Fullabrook Wind Farm, North Devon Local Resource Opportunities BF-PPT-001-001-003

2

Fullabrook Wind Farm, North Devon • 22 Wind Turbines, maximum capacity of 66MW • Planning Consent granted in October 2007 – largest onshore windfarm in England • Construction to start in July 2010 • Completion in Summer 2011 BF-PPT-001-001-003

3

BF-PPT-001-001-003

4

BF-PPT-001-001-003

5

Fullabrook Windfarm - Substation

BF-PPT-001-001-003

6

Fullabrook Windfarm – Section 278 Works

BF-PPT-001-001-003

7

Fullabrook Windfarm – Procurement Strategy

3 Main Contracts : • Turbine Supply & Install • Substation / Electrical Infrastructure • Balance of Plant / Civils Infrastructure BF-PPT-001-001-003

8

Fullabrook Windfarm – Contract Advertising OJEU Adverts Placed October – December 2009 Turbine Supply & Install Contract – Tendered November 2009 – Preferred Bidder Selected February 2010 Civils & Electrical Contracts – EOIs submitted January 2010 – Prequalification March 2010 – Tender Invitation May 2010

BF-PPT-001-001-003

9

Fullabrook Windfarm – Pre-Construction Opportunities • Substation / Electrical Works – Procured as a Design & Build Contract Design Involvement Expected: • Electrical Cabling / Switchgear • Control Building • Hard / Soft Landscaping BF-PPT-001-001-003

10

Fullabrook Windfarm – Construction Phase Opportunities S278 Adoptable Highway Works • Services Relocation • Traffic Management • Earthworks • Drainage • Blacktop / Concrete BF-PPT-001-001-003

11

Fullabrook Windfarm – Construction Phase Opportunities On-Site Works • Surveying • Fencing • Bulk Earthworks • Access Track Construction • Drainage BF-PPT-001-001-003

12

Fullabrook Windfarm – Construction Phase Opportunities On-Site Works • Cable Trench Excavation • Reinforced Concrete Foundations • Crane & Plant Hire • Abnormal Load Transportation • Devon Bank Opening / Reinstatement BF-PPT-001-001-003

13

Fullabrook Windfarm – Construction Phase Opportunities – Site Support Works • Office Unit Provision • Communications • Plant Maintenance • Administration • Workforce Accommodation • …and let’s not forget…………….. BF-PPT-001-001-003

14

…….the Caterers !!!!!!!

BF-PPT-001-001-003

15

Fullabrook Windfarm – The Figures • 10,500 m3 Concrete – Batching Plant? • 970 Tonnes Reinforcing Steel • 90 km 33kV Cabling • 12.5 km Access Tracks • • • •

20 km Stock-Proof Fencing 96,000 m2 Geotextile 48,000 m3 Stone 60+ Field Gates

• 1400 sqft Control Building BF-PPT-001-001-003

16

Fullabrook Windfarm – Post-Construction Phase Opportunities

• Planned & Reactive Maintenance Teams • Cleaning Contracts • Site Reinstatement Works BF-PPT-001-001-003

17

Fullabrook Windfarm – DWP / ESBs Commitment to Local Resourcing Devon Resources engaged to date: • • • • •

Geotechnical Archaeological Surveying Fencing Earthworks

BF-PPT-001-001-003

18

Fullabrook Windfarm – DWP / ESBs Ongoing Commitment • Main Contract Tenders to include a points based weighting to encourage local resource involvement • Details of Interested Organisations to be passed to Tenderers BF-PPT-001-001-003

19

Fullabrook Windfarm – Registering Interest Contact details and area of interest to be forwarded to: Rory Jordan [email protected] Tel: 07909938858 BF-PPT-001-001-003

20

Fullabrook Wind Farm, North Devon Local Resource Opportunities

Any Questions? BF-PPT-001-001-003