Vista del Sol

Report 1 Downloads 224 Views
Vista Del Sol Drive Improvements

Official Letting Results 2/23/17

Contractor

Base Bid

Total Bid

% Difference

Difference

1

Bain Construction

$

4,582,190.00

$

4,582,190.00

-

-

2

CMD Endeavors, Inc.

$

5,039,375.00

$

5,039,375.00

457,185.00

9.98

3

Jordan Foster Construction

$

5,297,214.60

$

5,297,214.60

715,024.60

15.60

4

Dan Williams Company

$

6,636,078.90

$

6,636,078.90

2,053,888.90

44.82

Lesna Contruction Inc.- Non-Responsive- Addendum # 1 Revised Bid Tabs not included in bid Allied Paving Company - Non-Responsive - Proposal not signed