Sault Ste. Marie MGP Sediment Remediation: A Public-Private ...

Report 6 Downloads 29 Views
MGP 2012

Sault Ste. Marie MGP Sediment Remediation: A Public-Private Partnership Under the Great Lakes Legacy Act Ed Sloan Marquette, Michigan

Former Sault Ste. Marie MGP - 1937 •  MGP Site •  Hickler Bros. Foundry and Marine •  Soo Warehouse

Page 2

MGP Gas Holder and Hickler Bros. - 1929

Page 3

Site Photo – Present Day

•  •  •  • 

MCM Marine Floating Dry Dock Soo Warehouse Hickler Brothers Foundry and Marine

Page 4

Page 5

Page 6

GLLA – St. Marys River Former MGP •  Approximately 35,000 cubic yards of contaminated sediment •  Primary contaminant of concern – Polycyclic Aromatic Hydrocarbons (PAHs) •  Non-federal sponsor – Consumers Energy Company •  Multiple potential sources of PAHs identified in AOC near the GLLA project site •  Initial contaminated sediment removal conducted solely by Consumers Energy in 2005 (7,300 cubic yards removed) •  Phase I GLLA removal completed in 2010 (7,800 cubic yards) •  Phase II GLLA removal completed for 2011 (20,000 cubic yards)

Page 7

Project Stakeholders •  Consumers Energy •  U.S. Environmental Protection Agency (USEPA) •  City of Sault Ste. Marie •  Michigan Department of Environmental Quality (MDEQ) •  Bi-National Public Advisory Council (BPAC) •  Sault Tribe of Chippewa Indians •  MCM Marine

Page 8

Sediment Investigation (2001 through 2009)

Barge Mounted Drill Rig Vibracore and Ponar

Page 9

On-Shore MGP Remediation Tar Tank Demo

Separator Tank Demo

Pier Demo, Re-Design, and Construction

Shoreline Restoration

Sediment Removal Design and Support Activities •  Geotechnical Evaluations •  Structural Stability Modeling and Monitoring •  Dredging effect on existing structures •  Temporary Shoring Design and Monitoring •  Conventional and Hydrographic Surveyors and Vessels •  Geographic Information System Specialists

Page 11

Phase I GLLA Sediment Removal (2010)

Page 12

Phase I GLLA Sediment Removal (2010) Modified Clamshell Bucket

Containment Pad

Page 13

Phase I GLLA Sediment Removal (2010)

Page 14

Phase I GLLA Sediment Removal (2010)

Turbidity Curtain and Oil Boom (Native Clay Layer)

Background Turbidity of St. Marys River 0 to 5 NTUs

Page 15

Phase I GLLA Sediment Removal (2010)

Water Treatment - Frac Tanks - Bag Filters - Organo-Clay - Tri-Carb - 2 Canister Carbon Polish - Discharge to Sanitary Sewer

Page 16

Clean-up Criteria Development •  Over 100 sediment sample locations (Surface and Cores) within the dredging footprint •  Began with evaluation of historical PAH (16) data [22.8 ppm Total PAHs – MacDonald 2000, Probable Effects Concentration (PEC)}. •  Gathered additional samples for analysis of PAH (16), PAH (34), and Pore Water (University of North Dakota Lab). •  Conducted a statistical analysis of data to derive clean-up criteria applicable to the site (115 ppm total PAH 16 – less than 1 toxic unit). •  Utilized multiple lines of evidence (visual contamination, thick soft sediment deposits, pore water PAH data, whole sediment PAH data) to propose the final dredging outline.

Page 17

Phase II Sediment Removal - Area Based on TU>1, PAHs >115 ppm, Visible, and Soft Sediment

Page 18

Phase II GLLA Sediment Removal (2011) •  •  •  • 

Federal Navigation Channel River Current and Level Changes Ship Traffic Working Dry Dock and Marine Contractor

Page 19

Phase II GLLA Sediment Removal (2011) Offloading to Containment Pad Hopper Barge

Page 20

Phase II GLLA Sediment Removal (2011)

•  12 CUYD Cable Arm •  Dredging to Hopper Barge

Truck Loading (Sediment Dried with Lime and Sawdust)

Page 21

Verification Sampling and Residual Cover

•  Over 50 verification samples were collected in the dredge footprint •  Samples verified that soft sediment was removed to the target native clay layer •  Areas with PAH levels above clean-up targets received residual sand cover

Page 22

Water Treatment

Thank You

Edward J. Sloan Senior Project Manager 906-226-4983 [email protected]