Bond Issue Vote February 10, 2015

Report 1 Downloads 48 Views
Bond Issue Vote February 10, 2015

Storm Shelter Protection Gaps Irving PK Mark Twain Elementary Plato Elementary Duncan High School EDGE Academy/5th Grade Center

Irving PK, Mark Twain & Plato Step 1 Pre-Fabricated Storm Shelters Funding Source: Building Fund * Awaiting Bids

Step 2 February 10, 2015 $2.7 Million Bond Issue Vote * Fifth Grade Center Kitchen, Dining Area, HVAC, 4 Classrooms and Storm Shelter Access * Duncan High School Safe Room & 4 Art Classrooms

5th Grade Center *87% Support 5th Grade Center (2014 Survey of Elementary Parents) *Reduce Over Crowding at Emerson, Horace Mann and Plato Proposed Project Includes: Renovate/Create Storm Shelter Area Four Additional Classrooms Serving Kitchen and Dining Area

Project Location

5TH GRADE CENTER

PROPOSED STORM SHELTER PACKAGE

Architectural Drawing

PROPOSED 5TH GRADE CENTER (Former Edge Academy) PROPOSED STORM SHELTER PACKAGE

Duncan High School 4 Art Classrooms & Saferoom

Architectural Drawing

EXISTING ART BUILDING AT DUNCAN HIGH SCHOOL PROPOSED STORM SHELTER PACKAGE

Architectural Rendering

BIRD’S EYE VIEW – SITE PLAN ADDITION AND RENOVATIONS TO DUNCAN HIGH SCHOOL

Project Location

STORM SHELTER/ ART CENTER

PROPOSED STORM SHELTER PACKAGE

Architectural Drawing

STORM SHELTER/ART CENTER AT DUNCAN HIGH SCHOOL PROPOSED STORM SHELTER PACKAGE

2015 Bond Issue 2012 - Voters Approved 17.6 mils 2015 Bond Issue: 18.49 mils (A .89 mil increase from 2012) Assessed 15.02 mils 2014 $2,700,000 Bond Issue 3.47 Storm Shelter mils

Cost Calculation * Net Assessed Value of Home X .0001 (mil) X 3.47 mils / 52 weeks= Cost per Week

Examples $150,000 Home = $1.00 per week $75,000 Home = $.50 per week $50,000 Home = $.33 per week

Vote February 10, 2015