STATEMENT OF WORK PROJECT NO. 370582329
BATHROOM RENOVATION PROJECT SMITH RESIDENCE 1 EXAMPLE ST ANYTOWN, NSW 2999 AU 12 DEC 2017
Copyright © 2017 pricemy reno.com.au. All rights reserved.
Version 1.00, October 2017
www.pricemyreno.com.au
PREFACE This Statement of Works was created at pricemy reno.com.au, using the free bathroom renovation calculator that helps home owners plan their bathroom renovation projects before talking to a builder. Pricemyreno.com.au has one mission: to make planning renovation s easy. The calculator aims to help the home owner develop their scope of works and understand how much it is likely to cost before asking builders to invest their time preparing a quote. The output is a written statement of work that is itemised, quantified and broken into clear trade packages, making coordination of trades easier. The result is a win -win for everyone.
ACKNOWLEDGEMENTS This document is based on the Standard Bathroom Renovation Statement of Work developed as a collaborative, industry -wide project lead by the team at pricemyreno.com.au. Many thanks to all the individuals and organizations who reviewed and contributed to this work, and to the industry representatives and trade advisors who made this document possible.
DISCLAIMER This document is unc ontrolled upon generation . Home owners are advised to seek advice from a design professional prior to consulting a builder. Price myreno.com.au shall not be held liable for damage or devaluation of property as a result of works undertaken using this document.
COPYRIGHT Bathroom Renovation Statemen t of Work © 2017 by pricemyreno.com.au. No portions of this work may be reproduced or displayed without the express written permission of the copyright holders. All rights reserved.
FEEDBACK We'd love to hear from you. If you love using this document or you have suggestions for improvement, please provide feedback via the purpose-built feedback form at: https://pricemyreno.formstack.com/forms/bathroom_reno_sow_feedback
Copyright © 2017 pricemy reno.com.au. All rights reserved.
INSTRUCTIONS FOR USE FOR THE HOME OWNER / INTERIO R DESIGNER Replace text in [red] with your detailed preferences. When complete, either: a. email the document to your preferred builder for pricing , or b. email it to
[email protected] and we'll get you a quote from one of our recommended builders in your area. FOR THE BUILDER Read the Statement of Work carefully. Enter your pricing into the attached form and return to sender.
12 Dec 2017
STATEMENT OF WORK
1
CONTENTS Preface ..................................................................................................................................................................... 0 Acknowledgements .............................................................................................................................................. 0 Disclaimer ................................................................................................................................................................. 0 Copyright ................................................................................................................................................................. 0 Feedback ................................................................................................................................................................ 0 Instructions for Use .............................................................................................................................................. 1 Introduction ............................................................................................................................................................ 3 Demolition Specification .................................................................................................................................. 3 Structural Specification ..................................................................... Error! Bookmark not defined. Plumbing Specification ...................................................................... Error! Bookmark not defined. Electrical Specification ..................................................................... Error! Bookmark not defined. Tile Refresh Specification ................................................................................................................................ 4 Tiling Specification .............................................................................. Error! Bookmark not defined. Joinery Specification .......................................................................................................................................... 4 Glazing Specification ........................................................................................................................................ 4 Painter Specification ......................................................................................................................................... 4 Window Furniture Specification .................................................................................................................... 5 Final Fix ..................................................................................................................................................................... 5 Builder's Works ....................................................................................................................................................... 5 Annexes ..................................................................................................................................................................... 7
12 Dec 2017
STATEMENT OF WORK
2
INTRODUCTION The purpose of this document is to desc ribe the scope of works for the bathroom renovation project at 1 Example St Anytown, NSW 2999 AU. This document shall be the primary reference document for the builder and/or tradesperson to develop their quotation. Upon acceptance of the quotation, the Statement of Work shall form part of the contract. OBJECTIVE OF THE PROJECT This is a Simple Facelift of an existing bathroom . DESCRIPTION OF THE S ITE The site is a Stand-alone home. The bathroom is on the ground floor. The dimensions are 2.0 m x 3.0m. SITE ACCESS Parking is available off the street. Access to the site is considered easy. Working days will be [Monday] to [Saturday]. The site will be accessible from [6am] each working day. Work must cease by [5pm] each working day. PROJECT TIMEFRAME The earliest start date for the project is [Start date]. The project must be completed by [Finish date].
DEMOLITION SPECIFICATION Photos of the current room have been provided in the appendices. The following existing items require removal :
Towel Rail Mirror Cabinetry
12 Dec 2017
STATEMENT OF WORK
3
One door is to be removed.
All waste material is to be removed from site and disposed of at the expense of the demolition contractor. The Contractor is responsible for protecti ng all surfaces to be retaine d. The Contractor is to leave the site in a clean and tidy state in preparation for installation works.
TILE REFRESH SPECIFICATION The following tiles require refreshing:
Shower floor tiles Shower floor tiles
The tiles require a Resurface and regrout. Shower wall tiles to 3/4 height . Other wall tiles to Skirting only .
JOINERY SPECIFICATION The following joinery is required: New vanity unit New wall-mounted storage A vanity unit is required with the following dimensions (in mm): 900(W) x 450(D). It is to be Free-standing. The joinery is to be of a basic level of quality, with a Timber Laminate bench top. The bench top is to be at a finished height of 900mm. It is to accommodate a basin. The configuration is to be Cupboard. A high level cabinet is require d with the following dimensions in mm: 600(W) x 150(D) x 300(H). The joinery is to be of a basic level of quality. Configuration is to be Open shelves.
GLAZING SPECIFICATION A Basic quality Framed mirror is to be installed measuring 700mm in height x 700 mm in width.
PAINTER SPECIFICATION The area of wall to be painted is 18 SQM. The area of ceiling to be painted is 6 SQM. 12 Dec 2017
STATEMENT OF WORK
4
One door and door frame requires painting. The length of window architrave to be painted is 4.2 LIN M. A Minor level of surface prepara tion is required.
WINDOW FURNITURE SPECIFICATION The following window furniture is required: Curtains. The quantity required is 1. Window furniture is to be of a Basic Quality. The size is approximately 1200 (H) x 1200 (W). For details of range and fabric, refer to the FF&E Schedule at Annex A. Window furniture is to be custom fitted to the window(s). The installer is to arrange with the builder to attend site to take measurements.
FINAL FIX A Basic quality Normal Towel Rail is to be supplied and securely in stalled to the wall.
BUILDER'S WORKS The builder is to obtain all necessary permits as required by local regulations prior to commencement of works. The Builder is to obtain appropriate insurances as required by local regulations. The Builder is to allow for transport of all materials to the site, as well as movement and handling of materials at the site. The Builder is to provide a portable toilet for use by contractors at the site for the duration of the works . The Builder is responsible for the security of all materials and tools brought to the site for the project. The Builder is responsible for protection of all surfaces at the site. The Builder must complete a dilapidation inspection in the presence of the client prior to commencement of any works. Re pair of any damage at the site as a result of the works is the responsibility of the Builder.
12 Dec 2017
STATEMENT OF WORK
5
The contract to be used is the Bathroom, Laundry and Kitchen Supply and Install Contract as published by the Housing Industry of Australia (HIA) in your state . The costs of using this contract are to be allowed for by the Builder. All gaps are to be sealed using professional quality silicon. Builder's clean is to be carried out to a professional standard. All marks and fingerprints are to be completely removed from all surfaces.
12 Dec 2017
STATEMENT OF WORK
6
ANNEXES A. Finishes, Fixtures & Equipment Schedule B. Reference Image C. Photo of Existing Bathroom
12 Dec 2017
STATEMENT OF WORK
7
ANNEX A. FINISHES, FIXTURES & EQUIPMENT SCHEDULE Item
Selection
Image
Pow er O utl et s , q u a lit y
M ak e: M o de l:
[Ins e rt Im ag e H e re]
Col ou r:
[Ins e rt Im ag e H e re]
Col ou r:
[Ins e rt Im ag e H e re]
M ak e: [ M ak e] M o de l: [ M o d el] Fr am e c ol ou r: [Col ou r]
[Ins e rt Im ag e H e re]
Ran g e: [R an ge] Col ou r: [C o lou r] Sh ee n: S em i gl os s Ran g e: [R an ge] Col ou r: [C o lou r] Sh ee n: M at t e
[Ins e rt Im ag e H e re]
Ran g e: [ M ak e] Fa br ic: [ M o d el]
[Ins e rt Im ag e H e re]
M ak e: [ M ak e] M o de l: [ M o d el]
[Ins e rt Im ag e H e re]
Joinery Van ity Un it 90 0( W) x 4 5 0(D) , Timb er La min at e B e nc ht op , b a s ic Qua lit y Join er y - Hig h Le v e l 6 00 (W ) x 1 50 (D) x 3 00( H ), Fi ni sh , b a sic Qua lit y
Glazing Mirr or , Ba s ic q u ali t y Fr a me d, 70 0( H) x 70 0( W )
Painting W al l s
C eil ing
[Ins e rt Im ag e H e re]
Window Furniture C urt ain s, B a sic q ua lit y
Final Fix Items Towe l Ra il , B a s ic q u ali t y
12 Dec 2017
STATEMENT OF WORK
8
ANNEX B. REFERENCE I MAGE