The Development of Long Bay

Report 7 Downloads 30 Views
3/17/2015

The Development of Long Bay

Background

 Council Plan Change 2004‐ Council Plan vs Landco, 

hearing Nov 2005.  Council decision May 2006.‐ note earthworks  imbalance, geotechnical instability  Revised Council Plan March 2007‐earthworks balance  but steep slopes & compromised outcomes.  Environment Court Hearing 2007‐  Landco – 5 million cubic metres over 180ha.  NSCC – 2 million cubic metres

1

3/17/2015

 Interim decision July 2008 followed by extensive 

consultation between appealing parties as to form of  development based on Courts direction.  Matters addressed such as stream protection,  management areas; location of town centre; ridgeline  protection; density grading;   Draft Structure Plan Nov 2008, Final March 2009  Further consultation required – lodge final plans and  text September 2009  Final Decision 2009

 Long Bay Structure Plan –land use strategy

2

3/17/2015

 Long Bay Structure Plan –additional controls

Physical Development

 First construction 

contract let Nov 2009  Work commenced Jan  2010.  Adjacent to Awaruku  Stream, pre‐load for  bridge approaches,  creation of on‐line  wetland.

3

3/17/2015

 Beach Rd – looking west Jan 2010

 Beach Rd – looking west May 2012

4

3/17/2015

 Earthworks:  Earthworks 1‐ Awaruku

wetland and Geotech remediation  Jan 2010 – May 2010 and  Sep 2010 – May 2011.  280,000 cubic metres  $4.9million  Involved wick drainage and  sand blanket for pre‐load  areas for Bridge  approaches and abutments  Shear key construction in  gulley fills 

5

3/17/2015

 Earthworks 2‐

Awaruku Ridge and  College gulley  Sep 2011‐May 2012 and  Sep 2012 – May 2013  750,000 cubic metres  $10.5 million  Max fill depth 20m  Max cut depth 11m  Shear keys, college  retaining wall.

Long  Bay college retaining wall‐ constructed Jan 2013, suffered slip July 2013 finally completed Jan 2015.

6

3/17/2015

 Earthworks 3 – Eastern 

extents of South  Vaughans, Stream 1b  realignment   Sep 2012 – May 2013  370,000 cubic metres  $9.7 million  18ha  Max fill depth 9m  Max cut depth 10m

7

3/17/2015

Stream 1B Realignment

 Stream 1B works 

confined to 31 dec to 31  march to avoid inga spawning season.

Earthworks 3

8

3/17/2015

 Earthworks 4 – Western 

extents of South  Vaughans, filling on  north Vaughans  Sep 2013‐May 2014 and  Sep 2014‐ May 2015.  680,000 cubic metres  $15.1 million  25ha

Earthworks 4

9

3/17/2015



Erosion and Sediment  Control



Focus on effect of  earthworks through  Environment Court.



All ponds chemically  treated



Limit on open areas



Working in close  proximity to existing  watercourses

Turning this

Into this

By This

10

3/17/2015

Civil Construction 

Stages 1 & 2.



Stage 1 – 50 lots



$3.4 million 



Built 2011 ‐2012



Stage 2 – 45 lots



$1.8 million



Built 2012 ‐2013



Stages 4 ( 35 lots) & 7  (54 lots)



$6.3 million 



Built 2013‐2014

11

3/17/2015

Earthworks 1 & 2 complete, Earthworks 3& 4 underway. Stages 1 & 2 complete, building underway, Construction on Stages 4 & 7 underway.

 Stage 8a    35 lots  $2.5 million  Built 2012‐

2013

12

3/17/2015

 Stages 9 & 10  97 lots  $8.4 million  Built 2013‐

2014

Stages 9 & 10 post bulk  earthworks

Stages 9 & 10 post civil  construction

13

3/17/2015

Civil Infrastructure  Long Bay Pump 

Station

 Long Bay 

Wastewater Tunnel  $6.0 million  872m of 1980mm  244m of 1050mm  June 2011 – Nov 2013  Awaruku Bridge  $1.8 million

 Awaruku Bridge  $1.8 million  March 2012 – October 

2012

14

3/17/2015

Concluding Remarks

 The development of Long Bay has been in the making 

for over 10 years  The developer has spent over $85 million in the past 5  years on construction   Approximately 2 million cubic metres of earthworks  This has realised in the order of 300 the odd lots in the  past five years  Two earthworks seasons left – complete May 2017  Dependent on the economic cycle there are 4‐5 years of  civil construction left