Owner: Iowa Western Community College To Contractor: Lueder Construction Supplemental Instruction No: ASI #005-Football Skyfold/Meeting Rooms Updates Date: July 6, 2016
The Work shall be carried out in accordance with the following supplemental instructions issued in accordance with the Contract Documents without change in Contract Time. If there is a change in Contract Time or Cost, submit a Cost Summary on the Architect’s Form, along with backup information with any change in contract time, before proceeding with the Work. DESCRIPTION:
Per Skyfold submittals, the panels have an area of clearance in order to operate up and down where nothing can be protruding into the area. The following items shall be coordinated by the Contractor to accommodate this area of clearance: Refer to the attached drawing ASI 05- SD1 for south elevation of meeting rooms showing the clearance area. Doors 014A, 016A, 018A, 020A shall be installed closer to Hall 012 in order for the door hardware to not be in the clearance area. The walltalker shall be installed at the length shown. Do not provide a frame as specified. Do provide a marker tray as specified, but the length shall be outside the clearance area. Refer to EDA’s electrical Field Directive E-1 and drawings E1.0-1, E2.0-1. E3.0-1 for electrical updates. Refer to ASI 05- SD1 for the south elevation of the meeting rooms for clarification.
X____________________________ Dean S. Fajen HGM Associates Inc.
Attachments: EDA-Electrical Field Directive E-1 and drawings E1.0-1, E2.0-1. E3.0-1 ASI 05- SD1 S:\ARCH\Projects\107115 Ia Western Football-Wrestling\CO ASI RFI\ASIs\ASI-4\ASI-4 Tracer Wire.doc
ELECTRICAL FIELD DIRECTIVE DIRECTIVE NO. E-1
Date: July 5, 2016 Engineers Project No.: 1534
PROJECT:
Iowa Western Football & Wrestling Building
OWNER:
Iowa Western Community College – Council Bluffs, Iowa
CONTRACTOR(S):
General: Mechanical: Plumbing: Electrical:
Lueder Construction – Omaha, Nebraska Grunwald Mechanical Contractors – Omaha, Nebraska Vincentini Plumbing – Omaha, Nebraska O’Neal Electric – Red Oak, Iowa
Attachments: Sketch E1.0-1, E2.0-1 & E3.0-1 Please note the following clarification to the original construction documents. The following item(s) should not be considered as a change to the cost or the time schedule, but only as a directive to modify the original plans. Refer to attached sketches. Note the “bubbled” devices. These devices are shown in a new location differing from the issued Construction Documents. Make these adjustments to accommodate the “Skyfold” folding partition wall required clearances. Field verify block coursing and install such that the devices do not impinge in the folding wall space. Utilize the next block opening away from the folding wall if it appears that the device will overlap the required clearance area. See architectural sketches for new elevations related to the field directive. In addition, coordinate with mechanical for revised thermostat locations on the north side of the rooms. These new locations are shown for reference on Sketch E3.0-1. Sketch E1.0-1: Bubbled devices are new locations for exit lights and low voltage light switches. Sketch E2.0-1: Bubbled devices are new locations for receptacles and Skyfold control button stations. Sketch E3.0-1: Bubbled devices are new locations for AV, CC and 2 gang deep box. Note the new locations for the T-stat rough-ins. DIRECTIVE BY:
cc:
Michael A. King, P.E.