solar pv in the uk, the developers prospective - Regensw

Report 1 Downloads 74 Views
SOLAR PV IN THE UK, THE DEVELOPERS PROSPECTIVE

REGEN SW: PLANNING FOR SOLAR PV PARKS, OCT 2010 David Maguire, Director BNRG Renewables

The Developers Perspective • BNRG Intro • Commercial Background to PV – Solar PV in Europe – Solar PV in the UK • Current Market Perspective • Project Development, BNRG Experience, Best Practice • Wider Benefits, Hurdles

COMMERCIAL BACKGROUND  Solar energy relies upon good solar resource and the provision of State incentives (known as Feed-in tariffs or Green Certificates) to stimulate investment.  Feed in tariffs are typically:  Granted for a long period  Greece, Germany, Italy: 20 years  UK, Bulgaria, Spain: 25 years  Are at a substantial premium over other forms of electricity  Bulgaria €0.37 /kwh  Greece €0.40/kwh  Italy €0.35/kwh  UK €0.36/kwh

SOLAR RADIATION

PV MARKET IN EUROPE Country

2009

2010

2011

Duration

Cumulative PV

MAJOR

FIT (€ /MWh)

FIT (€ /MWh)

FIT (€ /MWh)

Years

(MWs – Dec 2010)

Germany

320

280

262

20

12,000

Spain

280

280

210

25

3,700

Italy

440

400

350

20

2,000

France

328

420

369

20

350

Czech Rep

492

467

327

20

1,000

Belgium

510

410

390

20

450

Greece

400

400

380

20

100

Bulgaria

371

371

354

25

10

0

366

366

25

60

EMERGING

UK

ASSESSING PV TERRITORIES In assessing countries that provide best and safest returns key factors include: – – – – – – – – – – –

Feed-in Tariff Solar Radiation Power purchase period Grid access Planning and permitting regime Forthcoming tariff degressions Land cost and availability Tax Availability and cost of credit Currency risk Political risk

PV MARKET IN EUROPE MAJOR ESTABLISHED MARKETS Germany • Over one third of the world’s installed capacity. • The investment market is mature and the process is well understood. • Poor solar resource (1100-1400 hrs/m2/year) and mediocre feed-in tariff • PV regarded as a trustworthy investment and has been embraced by the investing public. • Germany is the number 1 player in the market, but will not see any further dramatic growth.

Spain • Phenomenal growth during the period 2005-2008. • Excellent solar resource. Up to 2,000 hrs (even higher in Canary Islands) • New Programme Cap and now a much reduced tariff. • Spanish market is effectively closed off.

Italy • Italy is the fastest growing major market • Very good solar resource, good tariff • Municipalities causing delays in the south (bureaucracy, inefficiency) • The Italian market is tailing off with further tariff degressions.

PV MARKET IN EUROPE EMERGING MARKETS The following are regarded by most commentators as the major emerging markets: • FRANCE – Massive grid-connection delays mean the market did not take off as expected. • GREECE – Best combination of tariff and solar resource. Investment subsidies. Bureaucratic hold-ups are an issue. Economic difficulties make banking difficult. • CZECH REPUBLIC – Best tariffs. Bureaucratic. Difficult to get new projects going. Little further growth expected after 2011. • BELGIUM – Fast growth, renewables-friendly. Poor solar resource, degression now in place. Little growth expected after 2010. • BULGARIA – Good tariff and sun. Efficient and quick licencing. Banking is more expensive. The are grid access limitations. • UK – Latest entrant (2010). Secure territory. Expected to have efficient licensing. Banking should prove to be less expensive. Mediocre solar resource. Expensive land and grid connection.

COMPARATIVE PV INVESTMENTS 2010 Country

Greece

Italy

Czech Rp

Bulgaria

France Spain

Belgium

UK

Germany

Opportunities to invest

Index

FIT €/kwh

Good

680

Fair

Resource Hrs/m2/yr

City

€0.40

1,700

Naphlio

668

€0.40

1,670

Foggia

Now Difficult

564

€0.47

1,200

Brno

Good

562

€0.37

1,520

Bourgas

Fair

534

€0.32

1,670

Beziers

Now Difficult

496

€0.28

1,770

Valencia

Fair

463

€0.41

1,130

Bruges

Good

446

€0.36

1,240

Exeter

Fair

342

€0.28

1,220

Stuttgart

UK SOLAR PV POLICY DRIVERS • UK requires a 34% reduction in carbon emission by 2020. • 51% of this reduction is targeted to come from RES. • DECC projects 37% of electricity to come from RES. • DECC 2020 target for solar is 3% of the electricity mix or 3GW. • OFGEM project up to 60MW installed in 2010 and 250MW in 2011.

CURRENT MARKET PERSPECTIVE BNRGB’s market perspective as of October2010: PROS •Good market for completed PV projects from investment funds and pension funds. •A general enthusiasm for Solar PV at local and regional level. •Good regulatory framework. The current FIT model is working. •Good opportunity for employment and industry. CONS •Currency risk not experienced in other territories. •Relatively higher tax regime. •Land costs are amongst the highest in Europe. •Grid connection costs are amongst the highest in Europe. •Regulatory uncertainties: New government not giving clear signals. Institutional investors are nervous.

SOLAR PROJECT DEVELOPMENT Site identification

Site Negotiation

Planning

• Identification of • Determine • Screening suitable sites Maturity of • Pre-planning Licences - Size - Visual Impact • Negotiate - Inclination Stage - Env Issues (ideally flat) payments - FRA/LRA etc - Solar Radiation • Conduct Due Level - Design Diligence - Proximity to - Public consult Grid - Planning Application

Negotiate EPC Contract

Plant Construction

• Negotiation of EPC Contract, including :

• Civil Engineering activities

- Schedule of payments

• Fencing etc

- Timing of construction - Service Levels / Guarantees

• Installation of panels

Grid Connection

• Connection to Grid • Signing power purchase agreement (PPC) with Grid Operator

Plant Mgt. (O&M)

• O&M contract typically made with EPC contractor: - Ordinary maintenance (cleaning, scheduled maintenance, monitoring) - Spare parts replacement

- Grid Feasibility

- Mgt. of system failures

- Grid Application

- Security

RISK ASSESSMENT Risk

Planning Construction

Description

 Failure in planning  Construction failure or below expected quality

 Changes at tariff structure

Political Risk

Risk Likelihood

 Likely to occur in some cases

Potential Impact

Risk mitigation actions

 Medium: abortion of planning process

 Careful site selection and design

 Low

 Medium to High

 Strict assessment of EPC’s  Tight monitoring on construction through local presence

 Low – no precedent

 High only in dramatic scenario’s

 Lobbying?!?

Theft/damage

 Theft/Damage of (parts of) the installed equipment

 Likely to occur in some cases

 Limited (temporary breakdown, replacement of spare parts)

 Use adequate insurance, as well as security systems

System Efficiency

 Plant productivity is lower than expected  Radiation levels

 Possible, but unlikely to drop under guaranteed productivity

 Depending on productivity value

 Careful technical assessment during EPC negotiation  Fix a realistic productivity guarantee

 Default / Financial distress of EPC Partner  Interest Rate

 Low

 Medium: abortion of construction process

 Careful assessment of EPC’s  Structuring of EPC Contract  Hedging interest risk

Financial Risk

BNRG EXPERIENCE GREECE •Most attractive incentives in Europe and high solar resource. •Extremely long and uncertain permitting process. •Uncertain regulatory and economic conditions. BULGARIA •Good incentives and good solar resource. •Relatively low land costs. •Transparent and efficient permitting process. •Restricted grid capacity.

Greek sites

21/10/2010

Greek Sites

21/10/2010

Bulgarian Sites

21/10/2010

IMPLEMENTING BEST PRACTICE Key Planning/Environmental Issues • Materials and Construction • Visual Impact • Ecological Impact Mitigation • Careful site selection based on grid and planning issues. • Environmental Impact Mitigation – Suitable mounting systems (little or no concrete) – Suitable screening (selective planting) – Enhance biodiversity (margins, planting, grazing) – Suitable security fencing 21/10/2010

WIDER BENEFITS • • • • • • • •

Energy Security (1MW = energy for circa 250 homes) Reduction in Carbon Emissions Job creation and up-skilling workforce Community benefit Investment in grid infrastructure Tax revenue UK Pension Funds Enhanced biodiversity

21/10/2010

UK HURDLES • Regulatory Uncertainty • Narrow window of opportunity (31st March 2012 or 2013 Deadline) • Planning timelines • Grid connection timeline and costs 21/10/2010

BNRG Renewables Ltd., Dublin Exchange Building, IFSC, Mayor Street, Dublin 1, Ireland T: 0035317917882, F: 0035317917932