project approach: understanding of what is required; safety and customer service; maximizing resources, etc. • Qualifications: experience of the firm and staff assigned to Cincinnati Streetcar • Price: fixed price to operate and maintain • Specific plans: start-up preparations and testing; operations and maintenance of the vehicles and electrical system; operating facility maintenance, etc.

What is being shared today The best-value pricing for the Cincinnati Streetcar operations and maintenance, based on: • The selected proposal for the turn-key contract

• The selected proposal for the management contract – Tentative costs related to SORTA-provided employees for management contract approach only • Costs for City’s and SORTA’s respective responsibilities

What is being shared today For both turn-key and management contract methods: • Contractor cost (fixed price) • SORTA’s streetcar costs, reimbursed by the City: – Administration including support for Federal compliance, contract oversight, customer service, communications, etc.

– Direct costs including electricity to operate the streetcar, fare media, ticket vending machine maintenance, etc. • City’s costs

Additional SORTA-provided employee costs: management contract method only Estimated wages and benefits for streetcar operators and facility maintenance/janitorial employees provided by SORTA These tentative costs are based on: • June 2 preliminary agreement with ATU Local 627 • Comparable Metro wages and benefits • Comparable work rules for Metro represented employees, which would add additional positions NOTE: There are a number of cost factors that cannot be fully known until a collective bargaining agreement is negotiated

Turn-key contract method Based on service plan in FTA grant and O&M Agreement Contractor’s price proposal (fixed)

Startup

City’s additional SORTA costs paid costs for services/ by City (fixed) administration*

Electric and other direct costs

$1,100,000

Total projected cost

City funding

$1,100,000

$1,100,000

Year 1 Year 2 Year 3 Year 4 Year 5 Total, Year 1-5

$3,269,921 $3,308,166 $3,478,734 $3,616,542 $3,701,930 $17,375,293

$261,594 $264,653 $278,299 $289,323 $296,154 $1,390,023

$257,234 $248,386 $264,951 $253,168 $272,900 $258,053 $281,087 $263,043 $289,519 $268,143 $1,365,690 $1,290,792

$4,037,135 $4,090,938 $4,287,985 $4,449,996 $4,555,746 $21,421,800

$4,200,000 $4,284,000 $4,369,680 $4,457,074 $4,546,215 $21,856,969

Option Year 1 Option Year 2 Option Year 3 Option Year 4 Option Year 5 Total, OY 1-5

$3,736,259 $3,861,183 $3,972,753 $4,096,655 $4,191,127 $19,857,977

$298,901 $308,895 $317,820 $327,732 $335,290 $1,588,638

$298,205 $273,353 $307,151 $278,677 $316,365 $284,118 $325,856 $289,679 $335,632 $295,361 $1,583,209 $1,421,189

$4,606,718 $4,755,906 $4,891,057 $5,039,922 $5,157,410 $24,451,014

$4,637,139 $4,729,882 $4,824,480 $4,920,969 $5,019,389 $24,131,859

Grand Total

$38,333,271

$2,978,662

$2,948,900 $2,711,981

$46,972,813

$47,088,828

*Not yet finalized

Management contract method Based on service plan in FTA grant and O&M Agreement Contractor’s price proposal (fixed) Startup

SORTA-provided labor costs*

City’s additional SORTA costs paid costs for services/ by City administration**

$950,000

$323,216

Year 1

$2,531,750

$1,365,578

$311,786

$257,234

Year 2

$2,537,284

$1,404,922

$315,376

Year 3

$2,679,399

$1,446,731

Year 4

$2,800,774

Year 5 Total, Year 1-5

Electric and other direct costs

Total projected cost City funding $1,273,216

$1,100,000

$248,386

$4,714,734

$4,200,000

$264,951

$253,168

$4,775,701

$4,284,000

$330,090

$272,900

$258,053

$4,987,172

$4,369,680

$1,491,230

$343,360

$281,087

$263,043

$5,179,495

$4,457,074

$2,878,227 $13,427,434

$1,538,666 $7,247,127

$353,351 $1,653,965

$289,519 $1,365,690

$268,143 $1,290,792

$5,327,907 $24,985,008

$4,546,215 $21,856,969

Option Year 1

$2,893,299

$1,589,311

$358,609

$298,205

$273,353

$5,412,777

$4,637,139

Option Year 2

$2,973,407

$1,643,461

$369,350

$307,151

$278,677

$5,572,047

$4,729,882

Option Year 3

$3,043,532

$1,701,446

$379,598

$316,365

$284,118

$5,725,060

$4,824,480

Option Year 4

$3,124,554

$1,763,624

$391,054

$325,856

$289,679

$5,894,767

$4,920,969

Option Year 5

$3,205,990

$1,830,392

$402,911

$335,632

$295,361

$6,070,286

$5,019,389

Total, OY 1-5

$15,240,783

$8,528,234

$1,901,521

$1,583,209

$1,421,189

$28,674,936

$24,131,859

Grand Total

$29,618,217

$16,098,576

$3,555,486

$2,948,900

$2,711,981

$54,933,160

$47,088,828

*Will change based on negotiations with new bargaining unit, training costs, etc.

** Not yet finalized

Comparison of best value proposals Based on service plan in FTA grant and O&M Agreement Total Streetcar Pricing

City funding Startup

Management contract

Difference between contract methods

1,100,000

$ 1,100,000

$ 1,273,216

$

(173,216)

Year 1

4,200,000

$ 4,037,135

$ 4,714,734

$

(677,599)

Year 2

4,284,000

4,090,938

4,775,701

(684,763)

Year 3

4,369,680

4,287,985

4,987,172

(699,187)

Year 4

4,457,074

4,449,996

5,179,495

(729,499)

Year 5

4,546,215

4,555,746

5,327,907

(772,161)

21,856,969

$ 21,421,800

$ 24,985,008

$ (3,563,209)

Option Year 1

4,637,139

4,606,718

5,412,777

(806,059)

Option Year 2

4,729,882

4,755,906

5,572,047

(816,140)

Option Year 3

4,824,480

4,891,057

5,725,060

(834,003)

Option Year 4

4,920,969

5,039,922

5,894,767

(854,845)

Option Year 5

5,019,389

5,157,410

6,070,286

(912,876)

Total, OY 1-5

24,131,859

$ 24,451,014

$ 28,674,936

$ (4,223,922)

$ 46,972,813

$ 54,933,160

$ (7,960,347)

Total, Year 1-5

Grand Total

$

Turn-key

$

$

47,088,828

City Council policy guidance In response to City of Cincinnati motion #201401401: SORTA requests that City Council provide guidance regarding the preferred method by the end of June: - Turn-key contract - Management contract Contract must be awarded by SORTA in July 2015 to meet deadlines related to first vehicle delivery in September. Delays will add cost to the project.