work breakdown structure (wbs)

Report 35 Downloads 178 Views
WORK BREAKDOWN STRUCTURE (WBS)

Project No. Doc. Date Page No. 1 of 2

Project Title

ENGINEERING, FABRICATION AND DELIVERY OF TEEMING LADLE FOR STEEL MELT SHOP

Project Manager

Name Del Fabro, Mr. Dino Elio

WBS ID 1.00 2.00 2.10 2.10.1 2.10.2 2.10.3 2.10.4 2.10.5 2.10.6 2.10.7 2.10.9 2.20 2.30 3.00 3.10 3.20 3.30 3.40 4.00 4.10 4.10.1 4.10.2 4.10.3 4.10.4 4.20 4.20.1 4.20.2 4.30 4.40 4.50 5.00 5.10 5.20 5.30 5.30.1 5.30.2 5.40 5.40.1 5.40.2 5.40.3 5.50

Authority Level Expert & Legitimate

Task/ Activity Name Engineering, fabrication and delivery of teeming ladle for steel meltshop 







Overall Project Activities  Prepare Project Documents  Issue Project Charter  Issue WBS  Issue Project Activities Sequence  Issue Project Schedule  Issue Project Budget  Issue Responsibility Assignment matrix  Issue Risk Analysis  Re-Examine Project  Kick Off Meeting  Review Project After Completion (Lessons Learned) Engineering  On-Site Survey  Issue Basic Engineering  Issue Detail Engineering  Issue Quality Control Plan Fabrication Materials Procurement  Procure Steel  Procure Plates  Procure Bottom Plates  Procure Drop Forged Materials  Procure Profiles  Procure Hardware Materials  Procure Screws  Procure Fittings  Procure Paint  Procure Welding Wire  Procure Welding Gas Fabrication  Cutting and Bending  Welding  Machining  Milling  Turning  Painting Activities  Sandblasting  Priming Coat application  Finish Coat application  Final Assembly

Contact Info [email protected]

WORK BREAKDOWN STRUCTURE (WBS)

Project No. Doc. Date Page No. 2 of 2

6.00 6.10 6.10.1 6.10.2 6.10.3 6.10.4 6.10.5 6.20 6.30 7.00 7.10 7.20 7.30 7.40 8.00 8.10 8.20 8.30 9.00 9.10 9.20 9.30









Inspections  Non Destructive Testing  Overall Visual Inspection  Visual Test of Welds (VT)  Dye Penetrant Test of Welds (PT)  Ultrasonic Test of Welds (UT)  Radiographic Test of Welds (RT)  Preliminary Acceptance Test  Final Acceptance Test Packing  Disassemble Ladle  Tag all Items  Pack all Items  Issue Packing List Delivery  Book Shipping  Load Goods  Shipping Quality Dossier  Collect Quality Certificates  Edit Quality Dossier  Issue Quality Dossier