Study Corridor Engineering & Recommendations

Report 4 Downloads 89 Views
Study  Corridor  Engineering  &  Recommendations   The  major  outcome  of  this  technical  report  will  be  the  development  of  pedestrian  and  bicycle  improvement  recommendations  along  the  targeted  study  corridor  and  other  specifically  identified  areas  of  interest.    These  targeted  sites  are  based  on  the  original  grant  application,  input  from  the  various  stakeholders,  deficiencies  noted  through  field  visits,  and  public  input  gathered  from  presentation  meetings  and  various  survey  techniques  utilized.  The main focus of the recommendations, and first  priority  of  the  recommended  improvements,  is  providing  a  connection  between  the  eastern  and  western  portions  of  Voorhees  Township’s  Bicycle  Network.    Recommendations  for  this  corridor  include  enhancing  crossing  locations  and  problem  intersections,  expanding  the  existing  sidewalk  network,  introducing  conceptual  road‐diet  striping  configurations,  and  alternative  routes.    Additional  recommendations  focus  on  traffic  calming  techniques  and  potential  solutions  for  identified  problem  areas  for  motorists  and  pedestrians,  streetscaping  concepts  for  Centennial  Boulevard  to  complement  the  proposed  Environmental  Park  with  a  pedestrian‐safe,  aesthetically  pleasing  roadway  design  incorporating  transportation  and  pedestrian  needs.    Improvement  concepts  are  intended  to  be easily implementable, and will emphasize realistic, cost‐  and reality‐driven options to help the Township structure its  capital funding and grant applications.  The  following  sections  are  ordered  according  to  their  priority  and  the  different  areas  impacted.    Specific  improvements are identified, and concepts and information  to  drive  future  improvements  beyond  the  scope  of  this  report  are  provided.    Each  section  shows  graphical  improvements of the depicted improvements, along with an  accompanying  narrative.    Cost  estimates  are  summarized  and  ordered  in  terms  of  magnitude  and  short‐,  mid‐,  and  long‐term  goals  of  the  study.    Options  considered  both  realistic and beneficial are given priority in discussion.  The  

        cost  estimates  are  based  on  standard  unit  prices  based  on  historical  bid  data  for  similar  projects  received  by  CME  Associates, and includes labor, materials, and contingency.                                            

22   

 

Sidewalk Network Improvements 

 

Through  an  investigation  of  the  existing  conditions  of  the  study  corridor,  engineering  judgment,  and  discussion  with  the  various  stakeholders,  including  the  Township,  it  has  been determined that the completion and expansion of the  sidewalk network along Laurel Oak Road and Echelon Road  is an integral facility for pedestrians traversing east‐west on  the  Township’s  Bicycle  Network.    Despite  the  intermittent  presence  of  sidewalk  on  both  sides  of  the  roadways,  the  existing  conditions  analysis  has  identified  numerous  gaps  and  missing  portions  that  divide  a  smooth  continuous  bicycling/pedestrian  surface.    In  some  locations,  adding  sidewalk  will  require  modification  or  reconfiguration  of  existing commercial driveways to accommodate curb ramps  and  pedestrian  traffic.    New  sidewalk  construction  should  provide a minimum width of 5 feet – optimally 8‐12 feet –  to  provide  a  minimum  width  that  allow  for  side‐by‐side  traffic  and  ease  in  passing.    It  should  be  noted  that  riding  bicycles  on  a  sidewalk  is  not  supported  by  various  regulatory  and  municipal  agencies;    separate  facilities  are  preferred.    A  4‐foot  sidewalk  width  will  be  considered  acceptable  in  areas  restricted  by  limited  right‐of‐way  or  physical  impediments.    The  main  limiting  factor  when  considering  new  sidewalk  construction  is  cost;    the  report  contains  recommendations  that  prioritize  specific  connections along the roadway, and provides suggestions to  secure  the  funding,  through  grant  applications  and  modifications  to  the  Township’s  land  development  ordinances.  Using this comprehensive, phased approach, a  two‐way  sidewalk  network  along  Laurel  Oak/Echelon  road  can  be  provided  in  order  to  allow  proper  pedestrian  conveyance  along  the  study  corridor.    Figure  10  shows  the  missing gaps in the sidewalk network along the corridor.       

23   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FIGURE | STUDY CORRIDOR SIDEWALK NETWORK                     

 

 

 

 

 

 

 

 

 

  VOORHEES TOWNSHIP  

 

 

 

Existing Sidewalk   

Missing Sidewalk 

 

Sidewalk/Pathway Improvements 

 

Along the approximately 11,000 linear feet of Echelon Road  and  Laurel  Oak  Road  between  Somerdale  Road  and  Haddonfield Berlin Road, per the attached Figure 10, there  are  gaps  in  the  system  (along  either  side  of  the  road)  of  roughly  5,350  linear  feet.    While  at  least  one  side  of  the  roadway  generally  has  sidewalk  (i.e.  there  are  no  spots  where sidewalk gaps exist on both sides of the street), these  conditions  are  generally  unsafe  for  pedestrians,  as  they’re  forced to travel on non‐paved surfaces, a roadway with no  shoulder, or have to cross at an unsignalized location to  

avoid  the  gaps  in  the  system.    These  problems  would  be  alleviated  by  completing  the  sidewalk  network  along  the  study path.  The  figure  on  this  page  shows  the  gaps  in  the  sidewalk  network  along  the  studied  corridor,  and  assigns  each  section  a  priority  for  installation  based  on  utility  and  necessity for completing the sidewalk network.     

     

24   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FIGURE | SIDEWALK CONTINUITY NEAR STUDY CORRIDOR             

 

 

 

 

 

 

 

 

 

VOORHEES TOWNSHIP 

 

 

Existing Sidewalk   

Missing Sidewalk 

 

Sidewalk  Continuity  Near  Existing  Study  Corridor    As  mentioned  in  the  existing  conditions  analysis,  the  sidewalk  network  in  Voorhees  Township  is  far  from  complete.  The numerous gaps result from the inconsistent  development (in timing) of portions of the Township, and a  lack  of  a  consistent  requirement  for  the  installation  of  pedestrian  facilities  along  the  frontage  of  new  development.  Improving the sidewalk network throughout  the  Township  should  be  a  long‐term  goal  of  Voorhees,  to  improve complete facilities for all modes of users. 

25   

The  figure  above  shows  the  presence  of  sidewalk  along  all  roadways  connecting  with  the  study  corridor  (Laurel  Oak  Road  to  Echelon  Road),  along  a  quarter  mile  of  their  intersection with the studied corridor.  This map is intended  to give future planners an idea of existing connections, both  missing  and  there,  from  local  neighborhoods  and  developments to the study corridor.  The map can be used  to  drive  decisions  behind  future  capital  improvements  and  decisions.