Demo Asphalt Paving for New Field House New Field House Bldg Pad looking NW & Ext. Building Demo New Field House Bldg Pad looking North Grading Baseball Field looking North Backfill & Compaction for Multi‐use Field Grading and Backfill for Netting Poles Bases Grading and Backfill for Netting Poles Bases Grading and Backfill Baseball Outfield
Demo Asphalt Paving for New Field House
New Field HouseBldg Pad looking NW & Ext. Building Demo
New Field House Bldg Pad looking North
Grading Baseball Field looking North
Walden Athletic Complex Atlanta Public Schools Weekly Construction Progress Report
WEEKLY CONSTRUCTION PROGRESS REPORT
Grading and Backfill for Netting Pole Bases Backfill & Compaction for Multi‐use Field
Grading and Backfill for Netting Poles Bases
Grading and Backfill Baseball Outfield
NEXT WEEK – Dec 3 thru Dec 9: Layout Building corners at Field House Start Footings Start CMU Foundation Plumbing rough‐in for slab Electrical rough‐in for slab Demolition of existing building ongoing Budget and Schedule Construction Budget: $7,390,000.00 Progress Earned: $0 Budget Status: On Budget Completion Date: August 8, 2018 (Substantial Completion) Schedule Status: On Schedule
Walden Athletic Complex Atlanta Public Schools Weekly Construction Progress Report
WEEKLY CONSTRUCTION PROGRESS REPORT
SCHEDULED DATE OF SUBSTANTIAL COMPLETION
August 8, 2018.
PREPARED BY:
Steven Carter, Parrish Construction
COPIES TO:
George Harkness, APS Michael Wright, Eberly & Associates Scott Griffin, Eberly & Associates John Rood, Parrish Construction Dave Yuhas, Parrish Construction Eric Wise, Parrish Construction Parrish Construction – Job File
Walden Athletic Complex Atlanta Public Schools Weekly Construction Progress Report