Update on BSEACD Activities Outline

Report 1 Downloads 102 Views
10/12/2017

Update on BSEACD  Activities  Presentation to the Buda City Council October 17, 2017 

Outline

The BSEACD ‐ Overview BSEACD Activities of Interest  Aquifer Science Projects

1

10/12/2017

The Barton Springs/ Edwards Aquifer  Conservation District

Groundwater  Conservation  Districts (GCDs)

Barton Springs and the  Edwards Aquifer

2

10/12/2017

Established:  1987 Funding:  Fee Based Area: 417 m2 (170 annexed) Board of Directors:  5 elected Directors Aquifers:  Fresh Edwards   Saline Edwards   Upper Trinity   Middle Trinity    Lower Trinity  Other Aquifers  Applied Aquifer Science Science‐based Policies Education and Outreach

3

10/12/2017

Outline

The BSEACD ‐ Overview BSEACD Activities of Interest  Aquifer Science Projects

HB 3405 annexation  (2015)  Expanded territory  over Trinity Aquifer  Transitional permit  process  Capped fee in  shared territory

Electro Purification Needmore Water LLC

 Ongoing activity:    

Pending applications Expand monitoring Inventory all wells Education and outreach

4

10/12/2017

Habitat Conservation  Plan Need:  ↑Pumping =↓Springflow  =Take Covered Species:  1. Austin Blind Salamander 2. Barton Springs Salamander

Covered Activity: Permitted Pumping

Measures:  Drought Management (DFC)  Research   Mitigation

Management Plan Update   Updated every 5 years  Current MP expires Jan. 

2018

 Revision Guidelines  Adopt TWDB Goal  Structure  HCP as baseline  Streamline  Comprehensive  Expand Scope  Adopted:              

September 28, 2017

www.bseacd.org

5

10/12/2017

Rulemaking Drivers  2015 ‐ 84th Legislation 

Session (ASR authority)  2017 85th Legislation 

Session (Texas Water Code)  Other minor changes

Activity to Date – ASR Rules 84th Legislative Session 2015 HB 655  o Enabled TCEQ with exclusive authority to regulate ASR injection. o Exception for certain Districts with ASR authority (BSEACD exempt).  o Established a comprehensive framework for ASR permitting o Eliminated requirement for pilot project (however pilot projects are still key) HB 3405  o Enabled BSEACD with authority to permit ASR recovery wells.

Working Meetings with TCEQ o Met with TCEQ staff (application process, interpretation of rules) o Met with TCEQ Management Team (legal positions, statute interpretations)

BSEACD Board activity o Staff presentation of rule concepts (August 17) o Rules committee meeting (September 17)

6

10/12/2017

Concepts for Rules

Topic Areas for ASR Rules  Definition of terms  Authorization for feasibility testing  Well drilling requirements/construction standards  Permitting (process, application requirements, fees, etc.)  Site location, extent of storage area, resource ownership  Permissible sources for injection  Recoverability volumes and relating permitting requirements  Accounting of source production, injection, and recovery volumes  Monitoring

Rulemaking Process Steps 1. Board Discussion on ASR Rulemaking Process (Oct 12th) 2. Technical Advisory Committee  3. Board Rules Committee  4. Board approval to propose rules 5. Public comment period 6. Public hearing 7. Board approval Target Completion Date:  Summer 2018

7

10/12/2017

Outline

The BSEACD ‐ Overview BSEACD Activities of Interest  Aquifer Science Projects

Alternative Water Supplies: ASR and Desal*

* Aquifer Storage and Recovery and Desalination

8

10/12/2017

Aquifer Storage and Recovery (ASR) “…the storage of water in a suitable aquifer… during times when water is available, and recovery of that water … during times when it is needed.” David G. Pyne, P.E

ASR Testing Near Buda

9

10/12/2017

Questions?

10