Crystal City Potomac Yard Transitway Project - Arlingtonva

Report 5 Downloads 97 Views
Crystal City Potomac Yard Transitway Project Arlington Segment

Construction Start-Up May 29, 2014

Agenda • Project purpose / background • Anticipated construction timeline and sequence • Anticipated potential disruptions • Ongoing updates • Q&A

Crystal City Potomac Yard Transitway Project

2

Transitway Project Purpose • Provide high-capacity and high-quality bus transit service • Support new transit-oriented development in Potomac Yard in Arlington and Alexandria • Extend the reach of the Metrorail system • Support redevelopment in Crystal City • Set the stage for streetcar

Crystal City Potomac Yard Transitway Project

3

Benefits • Manage congestion in Route 1 corridor • Provide faster, more reliable travel for transit users (9%38% travel time savings) • Attract riders to transit with frequent and convenient service and station amenities • Prepare for future streetcar

Crystal City Potomac Yard Transitway Project

4

Project Context • • • • • •

Bus Transitway Crystal City Sector Plan Two-way of Crystal Drive Planned two-way of Clark/Bell Crystal City streetcar Coordination with City of Alexandria

Crystal City Potomac Yard Transitway Project

5

Arlington’s Transitway Alignment & Station Locations

Approved Approved

Crystal City Potomac Yard Transitway Project

6

Construction Schedule • Board approved contract award and funding in February 2014 • County and contractor executed contract in March 2014 • Construction duration is 300-330 calendar days • Mobilization, surveys and site prep underway • Inspections and acceptance in late Winter 2015 • Transitway opening in Spring 2015 • On-going coordination with Alexandria and WMATA, and other County projects in Crystal City Crystal City Potomac Yard Transitway Project

7

Construction Schedule • Construction duration is 300-330 calendar days • Phase 1 – Roadway and stations in Potomac Yard o Eight month duration o Mobilization, surveys, site preparation o Begin construction of stations A, B and C • Phase 2 – Finish station B in Potomac Yard o 15 day duration, following end of Phase 1 • Phase 3 – Construct stations D, E, F, G and lane markings in Crystal City o 80 day duration, some of which is concurrent with Phase 1 • Phase 4 – 18th and Bell intersection improvement o To be completed concurrently under separate construction contact • Phases 5 and 6 – Complete stations and install furnishings and signage o 24 day duration, following end of Phase 2 o Finish construction of stations A and C, including manhole structure Crystal City Potomac Yard Transitway Project

8

Construction Disruptions • Lane closures  Crystal Drive never completely shut down  Two-way traffic maintained • Day, night and weekend work  Day shift Monday thru Friday, 7:00 a.m. to 4:30 p.m.  No roadway work 6:30-9:30 a.m. and 3:30-6:30 p.m.  Night shift, when applicable, Monday thru Friday, 8:00 p.m. to 4:30 a.m.  Weekend work, if scheduled, Saturday only from 9:00 a.m. to 4:30 p.m. • Noise  The contractor must abide by the Arlington County Noise ordinance • Pedestrian detours  No more than one block for pedestrian detours  Storefronts remain open  Accessibility will be maintained

Crystal City Potomac Yard Transitway Project

9

Keeping Track • Construction updates posted on County website: http://sites.arlingtonva.us/ccpc/construction-underway/ • Subscribe to our email update at: http://sites.arlingtonva.us/ccpc/transit-improvements/crystal-citypotomac-yard-transitway/

• Bee Buergler, Program Manager, [email protected] 703-228-0597

Crystal City Potomac Yard Transitway Project

10

Comments and Questions?