City of Buda 2014 Bond Program

Report 0 Downloads 11 Views
February 20, 2018

CITY OF BUDA 2014 BOND PROGRAM UPDATE Proposition 1 – City Hall/Library Proposition 2 – Public Safety Building Heritage Tree Relocation / Site Development

Project Update • Proposition 1 - City Hall / Library: • Work in Progress as of February 20, 2018:

• 1. • 2. • 3. • 4.

• 5. • 6.

Exterior metal trim around the eave of the roof is complete Exterior wood finishes 85% Complete– Stone 100% complete Exterior wall glass and glazing complete Area C (City Hall) – Complete - punch list items ongoing Area B (Public Space) – 80% Complete – Finishes ongoing, millwork installation ongoing, IPE wood installation 80% complete. Area A (Library) – 75% Complete – Finishes on going, ceiling, electrical, lighting installation, millwork, doors and frames and hardware installation - on going.

Project Update • Proposition 1 - City Hall / Library: • Work in Progress as of February 20, 2018 (continued):

• 7. Interior glass and glazing – 95% complete. • 8. Communication and data cabling - on going. • 9. Back-up generator is in place and functioning.

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update

Project Update • Proposition 1 & 2 – Site Development • Work in Progress as of February 20, 2018:

• • • • • • • • • •

1. 2. 3. 4. 5. 6. 7. 8. 9. 10.

Pavement, curb and gutters in parking lot - complete Final installation of light poles in the parking lot complete Retaining wall installation at Reading Garden and Front Entry complete Walks at Reading Garden – 90% complete Sidewalk from Main Street 90% complete Rough grading in progress on South side of the building Monument sign base set – work continuing. Electrical for site lighting in progress Force protection along Main street 80% complete

Pedestrian Bridge – final finishes in progress

Project Update • Proposition 1 & 2 – Site Development • Work in Progress as of February 20, 2018 (continued): • 11.

Site electrical for site lights are being run on the south side of the building. • 12. Heritage Tree: Weekly feeding and watering of the tree continues. Based on the latest report the tree continues to thrive. A one year maintenance agreement is being issued to monitor the continual growth.

Project Update

Project Update • Proposition 2 – Public Safety Building: • Complete and operational • Warranty period is in affect