Community Meeting - Arlingtonva

Report 14 Downloads 69 Views
2/24/2011

Arlington County Department of Environmental Services

Ballston Beaver Pond Improvement Project

Community Meeting February 24, 2011

In Association With:

I N T R O D U C T I O N

Project Goals and Objectives  Maintain flood protection and improve stormwater         quality treatment  Provide TMDL Credits (Chesapeake Bay)  Improve Wildlife  Habitat and  Public Education  Improve Public Access  Impro e P blic Access and Interpretation Community Outreach

1

2/24/2011

I N T R O D U C T I O N

Presentation Agenda  Project Goals, Objectives and Progress Water Quality Enhancements  Ecosystem Restoration Community Connections  Public Outreach and Participation P bli O t h d P ti i ti

Project Goals, Objectives and Progress  Water Quality  Enhancements Ecosystem Restoration  Community Connections  Public Outreach and  Participation

2

2/24/2011

W A T E R

Q U A L I T Y

E N H A N C E M E N T S

Water Quality / SWM Goals  Water Quality Improvements • Extended Detention / Pollutant Removal • Chesapeake Bay TMDLs h k • NPDES Permit Requirements

 Peak Flow Reduction/  Enhancement • WQ Storm • 1‐year, 2‐year, 5‐year

 Reduce Short‐Circuiting • Longer Flow Paths

 Litter Control No Upstream Impacts

W A T E R

Q U A L I T Y

E N H A N C E M E N T S

Possible Design Considerations  Reclaim Existing Pond Volume • Excavate accumulated sediment

 Increase Pond Resonance Time • Low‐flow channels, feeder “channels”

 Increase Biological Uptake with Plantings • Cleaner Water ‐ Let the Plants do the Work

3

2/24/2011

W A T E R

Q U A L I T Y

E N H A N C E M E N T S

Progress to Date  Completed Draft Field Survey  Pond Rating Curves Developed  Hydrologic Modeling Initiated  Utility Coordination Current Priority 

Project Goals, Objectives and Progress  Water Quality  Enhancements Ecosystem Restoration  Community Connections  Public Outreach and  Participation

4

2/24/2011

E C O S Y S T E M

R E S T O R A T I O N

Ecosystem Restoration Goals  Manage Invasive Species  Promote Plant Community  Diversity  Promote Habitat Diversity

E C O S Y S T E M

R E S T O R A T I O N

Possible Design Considerations  Hydrologic  y g Variability through  Grading  Enhance Cover  and Underwater  Structure  Enhance Soils to  Enhance Soils to Promote Native  Plant Growth

5

2/24/2011

E C O S Y S T E M

R E S T O R A T I O N

Progress to Date  Wetland Delineation  Complete  Draft Natural Resources  Inventory Complete  Draft Tree Survey  Complete

Project Goals, Objectives and Progress  Water Quality  Enhancements  Ecosystem Restoration  Community Connections  Public Outreach and  Participation

6

2/24/2011

C O M M U N I T Y

C O N N E C T I O N S

Connectivity

Four Mile Run Example

C O M M U N I T Y

C O N N E C T I O N S

Interpretive Elements

7

2/24/2011

C O M M U N I T Y

C O N N E C T I O N S

Educational Opportunities

C O M M U N I T Y

C O N N E C T I O N S

Community Connections

8

2/24/2011

C O M M U N I T Y

C O N N E C T I O N S

Community Connections

Project Goals, Objectives and Progress  Water Quality  Enhancements  Ecosystem Restoration  Community Connections  Public Outreach and  Participation

9

2/24/2011

PU B LI C O U T R EAC H & PAR T I C I PAT I O N

Public Outreach

PU B LI C O U T R EAC H & PAR T I C I PAT I O N

Community Engagement Providing multiple opportunities for the  exchange of ideas and for feedback. Structure:  A series of meetings throughout the  study process for … •Stakeholder Advisory Committee •The Community at large Schedule of Community Meetings: •Initial Information Meeting  (February 24, 2011) •Design Concept Input (May 2011) •50% Design Review (October 2011)

10

2/24/2011

PU B LI C O U T R EAC H & PAR T I C I PAT I O N

JANUARY STAKEHOLDER ADVISORY COMMITTEE MEETING: KEY ISSUES What do you value about this area? •The open space it provides •The wildlife •An “urban oasis” What would you like to change? •Graffiti, trash, pests •Better/more access points B tt / i t Now, it’s your turn!

PU B LI C O U T R EAC H & PAR T I C I PAT I O N

QUESTIONS FOR TONIGHT 1. What do you currently value about the pond? 2 How do you currently use the pond and its  2. How do you currently use the pond and its surrounding area, and how do you see others  using it? 3. What would you like to see changed in this  area? 4 What would you not want to see changed? 4. What would you not want to see changed? 5. What interpretive opportunities might we  consider for the area, including any good  ideas that you have seen used elsewhere?

11

2/24/2011

Arlington County Department of Environmental Services

Ballston Beaver Pond Improvement Project

Community Meeting February 24, 2011

In Association With:

12