PROJETO BUS RAPID TRANSIT (BRT) SANTA CLARA-ALUM ROCK
SANTA CLARA-ALUM ROCK BUS RAPID TRANSIT (BRT) PROJECT
Reconstrução e Pavimentação da via na Alum Rock Avenue
Alum Rock Avenue Roadway Reconstruction and Paving
Os seguintes pontos entrarão em vigor, caso o tempo e as condições o permitam:
The following will be in effect as indicated, weather and conditions permitting:
O QUÊ: A reconstrução e pavimentação da via serão efetuadas por segmentos no lado norte (em direção a oeste) da Alum Rock Avenue desde a Sunset Ave., to west of McCreery _________________________________________________________ Including front of Book Buyers/Discount ________________________________________________________. Store, Flamingos, portion of N.Sunset
QUANDO:
Cada segmento levará 72 horas a ser concluído e incluirá 2 a 3 noites de atividades ligadas à construção desde
5/4/15,7pm - 5/7/15, 7pm _________________________________________________________ ________________________________________________________. Os acessos estarão inacessíveis a todos os veículos, exceto os de emergência, durante o referido período de 72 horas. O acesso de peões estará disponível. As atividades produzirão ruído, vibração e impactos consideráveis no trânsito, incluindo, entre outros: • Aumento do trânsito de pesados • Serragem e trituração do asfalto • Uso de equipamento pesado para demolição e remoção de betão • Abertura de fossos e escavação • Alarmes de recuo do equipamento (bip) • Luzes intensas • Compactação e Pavimentação • Poeiras • Desvio de peões/de trânsito
ESTACIONAMENTO: Os acessos estarão
inacessíveis a todos os veículos. O acesso de peões estará disponível. • Poderá estacionar nas ruas das proximidades durante as obras. ______________________________________________________ _____________________________________________________ • Comunidades de habitação múltipla: Se um dos acessos alternativos a partir da Alum Rock Avenue estiver vedado, contacte a administração para abrir o acesso.
RUÍDO: Poderão ocorrer trabalhos nocturnos para reduzir a duração do encerramento dos acessos. São esperados ruídos e vibrações intensas devido ao uso de equipamento pesado para demolições e remoção de betão, serragem, trituração do pavimento e alarmes de segurança. As sugestões para minimizar o ruído incluem manter as janelas viradas para a Alum Rock Avenue fechadas e usar tampões para os ouvidos (fornecidos). LIXO:
A recolha do lixo não estará disponível de segunda a quinta neste segmento.
NOTAS: Para segurança do público e dos trabalhadores da
construção civil, serão tomadas medidas de controlo de tráfego sempre que necessárias. Serão colocados sinais de aviso para garantir a segurança. As equipas de construção farão o possível para manter as passagens e para minimizar os inconvenientes para os motoristas, ciclistas, peões, empresas e moradores.
Roadway reconstruction and paving will be performed on the north side (westbound) of Alum Rock Avenue from Sunset Ave. to west of McCreery ______________________________________________________
Night work may be required to reduce the duration of closed driveways. Heavy noise and vibration is to be expected from heavy equipment for demolition and concrete removal, saw-cutting, grinding of pavement, and back up alarms. Suggestions to help minimize the noise include keeping windows facing Alum Rock Avenue closed, and consider ear-plugs (provided).
Including front of Book Buyers/Discount _____________________________________________________. GARBAGE: Garbage pick-up will not be available Store, Flamingos, portion of N.Sunset
WHEN:
This segment will take 72 hours to complete and may include 1-3 nights of construction activities from ______________________________________________________
5/4/15, 7pm - 5/7/15, 7pm _____________________________________________________. Driveways will be inaccessible to all vehicles except emergency vehicles during this 72 hour period. Pedestrian access will be maintained. Activities will generate noticeable noise, vibration, and traffic impacts, including and not limited to: • Increased truck traffic • Saw cutting and grinding of asphalt • Heavy equipment used for demolition and concrete removal • Trenching and excavation • Equipment back up alarms (beeping) • Bright lights • Compaction and paving • Dust • Pedestrian/Traffic detours
Monday through Thursday in this segment.
NOTES: For the safety of the public and construction workers, traffic control measures will be used when needed. Information and warning signs will be posted to ensure safety. Construction crews will make every effort to maintain access and minimize inconvenience to motorists, bicyclists, pedestrians, businesses and neighbors. For more project information: VTA Community Outreach (408) 321-7575 | TTY only (408) 321-2330 Email:
[email protected] Website: www.vta.org/scar-brt
A
y e
Av
te
ga
st Ea e Av
1503-0051
er re
cC
M
______________________________________________________ • Multi-housing communities: If there is an alternate driveway off of Alum Rock Avenue that is gated, contact your management to make this driveway accessible.
Ro
e Av et
lum
ns
PARKING: Driveways will be inaccessible to all vehicles. Pedestrian access will be available. • Consider parking on nearby side streets during this time. ______________________________________________________
ve
A ck
Su
Para mais informações sobre o projeto: Comunicação da Comunidade VTA (408) 321-7575 | Apenas TTY (408) 321-2330 E-mail:
[email protected] Web: www.vta.org/scar-brt
WHAT:
NOISE:
PROYECTO DE TRANSPORTE RÁPIDO DE AUTOBÚS (BRT) DE LA RUTA SANTA CLARA-ALUM ROCK Reconstrucción y pavimentación vial de Alum Rock Avenue Las siguientes actividades se estarán llevando a cabo, tal y como se indica, si el clima y las condiciones lo permiten:
QUÉ: La pavimentación y reconstrucción vial se llevarán a
cabo en el lado norte (rumbo al oeste) de Alum Rock Avenue desde Sunset Ave., to west of McCreery ______________________________________________________
Including front of Book Buyers/Discount _____________________________________________________. Store,Flamingos, portion of N.Sunset
CUÁNDO: Este segmento tomará 72 horas para concluirlo y podría incluir de 1 a 3 noches de actividades de construcción de ______________________________________________________ 5/4/15,7pm - 5/7/15, 7pm _____________________________________________________. Durante este periodo de 72 horas las entradas de las cocheras serán inaccesibles para todos los vehículos excepto los vehículos de emergencia. Se conservará el acceso para peatones.
Including front of Book Buyers/Discount Store,Flamingos, portion of N.Sunset
BASURA: El servicio de recolección de basura no estará disponible en este segmento de lunes a jueves.
5/4/15,7pm - 5/7/15, 7pm
NOTAS: Para mayor seguridad del público y del
personal de construcción, se implementarán medidas de control del tránsito conforme sean necesarias. Se colocarán avisos de información y precaución para garantizar la seguridad. Las cuadrillas de construcción harán todo lo posible por mantener el acceso y minimizar los inconvenientes para los conductores, ciclistas, peatones, negocios y vecinos.
et Av e
er
re cC
M y e
Av
te
ga st e Av
et
M
e Av
A
Ro
ns
lum
ve
A ck
Su
Las entradas de las cocheras estarán inaccesibles a todos los vehículos. Estará disponible el acceso para peatones. • Considere estacionarse en calles aledañas durante este periodo. ______________________________________________________ ______________________________________________________
R
e
Av
ns
um Al
k oc
Su
Para más información sobre el proyecto: Programa de Extensión de VTA en la Comunidad (VTA Community Outreach) (408) 321-7575 | Solo TTY (408) 321-2330 Email:
[email protected] Sitio web: www.vta.org/scar-brt
ESTACIONAMIENTO:
ry
ee
r cC e
ga st
Av
Ea te e
Av
• Comunidades multiviviendas: Si existe una entrada alternativa a una cochera en Alum Rock Avenue que esté cercada, contacte a sus administradores para hacer esta entrada accesible.
Sunset Ave to west of McCreery
Ea
Las actividades generarán un ruido considerable, vibración e impactos al tráfico, incluyendo, pero sin limitarse a lo siguiente: • Aumento en el tráfico de camiones de carga • Corte con sierras y molienda de asfalto • Presencia de equipo pesado utilizado para demolición y retiro de concreto • Apertura de zanjas y excavaciones • Alarmas de retroceso de los equipos (pitidos) • Luces intensas • Compactación y pavimentado • Polvo • Desviaciones de peatones y tráfico
RUIDO: Podría ser necesario realizar labores nocturnas para reducir la duración del cierre de cocheras. Es de esperar que haya ruido y vibración fuertes causados por el equipo pesado de demolición y retiro de concreto, corte con sierras, molienda de pavimento y alarmas de retroceso. Algunas sugerencias para ayudar a minimizar el ruido incluyen mantener cerradas las ventanas ubicadas al lado de Alum Rock Avenue, y considerar usar tapones para los oídos (proporcionados).