Bidding Construction and Capital Projects Purchasing PDC Part 1 – Pre-Bid Process Part 2 – Post-Bid Opening

65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16

Introduction Terry Felden – LEED AP BD+C, Director of k-12 Education for ICI, Inc. Ken Florey – Partner and Attorney for Robbins Schwartz Howard Metz – Partner and Attorney for Robbins Schwartz Ron Johnson – Director of Purchasing and Transportation for Oak Park and River Forest High School District 200 John Pahlman - Director of Operations for Niles Township High School District 219

65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16

Part 1 of 2: Pre-Bid Process •   Utopia C •   Thursday, May 5th - 9:30 – 10:30 AM

65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16

Pre-Bid Process •   Timeline planning is critical for the success of the project –   Define the scope of the project early –   Get the right people on the project team •   Empower District Staff with information that define characteristics for the selection of a Project Team on any construction related project.

–   Be aware of the zoning and building codes –   Building of the drawings •   Who is involved? –   Priority of Alternates 65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16

Pre-Bid Process •   Building the bid documents and running the bid process –   Specifications –   Bonding Requirements –   Drawings –   Broiler Plate Documents –   Mandatory or Voluntary Pre-Bid Meeting –   Contract/ agreement. AIA? –   Instructions to Bidders –   Advertisement for Bid 65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16

Pre-Bid Process •   Project Labor Agreements (PLA’s) •   Legal requirements for posting •   Advantages/Benefits •   Disadvantages •   Only Union firms will bid? •   Is this really just a panacea?

65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16

Part 2 of 2: Post-Bid Opening •   Utopia C •   Thursday, May 5th – 11:00 AM – 12:00 PM

65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16

Post-Bid Opening •   Qualifications of Contractors –   Clear and objective qualification criteria must be set in the bid documents –   Interview the apparent low bidder, scope review –   Negative references must have written documentation

•   Evaluation of Bids –   Responsive •   A Bid which is in strict compliance with the Bidding Documents

–   Responsible •   Assessed based upon the contractor’s past history and technical experience on similar sized and/or complex projects, its financial and bonding capacity, the depth and experience of its labor forces and management personnel 65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16

Post-Bid Opening •   Evaluation of Alternates –   How do you take into account the base bid and alternates? –   Clearly establish which alternates are the priority for the educational purposes of the District. –   Read the alternate amounts at the bid opening. –   Award the alternates with the Board Action for the Contract.

65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16

Post-Bid Opening •   Awarding the Contracts •   Contract Compliance Practices •   Best Practices in Monitoring Project Milestones –   Steps to take when project is derailing

65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16

Other Resources •   List other presentations

65th ILLINOIS ASBO CONFERENCE AND EXHIBITIONS May 4 – MAY 6, 2016 @IllinoisASBO #iasboAC16