Status March Construction Report

Report 1 Downloads 224 Views
Bossier  Casino  Venture,  Inc.   dba   Margaritaville  Resort  Casino   P  .O.  Box  92610         Lafayette,  Louisiana  70509-­2610     (337)  266-­2166          

     

       

     

  600  Jefferson  Street        Lafayette,  Louisiana  70501     Fax  (337)  266-­2229  

    March  30,  2012       Dear  Investors  and  Lenders:   Following  is  my  first  status  report  with  respect  to  our  Margaritaville  Bossier  City   project.    Such  report  includes,  as  attachments,  a  detailed  Construction  Progress   Report  and  current  photos  of  the  site.    You  will  be  receiving  this  week,  directly  from   the  Agent  (Cortland  Capital  Market  Services)  our  first  Disbursement  Advance   Request,  together  with  supporting  documentation,  and  the  Construction  Consultants   Report,  reconciling  such  Disbursement  Request  to  the  Budget.    These  reports  will   demonstrate  that  we  have  made  significant  progress  since  funding  last  month  and   that  we  are  currently  on  schedule  and  on  budget.   The  official  ground  breaking  ceremony  was  a  major  press  event  and  success  as   Jimmy  Buffett  attended  and  we  thus  garnered  front  page  newspaper  coverage  in   Shreveport  and  related  stories  in  dozens  of  television  and  radio  news  broadcasts,  as   well  as  print  articles,  throughout  the  entire  region.   We  have  been  engaged  in  numerous  additional  activities,  besides  construction,  in   furthering  the  project.    We  have  had  numerous  discussions  with  banks,  equipment   providers  and  other  senior  lenders  with  respect  to  securing  the  additional  $25   million  of  super-­‐senior  secured  financing  necessary  to  complete  the  project.    We   expect  proposals  in  the  near  future  from  one  or  more  of  the  entities  with  whom  we   are  dealing.   We  are  completing  interior  design  selections  for  guest  rooms,  restaurants,  the   casino  and  other  public  areas  over  the  next  thirty  to  forty-­‐five  days  and  will  shortly   commence  construction  of  a  model  guest  room  and  suite.   We  have  interviewed  and  reached  an  agreement  in  principle  with  a  candidate  for   the  position  of  controller,  and  as  soon  as  such  agreement  is  complete,  we  will   provide  you  with  background  information  on  this  outstanding  candidate.    This   person  will  immediately  be  given  responsibility  for  preparing  future  draw  requests   and  loan  covenant  compliance.    He  will  also  prepare  our  internal  controls  and   procedures,  and  assist  in  the  design  and  designation  of  equipment  placement  for  the    

March  30,  2012   Status  Report   Page  Two     cage,  count  rooms,  players  club  and  other  similar  areas.    We  have  also  had  extensive   discussions,  and  believe  that  we  will  come  to  an  agreement  shortly,  with  our   number  one  candidate  for  General  Manager.    In  addition,  I  have  had  discussions   with  prime  candidates  for  the  Director  of  Slots,  Director  of  Table  Games  and   Director  of  Security  positions.    All  are  seasoned  executives  who  have  significant   experience  in  the  Shreveport-­‐Bossier  City  gaming  market.   We  will  have  our  website  operational  next  week  and  a  webcam  to  view  construction   on  a  real  time  basis  within  two  weeks.    Through  a  password  controlled  section  of   the  website,  my  future  status  reports,  as  well  as  updated  construction  schedules,   budgets  and  other  similar  information  will  be  available  to  lenders  and  investors.   We  have  made  excellent  initial  progress  and  I  am  extremely  pleased  with  our   accomplishments  during  these  first  seven  weeks  since  funding.    Most  importantly,  I   have  confirmed  that  the  first  interest  payment  has  been  made  today.   Any  questions,  please  feel  free  to  call  me  at  any  time.   Paul  Alanis     Chief  Executive  Officer   Bossier  Casino  Venture,  LLC     626.356.1188  

     

Margaritaville  Resort  Hotel  and  Casino   Bossier  City,  Louisiana  

Construction  Update     Week  7  -­‐  March  30,  2012       Executive  Summary     General  Project    Milestones     • Project  funding  occurred  on  February  9th  2012.   • The  Notice  to  Proceed  to  the  general  contractor,  Roy  Anderson  Construction,  was  given  on   February  13,  2012  and  mobilization  began  without  delay.       • Administrative  personnel  of  the  project  team  which  consist  of  the  owner,  the  architect,  the   contractor,  the  construction  consultant  and  the  owner’s  construction  representative,  met  to   review  all  disbursement  documentation  and  established  responsibilities,  time  lines  and   procedures  for  invoicing,  processing,  executing  and  submittals  as  they  relate  to  the  mechanics   and  requirements  of  the  disbursement  agreement.  The  disbursement  agent  was  furnished  with   the  anticipated  recurring  monthly  schedule  as  it  relates  to  the  advance  request.     • The  policies  and  procedures  for  the  design/construction  team  have  been  established.  They   address  processes  for  submittals,  requests  for  information  (RFI),  scheduling,  quality  control,   testing,  reporting  and  timelines.   • The  design  team  has  released  the  construction  documents  for  the  site  work  civil,  foundations,   structure,  and  the  building  envelope  or  exterior.   • The  general  contractor  has  let  and  awarded  the  site  work,  foundations,  structural  steel,   electrical,  mechanical,  plumbing  and  procurement  of  concrete  subcontractors,  consistent  with   the  Budget.  The  award  of  post  tension  concrete  and  the  structural  concrete  is  pending.  Bid   packages  for  the  building  exterior,  roofing,  glass  and  glazing,  doors  and  hardware,  drywall,   masonry  and  EFIS,  have  been  assembled  to  let  next  week.   • Parties  on  site  include  the  owner’s  representative,  general  contractor,  site  work  subcontractor,   piling  subcontractor,  electrical  subcontractor,  and  mechanical  contractor.  Coordination   meetings  have  been  conducted  weekly  with  agenda  and  minutes  distributed  by  the  host,  the   general  contractor.     • The  project  is  currently  in  budget  and  on  schedule.     Construction  Milestones     For  future  on-­‐  going  reporting,  it  is  important  to  understand  that  the  project  is  sequenced  into  four  (4)   primary  areas  which  are  the  hotel  high  rise,  the  casino  barge  and  basin,  the  lowrise  area  consisting  of   restaurants,  retail  and  back  of  house,  and  the  event  center.       • Contemporaneous  with  the  notice  to  proceed,  the  contractor  pulled  the  appropriate   construction  permits  for  foundations  and  subcontracted  the  mass  excavation  site  work  for  the   footprint  of  all  four  areas.  The  general  contractor  installed  a  temporary  8’  chain  link   construction  fence  around  the  entire  site.    There  was  minimal  activity  on  site  during  the  first   week  of  construction.  













In  week  2,  the  subcontractor  established  all  required  erosion  control,  sampled  the  soils  from   three  local  dirt  sources,  mobilized  all  required  heavy  equipment,  stockpiled  the  topsoil  from   the  site  and  began  the  excavation.  Once  excavated  to  the  plan  depth,  each  area  was  proof   rolled  to  detect  any  potential  soft  spots.  The  results  were  minimal  and  only  three  small   locations  required  an  18”  undercut  where  the  soils  were  replace  with  dry  suitable  materials   from  the  site.     During  week  3,  after  selecting  the  fill  material  for  the  project  and  having  enough  excavation   completed,  the  contractor  began  hauling  in  select  fill,  which  was  installed  and  compacted  in   shallow  lifts.  Each  lift,  which  is  to  be  installed  within  2%  of  optimum  moisture  and  requiring  a   final  compaction  density  of  95%,  was  test  using  a  nuclear  density  device.  Although  the   moisture  was  running  high  in  the  imported  material  it  required  minimal  processing  to  achieve   the  moisture  and  density  requirements.  In  week  3,  the  contractor  also  awarded  the  auger  cast   pile  contract  and  the  subcontractor  began  mobilizing  its  equipment.  Concrete  mix  designs   were  submitted  at  this  time  along  with  the  proposed  locations  and  testing  methods  for  test   piles.   Beginning  week  4,  the  site  work  contractor  had  80%  of  the  fill  material  for  all  areas  receiving   deep  foundations  in  place  up  to  the  critical  elevation  at  the  top  of  proposed  piles  and  below   the  pile  caps  (+  or-­‐  12”).  By  the  end  of  the  week  the  pile  contractor  had  their  crane  set  up  and   they  were  able  to  begin  installation  for  two  test  piles  along  with  the  six  reaction  piles  at  each   location.  These  piles  were  not  completed  in  week  5,  and  we  are  required  to  be  in  place  for  a   minimum  of  7  days  prior  to  testing.   Week  5  brought  the  completion  of  the  test  pile  installation  while  the  site  work  contractor   completing  all  mass  excavation  continued  to  install  selected  material  in  the  low  rise  area.  The   clearing  operation  along  the  river,  west  of  the  proposed  parking  area,  began  and  was   completed  in  3  days.  With  reinforcing  steel  for  the  deep  foundations  arriving  on  site  the   contractor  began  sorting  and  staging  the  re-­‐bar  as  they  prepared  to  tie  the  steel  for  the  auger   cast  production  piles.   During  week  6,  although  a  short  week  due  to  2  days  of  heavy  rain,  the  test  piles  were  tested   and  these  test  results  were  processed  and  circulated  to  the  design  and  construction  team.   During  the  first  2  days  of  week  6  the  site  work  subcontractor  continued  to  import  fill  at  the  low   rise  and  outside  the  perimeter  of  the  building  footprint.  It  then  graded  the  site  for  positive   draining  in  anticipation  of  the  forecasted  heavy  rains.   Week  7,  after  the  review  of  the  test  pile  results,  the  contractor  proposed  and  the  design  team   approved,  the  final  geometry  and  the  grout  mix  design  for  the  production  piles.  During  these   discussions  everyone  agreed  that  we  would  install  2  test  piles  using  the  final  geometric  design   which  is  18”  in  diameter  in  lieu  of  16”  and  all  proposed  piles  will  be  a  uniform  55’  in  depth  in   lieu  of  varying  lengths.  Once  installed  the  contractor  began  production  piling  at  noon  on  March   29,  2012.    The  first  piles  installed  were  at  the  south  end  of  the  hotel  tower  footprint.   The  piles  will  be  installed  from  south  to  north  along  the  footprint  of  the  hotel  tower,  then  west   to  east  at  the  casino  basin  and  barge.  The  site  work  subcontractor  is  continuing  the  fill   operation  in  the  lowrise  and  areas  adjacent  to  the  building.  To  date  approximately  62,000   cubic  yards  of  imported  select  fill  has  been  installed.  

  The  Owner’s  website  is  scheduled  to  be  operative  on  Friday  April  6th  and  fully  functional  with  the   installation  and  activation  of  the  webcam  shortly  thereafter,  where  lenders  and  investors  will  be  able  to   view  construction  progress  on  a  real  time  basis.