clay street bridge replacement

Report 0 Downloads 138 Views
HYDROLOGY /HYDRAULICS REPORT . EL DORADO COUNTY

CLAY STREET BRIDGE REPLACEMENT Prepared by:

Joseph Domenichelli Domenichelli & Associates 1107 Investment Blvd., Suite 145 El Dorado Hills, California 95762 (916) 933-1997 JULY 14, 2009

HYDROLOGY/HYDRAULICS REPORT Clay Street Bridge Replacement El Dorado County, California P R O J E C T L O C AT I O N A N D D E S C R I P T I O N Clay Street Bridge is located in El Dorado County near downtown Placerville. The existing bridge is a two-span concrete arch structure. Hangtown Creek flows under the north span of the bridge and the south span of the bridge serves as the outfall location for Cedar Ravine. Flow from Cedar Ravine joins Hangtown Creek directly downstream from the bridge. The existing bridge has a total span of approximately 60'-0" with a maximum opening width of approximately 21'-0" over the Hangtown Creek channel. The bridge width is approximately 19'-0". It is supported on concrete wall abutments at the banks and there is a central pier that ties into the concrete channel wall on the upstream side of the bridge. The central pier also separates Hangtown Creek and Cedar Ravine flow. The bridge width is insufficient for traffic demands and does not meet freeboard requirements for the 50-yr or 100-yr flows. There are existing utilities that run below or adjacent to the bridge. These utilities include sewer lines and manhole risers and a water line that is attached to the bridge on the west side. There are also multiple drain/culvert pipes and many unidentified pipes in the vicinity of the bridge. The in-channel utilities will be removed prior to bridge removal.

Figure 1 –Clay Street Bridge.

Figure 2 –Existing utilities downstream of Clay Street Bridge.

It is proposed to remove the existing bridge (including 8'x20' of concrete sill in channel) and replace it with a single span bridge that has a total open span length of 32'-0" and an overall width of 45'-6". The proposed bridge will have concrete barrier type 80SW (mod) with architectural treatment and barrier mounted iron railings. The bridge deck type has not been selected. It will either be a cast-in-place reinforced concrete slab with a depth of 2'-0" or a pre-cast pre-stressed slab with a depth of 1'-9". The City would like to minimize

1

Clay Street Hydrology/Hydraulics

removal of the existing 66" corrugated metal culvert for Cedar Ravine. However, the proposed bridge design will require the Cedar Ravine pipe outlet to be reconstructed and the embankment regraded.

H A N G T O W N C R E E K A N D C E D A R R AV I N E H Y D R O L O G Y A hydrologic analysis was completed to establish design flows for the 50-yr and 100-yr events for Hangtown Creek and Cedar Ravine. A computer model was developed to determine these flows using the Army Corps of Engineers' Hydrologic Engineering Center's Hydrologic Modeling System (HEC-HMS version 3.0.1). The El Dorado County Drainage Manual was used in conjunction with the U.S. Department of Natural Resources Conservation Service (NRCS) to determine watershed conditions such as rainfall and soil data. Other watershed conditions such as channel storage potential, channel Manning's n-values and existing surface development were determined during a site visit. The City will require that flows from new developments within the watershed be mitigated to existing flow conditions so that peak flows in Hangtown Creek will not increase in the future. A flow verses frequency relationship for Hangtown Creek and Cedar Ravine are shown in the tables below. The combined flow for Hangtown Creek upstream of Clay Street and Cedar Ravine at Clay Street does not equal the flow at the confluence because the two stream hydrographs do not peak at the same time. Table 1: Peak flow rates for the 50-yr event. Location

Peak Flow Rate (cfs)

Hangtown Creek just upstream of Clay Street

2453

Cedar Ravine at Clay Street

381

Confluence of Hangtown Creek and Cedar Ravine

2782

Table 2: Peak flow rates for the 100-yr event. Location

Peak Flow Rate (cfs)

Hangtown Creek just upstream of Clay Street

2852

Cedar Ravine at Clay Street Confluence of Hangtown Creek and Cedar Ravine

450 3219

HANGTOWN CREEK HYDRAULICS Existing Conditions Model An existing conditions computer model was created for both Hangtown Creek and Cedar Ravine using the Army Corps of Engineers' Hydrologic Engineering Center River Analysis System (HEC-RAS version 3.1.3). Survey by Area West Engineers provided existing channel cross sections of Hangtown Creek both upstream and downstream of Clay Street. Manning's n-values for Hangtown Creek varied from 0.03 in the channel to 0.05 along the banks. A Manning's n-value of 0.014 was used for the concrete sill located in the channel on the downstream side of Clay Street Bridge.

2

Clay Street Hydrology/Hydraulics

Figure 3 –Manning's n-values from 0.03-0.05 for HC.

Contraction and expansion coefficients of 0.3 and 0.5, respectively, were set in the vicinity of Clay Street Bridge and the Bedford Avenue Bridge downstream from Clay Street. The existing bridge geometry was entered into the model based on field measurements. Figure 4 and 5 show HEC-RAS cross-sections upstream and downstream of Clay Street Bridge. Figure 6 shows a profile through the existing bridge. The gray shaded areas represent blockage from structures such as the bridge deck/abutments. The top of existing bridge deck (not including railings) is at an elevation 1867.25 feet and the top soffit of the bridge arch is at an elevation of 1864.75 feet. Figure 4 –Existing conditions cross section (upstream). Clay Street

Plan: Existing Clay Street

River = Hangtown Creek Reach = Clay Street .03

Figure 5 –Existing conditions cross section (downstream).

.03

RS = 941.5 .045

BR

Clay Street Clay Street Bridge

.05

Plan: Existing Clay Street

River = Hangtown Creek Reach = Clay Street

.03

.03

1868

1868

Legend WS 100 YR WS 50 YR

1866

. 0 1 4

.03

. 0 1 4

RS = 941.5

BR

Clay Street Bridge

.045 Legend WS 100 YR WS 50 YR

1866

Ground

Ground

Ineff

Ineff

Bank Sta

1864

1862 Elevation (ft)

1862 Elevation (ft)

Bank Sta

1864

1860

1860

1858

1858

1856

1856

1854

1854

1852

1852 0

50

100

150

200

0

Station (ft)

50

100

150

200

Station (ft)

3

Clay Street Hydrology/Hydraulics

Clay Street

Plan: Existing Clay Street Legend WS 100 YR WS 50 YR

1870

Ground LOB ROB

Elevation (ft)

1860

0

200

400

600

800

1000

Deck

1175

1079

931 Clay St Bridge

500

1840

861

645 Bedford Ave Bridge

1850

1200

Main Channel Distance (ft)

Figure 6 –Existing conditions 50-yr and 100-yr profile.

Approximately 249' upstream from Clay Street Bridge is a deck off of a building that spans over the channel. The deck is approximately 22' x 50' and it contains one pier that is one foot wide. Approximately 282' downstream of Clay Street Bridge is Bedford Avenue Bridge. This bridge is 19' wide with a 26' span. The existing model was run with the flows described previously. Results in the vicinity of Clay Street Bridge are presented in the following tables. Table 3: 50-yr water surface elevations and velocities for the existing bridge. Cross-section (River Sta)

Location Relative to Bridge

WSEL (feet)

Channel Velocity (fps)

294' upstream

1870.0

7.2

1175

234' upstream

1866.4

13.9

1079

138' upstream

1865.5

10.6

953

12' upstream

1865.2

10.0

931

11' downstream

1862.7

16.2

861

81' downstream

1863.9

7.2

1235 Deck off of house

Clay Street Bridge

4

Clay Street Hydrology/Hydraulics

Cross-section (River Sta)

Location Relative to Bridge

WSEL (feet)

Channel Velocity (fps)

268' downstream

1863.6

6.4

645

297' downstream

1860.6

13.1

500

442' downstream

1859.9

10.6

0

942' downstream

1849.9

10.6

674 Bedford Ave Bridge

Table 4: 100-yr water surface elevations and velocities for the existing bridge. Cross-section (River Sta)

Location Relative to Bridge

WSEL (feet)

Channel Velocity (fps)

294' upstream

1870.6

6.8

1175

234' upstream

1867.3

13.9

1079

138' upstream

1867.7

8.2

953

12' upstream

1866.7

10.3

931

11' downstream

1863.5

17.0

861

81' downstream

1864.3

7.7

674

268' downstream

1864.0

6.8

645

297' downstream

1862.1

10.9

500

442' downstream

1860.3

10.8

0

942' downstream

1850.3

10.8

1235 Deck off of house

Clay Street Bridge

Bedford Ave Bridge

As seen in the profile and related tables the existing bridge will nearly overtop during the 100-yr flood event and will pass the 50-yr flow with no clearance to the soffit.

Proposed Conditions Model The existing conditions model was modified to create the proposed conditions model. The proposed conditions model contains the new bridge geometry provided by Quincy Engineering, Inc. The proposed geometry was inserted into the model based on the provided plans shown in Appendix A. The alternative with the 2'-0" thick cast-in-place reinforced concrete slab was modeled for this analysis as hydraulically the most conservative alternative. If the alternative with the thicker slab meets clearance requirements then the other alternative will also meet clearance requirements. The proposed single span bridge will exceed the total width of the existing bridge by approximately 26'-6". Since the proposed bridge is much wider than the existing bridge, additional cross sections upstream and downstream from the bridge were created based on the topography provided by Quincy Engineering. The right side of the bridge was brought in 2 feet to account for debris that could potentially gather around the right side of the bridge abutment. Figure 7 and 8 show HEC-RAS cross-sections upstream and downstream of Clay Street Bridge. Figure 9 shows a profile through the new bridge. The top of the new bridge deck (not including the concrete barrier and hand railing) is at an elevation of 1868.57 feet and the bottom soffit of the bridge is at an elevation of 1866.57 feet.

5

Clay Street Hydrology/Hydraulics

Clay Street Plan: Final_Proposed Clay Street RS = 967.25 BR Clay Street Bridge .045

Clay Street Plan: Final_Proposed Clay Street RS = 967.25 BR Clay Street Bridge

.03

.045

1870

.03

1870

Legend

Legend

WS 100 YR

WS 100 YR

1868

1868 WS 50 YR

WS 50 YR

Ground

1866

Ground

1866

Ineff

1862

1862

1860

1860

1858

1858

1856

1856

1854 -40

-20

0

20

40

60

Bank Sta

1864 Elevation (ft)

Elevation (ft)

Ineff

Bank Sta

1864

1854 -40

80

-20

0

20

Station (ft)

40

60

80

Station (ft)

Figure 7 – Proposed conditions cross section (upstream).

Clay Street

Figure 8 – Proposed conditions cross section (downstream).

Plan: Final_Proposed Clay Street

Hangtow n Creek Clay Street 1875

Legend WS 100 YR

1870

WS 50 YR Ground LOB

1865

ROB

Elevation (ft)

1860

1855

Deck

1175

1079

1034.75

Clay St Bridge

500

1840

861

645 Bedford Ave Bridge

1845

921.25

1850

1835 0

200

400

600

800

1000

1200

1400

Main Channel Distance (ft)

Figure 9 – Proposed conditions 50-yr and 100-yr profile.

The same flow rates as in the existing conditions model were run with the new bridge in place. Results in the vicinity of the new bridge are presented in the following tables. Table 5: 50-yr water surface elevations and velocities for the proposed bridge. Cross-section (River Sta) 1235

WSEL (feet)

Channel Velocity (fps)

245' upstream

1870.0

6.7

185' upstream

1866.4

13.8

Location Relative to Bridge

Deck off of house 1175

6

Clay Street Hydrology/Hydraulics

Cross-section (River Sta)

Location Relative to Bridge

WSEL (feet)

Channel Velocity (fps) 9.2

1079

89' upstream

1866.3

1034.75

45' upstream

1866.4

7.6

995.25

5' upstream

1864.9

11.1

939.25

5' downstream

1863.1

14.2

921.25

23’ downstream

1863.4

10.3

861

84' downstream

1863.9

7.2

674

271' downstream

1863.6

6.4

645

300' downstream

1860.6

13.1

500

445' downstream

1859.9

10.6

0

945' downstream

1849.9

10.6

Clay Street Bridge

Bedford Ave Bridge

Table 6: 100-yr water surface elevations and velocities for the proposed bridge. WSEL (feet)

Channel Velocity (fps)

245' upstream

1870.6

6.9

1175

185' upstream

1867.3

13.9

1079

89' upstream

1867.3

9.0

1034.75

45' upstream

1867.3

7.8

995.25

5' upstream

1865.6

11.8

939.25

5' downstream

1863.9

14.6

921.25

23’ downstream

1863.5

11.7

861

84' downstream

1864.3

7.7

674

271' downstream

1864.0

6.8

645

300' downstream

1862.1

10.9

500

445' downstream

1860.3

10.8

0

945' downstream

1850.3

10.8

Cross-section (River Sta) 1235

Location Relative to Bridge

Deck off of house

Clay Street Bridge

Bedford Ave Bridge

Based on the results, the proposed bridge deck will have 1.73 feet of clearance between the deck soffit and the 50-yr water surface and can pass the 100-yr flow with 1.0 foot of clearance (shown in Table 7), therefore, exceeding clearance and freeboard requirements. It is important to note that freeboard was calculated from top of deck and clearance was calculated from soffit. Table 7: Top of deck freeboard and soffit clearance for 50-yr and 100-yr events. 100-yr Freeboard (ft)

50-yr Freeboard (ft)

100-yr Soffit Clearance (ft)

50-yr Soffit Clearance (ft)

Existing Conditions

0.5

2.0

0.0

0.0

Proposed Condition

3.0

3.73

1.0

1.73

7

Clay Street Hydrology/Hydraulics

Table 8 provides a comparison between existing conditions and the proposed bridge conditions water surfaces immediately upstream of the bridges and at cross section 861 downstream of the bridges. The models show no difference in water surface elevations downstream from the bridge. The models show that the upstream water surface elevations decrease with the new bridge. The models also show the velocities slowing down through the new bridge. Therefore, the new bridge will have no negative impacts to the Hangtown Creek floodplain. Table 8: Comparison of water surface elevations and velocities for 50-yr and 100-yr events. 100-year Event

50-yr Event

WSE Downstream of Bridge (ft)

WSE Upstream of Bridge (ft)

Velocity through Bridge (fps)

WSE Downstream of Bridge (ft)

WSE Upstream of Bridge (ft)

Velocity through Bridge (fps)

Existing Conditions

1864.3

1866.8

16.6

1863.9

1865.3

15.2

Proposed Condition

1864.3

1865.6

11.9

1863.9

1864.9

11.3

Difference

0.0

-1.2

-4.7

0.0

-0.4

-3.9

C E D A R R AV I N E H Y D R A U L I C S Existing Conditions Model An existing conditions computer model was created for Cedar Ravine using the Army Corps of Engineers' Hydrologic Engineering Center River Analysis System (HEC-RAS version 3.1.3). Survey by Area West Engineers provided cross sections upstream on Cedar Ravine. The modeled portion of Cedar Ravine consists of approximately 40 feet of open channel that flows into a 4' x 7.8' box culvert. The box culvert extends for about 234 feet and then it transitions into a 66" corrugated metal pipe that extends for approximately 286 feet where it outlets into Hangtown Creek. Due to limited survey, all lengths and dimensions were approximated during a site visit. A Manning's n-value of 0.025 was used for the open channel segment of Cedar Ravine. Manning's nvalues of 0.017 and 0.024 were used for the box culvert segment and corrugated metal pipe segment, respectively. Cross sections and Manning's n-values downstream from the confluence of Hangtown Creek and Cedar Ravine remained the same as in the existing conditions model for Hangtown Creek.

Figure 10 –Manning's n-value of 0.025 for Cedar Ravine.

8

Figure 11 –Manning's n-value of 0.017 for box culvert.

Clay Street Hydrology/Hydraulics

The results show that Cedar Ravine cannot convey the 50-yr and 100-yr event flows through the culverts and some roadway flooding is anticipated during major storm events. Table 9 shows results for the culvert. Table 9: Flow vs. capacity for Cedar Ravine culvert. Location

Flow Rate (cfs)

Approximate flow conveyed in culvert

300

50-yr event flow

381

100-yr event flow

450

S C O U R A N A LY S I S A scour analysis of the Clay Street Bridge at Hangtown Creek was performed for the proposed bridge replacement (cast-in-place 2'-0" reinforced concrete slab). The other alternative was not analyzed because there should not be any significant difference in scour due to similar bridge alignment and dimensions. Evaluation of scour at the bridge is based on criteria and methodologies developed by the Federal Highways Administration, Hydraulic Circular No. 18 (HEC-18), Evaluating Scour at Bridges (February 1993). The analysis estimates scour potential that is based primarily on channel hydraulics, without consideration for streambed surface and subsurface conditions. It should be noted that the predictive scour equations were developed from laboratory tests using fine granular materials. The resulting values of estimated potential scour are typically conservative, especially in cases where the depth to scour resistant materials is shallower than the estimated scour depth.

H y d r a u l i c Va r i a b l e s Hydraulics variables such as channel flow, velocity and depth are adapted from the HEC-RAS Hydraulic Model for Hangtown Creek at the proposed Clay Street Bridge.

Soils Investigation A preliminary foundation report was created by Taber. The report states that the stream channel contains bedrock that shows little erosion from flow and it appears to be scour resistant. Although the extent and depth of bedrock in the channel was not stated, the depth of scour resistant materials can be expected to be less than the calculated scour depths. When designing bridge foundations, depth to this scour resistant material should be accurately determined.

L o n g Te r m A g g r a d a t i o n a n d D e g r a d a t i o n Long term changes in streambeds may be either by aggradation (filling) or degradation (cutting) of the streambed over long periods of time. Long term changes differ from short term modifications in that changes are not apparent within the year, as is the case with local scour of the streambed at bridges. Generally, short term (local) changes result from bridge hydraulics, while long-term changes are associated with changes in the hydraulics of the stream itself. Thus, long-term changes are noticeable throughout the stream reach and not just at bridge locations.

9

Clay Street Hydrology/Hydraulics

Due to the presence of exposed bedrock along the channel bottom of Hangtown Creek, there are no significant signs of long-term aggradation or degradation. However, a value of 1 foot degradation has been assumed for conservative analysis.

Contraction and Pier Scour There is no contraction scour due to the alignment of the new bridge and there is no pier scour because the new single span bridge does not have piers.

Local Abutment Scour Local abutment scour occurs when the abutment obstructs the flow. In the case of the Clay Street Bridge the right and left abutment scour is fairly similar. The abutment scour was calculated using Froehlich’s equation as described in HEC-18. The abutment scour was calculated for the worst case conditions using the channel capacity flow conditions. ⎛ a' Ys = 2.27 × K 1 × K 2 × ⎜⎜ Ya ⎝ Ya

⎞ ⎟⎟ ⎠

0.43

× Fr 0.61 + 1

where : K 1 = vertical wall K 2 = angle coeff. a' = Projection into Normal flow Ya = average depth of flow on the floodplain Fr = Froude number of approach upstream of the abutment Fr =

Ve (g × y a )1/2

Ve = Average velocity in overbank g = 32.2 ft/sec

Table 10 below shows the variables for the right and left abutment scour calculations and the total scour calculated. Table 10. Variables for abutment scour calculations. Right Abutment

Left Abutment

K1

1.0

1.0

K2

1.0

1.0

a’ (ft)

15.9

56.4

Fr

0.37

0.41

ya (ft)

1.85

0.85

ys (ft)

7.6

7.7

10

Clay Street Hydrology/Hydraulics

To t a l S c o u r P o t e n t i a l a n d R e c o m m e n d a t i o n s The scour potential at the Clay Street Bridge at Hangtown Creek consists mostly of abutment scour. The maximum scour expected at the abutments is 7.6 feet for the right abutment and 7.7 feet for the left abutment. However, it is important to note that bedrock exists in this area and that abutment scour will only occur to the depth of bedrock. Rock protection is recommended at the abutments if foundation exposure is an issue. If rock protection is necessary, it should consist of standard Caltrans facing material with a minimum thickness of 1.8 feet for a width of 5 feet along each abutment. Significant scour is not anticipated at the confluence of Hangtown Creek and Cedar Ravine due to the proposed alignment of the new bridge and the outlet of Cedar Ravine. The proposed alignment of Cedar Ravine outlet will direct flow inline (parallel) with the flow of Hangtown Creek reducing cross bank flow and turbulence from that of the existing alignment. The existing rock channel bottom has not experienced significant sour downstream of the confluence, therefore the improved condition is not expected to show any measurable scour. If existing rock downstream from the culvert outlet is removed during construction it should be replaced in-kind or using Caltrans facing material as described above. The limits of the rock protection should extend approximately 20 feet downstream from the culvert outlet.

11

Clay Street Hydrology/Hydraulics

APPENDIX A - PROPOSED BRIDGE PLANS

Clay Street Bridge H & H Analysis

APPENDIX B - HEC-HMS OUTPUT

Clay Street Bridge H & H Analysis

HEC-HMS SCHEMATIC FOR THE 50-YR AND 100-YR EVENTS

AREA OF INTEREST

Project: Clay Street Brdg

Simulation Run: Existing 50YR

Start of Run: 01Jan2006, 00:00 End of Run: 02Jan2006, 00:00 Compute Time: 15Nov2007, 08:45:30 Volume Units:

Basin Model: Existing Meteorologic Model: GAGE 50YR Control Specifications: 1-day

AC-FT

Hydrologic Element

Drainage Area (MI2)

Peak Discharge Time of Peak (CFS)

Volume (AC-FT)

A1

0.5950

363.55

01Jan2006, 12:32

116.64

C1

0.4761

267.69

01Jan2006, 12:32

92.32

C2

0.0555

44.48

01Jan2006, 12:16

12.53

C3

0.3050

238.37

01Jan2006, 12:17

61.51

CR

0.8366

381.27

01Jan2006, 12:20

165.60

HC_CR

5.5396

2782.33

01Jan2006, 12:33

1023.52

HT1

0.2400

138.65

01Jan2006, 12:30

43.21

HT2

0.3160

208.84

01Jan2006, 12:21

57.82

HT3

0.1680

154.25

01Jan2006, 12:19

41.95

HT4

0.1010

104.94

01Jan2006, 12:18

29.34

HT5

0.0650

47.77

01Jan2006, 12:17

12.32

HT6

0.0750

63.96

01Jan2006, 12:16

16.59

HT7

0.0720

63.94

01Jan2006, 12:22

18.36

J1

1.3180

597.39

01Jan2006, 12:41

205.10

J2

4.6310

2396.34

01Jan2006, 12:32

841.32

J3

0.7660

522.51

01Jan2006, 12:24

155.57

J4

1.6010

1021.15

01Jan2006, 12:29

314.74

J5

1.9170

1205.27

01Jan2006, 12:28

372.31

J6

2.4650

1456.65

01Jan2006, 12:29

472.60

J7

2.8080

1595.69

01Jan2006, 12:30

527.30

J9

0.3100

108.74

01Jan2006, 12:31

45.37

L1

0.0500

21.69

01Jan2006, 12:25

6.36

L1.2

0.0960

50.38

01Jan2006, 12:15

12.75

L1.3

0.1360

65.88

01Jan2006, 12:28

20.01

L2

0.0700

60.10

01Jan2006, 12:10

13.73

Page 1

Hydrologic Element

Drainage Area (MI2)

Peak Discharge Time of Peak (CFS)

Volume (AC-FT)

L2.2

0.0280

34.11

01Jan2006, 12:04

6.67

R1

0.5340

239.58

01Jan2006, 12:38

81.67

R1-R2

0.5340

239.48

01Jan2006, 12:46

80.93

R2

0.7840

370.43

01Jan2006, 12:36

124.17

R2-R3

1.3180

597.16

01Jan2006, 12:46

203.84

R3

0.4300

331.91

01Jan2006, 12:22

94.13

RC1

0.5316

236.37

01Jan2006, 12:56

104.09

RES-C1

0.5316

236.44

01Jan2006, 12:48

104.81

RES-LL

0.1860

76.92

01Jan2006, 12:37

25.98

RHT-1

0.7660

522.20

01Jan2006, 12:28

154.89

RHT-10

0.1860

76.92

01Jan2006, 12:38

25.95

RHT-11

0.3100

108.73

01Jan2006, 12:32

45.35

RHT-12

0.3100

108.72

01Jan2006, 12:33

45.28

RHT-2

1.6010

1020.83

01Jan2006, 12:30

314.49

RHT-6

1.9170

1204.82

01Jan2006, 12:30

371.63

RHT-7

2.4650

1452.78

01Jan2006, 12:31

471.28

RHT-8

2.8080

1594.41

01Jan2006, 12:31

526.76

RHT-9

4.6310

2389.18

01Jan2006, 12:34

839.56

S1

0.1770

53.84

01Jan2006, 12:15

14.35

SM1

0.5850

380.84

01Jan2006, 12:26

113.84

SM2

0.1810

154.46

01Jan2006, 12:19

41.74

Page 2

Project: Clay Street Brdg

Simulation Run: Gage 100YR

Start of Run: 01Jan2006, 00:00 End of Run: 02Jan2006, 00:00 Compute Time: 15Nov2007, 08:43:49 Volume Units:

Basin Model: Existing Meteorologic Model: Gage 100YR Control Specifications: 1-day

AC-FT

Hydrologic Element

Drainage Area (MI2)

Peak Discharge Time of Peak (CFS)

Volume (AC-FT)

A1

0.5950

418.01

01Jan2006, 12:31

133.73

C1

0.4761

308.36

01Jan2006, 12:32

105.87

C2

0.0555

50.90

01Jan2006, 12:16

14.27

C3

0.3050

276.06

01Jan2006, 12:16

71.79

CR

0.8366

450.13

01Jan2006, 12:42

191.07

HC_CR

5.5396

3219.30

01Jan2006, 12:33

1183.79

HT1

0.2400

160.91

01Jan2006, 12:29

49.95

HT2

0.3160

243.03

01Jan2006, 12:21

66.97

HT3

0.1680

174.17

01Jan2006, 12:18

47.52

HT4

0.1010

116.79

01Jan2006, 12:18

32.72

HT5

0.0650

55.56

01Jan2006, 12:17

14.39

HT6

0.0750

73.34

01Jan2006, 12:16

19.09

HT7

0.0720

71.83

01Jan2006, 12:22

20.90

J1

1.3180

703.50

01Jan2006, 12:40

240.59

J2

4.6310

2789.80

01Jan2006, 12:32

973.90

J3

0.7660

602.14

01Jan2006, 12:24

179.02

J4

1.6010

1176.67

01Jan2006, 12:29

361.91

J5

1.9170

1391.98

01Jan2006, 12:28

428.59

J6

2.4650

1686.46

01Jan2006, 12:28

545.03

J7

2.8080

1849.82

01Jan2006, 12:30

609.04

J9

0.3100

130.86

01Jan2006, 12:30

53.81

L1

0.0500

26.22

01Jan2006, 12:25

7.61

L1.2

0.0960

61.18

01Jan2006, 12:15

15.32

L1.3

0.1360

78.19

01Jan2006, 12:28

23.57

L2

0.0700

70.39

01Jan2006, 12:10

15.99

Page 1

Hydrologic Element

Drainage Area (MI2)

Peak Discharge Time of Peak (CFS)

Volume (AC-FT)

L2.2

0.0280

40.03

01Jan2006, 12:04

7.80

R1

0.5340

282.26

01Jan2006, 12:37

95.59

R1-R2

0.5340

282.14

01Jan2006, 12:46

94.74

R2

0.7840

434.69

01Jan2006, 12:36

145.85

R2-R3

1.3180

703.16

01Jan2006, 12:46

239.11

R3

0.4300

379.04

01Jan2006, 12:22

107.29

RC1

0.5316

330.37

01Jan2006, 12:43

119.28

RES-C1

0.5316

335.41

01Jan2006, 12:35

120.09

RES-LL

0.1860

92.06

01Jan2006, 12:37

30.71

RHT-1

0.7660

601.78

01Jan2006, 12:28

178.24

RHT-10

0.1860

92.04

01Jan2006, 12:38

30.68

RHT-11

0.3100

130.82

01Jan2006, 12:30

53.79

RHT-12

0.3100

130.81

01Jan2006, 12:32

53.71

RHT-2

1.6010

1176.32

01Jan2006, 12:30

361.62

RHT-6

1.9170

1391.44

01Jan2006, 12:30

427.81

RHT-7

2.4650

1682.13

01Jan2006, 12:31

543.49

RHT-8

2.8080

1848.20

01Jan2006, 12:31

608.41

RHT-9

4.6310

2780.51

01Jan2006, 12:34

971.82

S1

0.1770

70.99

01Jan2006, 12:15

18.43

SM1

0.5850

440.21

01Jan2006, 12:26

131.44

SM2

0.1810

176.62

01Jan2006, 12:19

47.57

Page 2

APPENDIX C - HEC-RAS OUTPUT FOR HANGTOWN CREEK

Clay Street Bridge H & H Analysis

HEC-RAS Plan: Existing River: Hangtown Creek Reach: Clay Street Reach

River Sta

Profile

Q Total

Min Ch El

W.S. Elev

Crit W.S.

E.G. Elev

E.G. Slope

Vel Chnl

Flow Area

Top Width

(cfs)

(ft)

(ft)

(ft)

(ft)

(ft/ft)

(ft/s)

(sq ft)

(ft)

Froude # Chl

Clay Street

1235

100 YR

2852.00

1857.75

1870.61

1867.31

1871.22

0.002226

6.79

474.51

88.24

0.38

Clay Street

1235

50 YR

2453.00

1857.75

1870.02

1866.39

1870.61

0.002279

6.64

422.51

88.24

0.38

Clay Street

1190

Clay Street

1175

100 YR

2852.00

1857.75

1867.31

1867.31

1870.28

0.014654

13.89

208.62

38.96

0.94

Clay Street

1175

50 YR

2453.00

1857.75

1866.39

1866.39

1869.38

0.017418

13.89

176.61

30.69

1.01

Clay Street

1079

100 YR

2852.00

1856.40

1867.71

1868.75

0.005667

8.24

361.13

99.30

0.57

Clay Street

1079

50 YR

2453.00

1856.40

1865.53

1867.27

0.013011

10.57

232.09

45.18

0.82

Clay Street

953

100 YR

2852.00

1852.69

1866.70

1861.84

1868.36

0.001495

10.33

276.19

183.84

0.50

Clay Street

953

50 YR

2453.00

1852.69

1865.20

1861.03

1866.76

0.001656

10.03

244.66

32.05

0.52

Clay Street

941.5

Clay Street

931

100 YR

3219.00

1853.20

1863.49

1863.49

1867.99

0.004535

17.03

189.05

46.71

1.00

Clay Street

931

50 YR

2782.00

1853.20

1862.65

1862.65

1866.74

0.004686

16.22

171.52

44.32

1.00

Clay Street

861

100 YR

3219.00

1852.08

1864.26

1865.07

0.002850

7.66

479.25

112.40

0.46

Clay Street

861

50 YR

2782.00

1852.08

1863.89

1864.61

0.002649

7.17

438.25

107.15

0.44

Clay Street

674

100 YR

3219.00

1850.42

1863.98

1862.14

1864.56

0.002002

6.81

558.35

108.91

0.36

Clay Street

674

50 YR

2782.00

1850.42

1863.63

1859.44

1864.14

0.001829

6.38

520.12

108.91

0.34

Clay Street

659.5

Clay Street

645

100 YR

3219.00

1850.42

1862.14

1862.14

1863.74

0.005943

10.85

357.76

108.91

0.62

Clay Street

645

50 YR

2782.00

1850.42

1860.64

1859.44

1863.30

0.010464

13.10

214.22

81.01

0.81

Clay Street

500

100 YR

3219.00

1847.91

1860.32

1860.32

1861.87

0.007719

10.75

358.30

108.90

0.65

Clay Street

500

50 YR

2782.00

1847.91

1859.86

1859.86

1861.42

0.008063

10.59

308.77

103.30

0.66

Clay Street

0

100 YR

3219.00

1837.91

1850.32

1850.32

1851.87

0.007719

10.75

358.30

108.90

0.65

Clay Street

0

50 YR

2782.00

1837.91

1849.86

1849.86

1851.42

0.008063

10.59

308.77

103.30

0.66

Bridge

Bridge

Bridge

1

HEC-RAS Plan: Final_Proposed River: Hangtown Creek Reach: Clay Street Reach

River Sta

Profile

Q Total (cfs) 2852.00

Min Ch El (ft) 1857.75

W.S. Elev (ft) 1870.60

Crit W.S. (ft) 1867.29

E.G. Elev (ft) 1871.22

E.G. Slope (ft/ft) 0.002148

Vel Chnl (ft/s) 6.86

Flow Area (sq ft) 473.51

Top Width (ft) 88.24

Froude # Chl

2453.00

1857.75

1870.01

1866.39

1870.60

0.002192

6.70

421.50

88.24

0.38

1867.29 1866.41

1870.29 1869.38

0.013875 0.016189

13.92 13.84

208.12 177.23

38.85 30.87

0.94 1.00

Clay Street

1235

100 YR

Clay Street

1235

50 YR

0.38

Clay Street

1190

Clay Street Clay Street

1175 1175

100 YR 50 YR

2852.00 2453.00

1857.75 1857.75

1867.29 1866.41

Clay Street

1079

100 YR

2852.00

1856.40

1867.28

1868.53

0.007300

8.97

320.71

79.31

0.64

Clay Street

1079

50 YR

2453.00

1856.40

1866.29

1867.59

0.008831

9.18

267.32

48.57

0.69

Clay Street Clay Street

1034.75 1034.75

100 YR 50 YR

2852.00 2453.00

1856.00 1856.00

1867.31 1866.36

1863.82 1863.24

1868.25 1867.25

0.002764 0.003062

7.78 7.55

366.62 324.79

112.58 90.13

0.48 0.49

Clay Street

995.25

100 YR

2852.00

1855.00

1865.61

1864.04

1867.76

0.003911

11.75

242.69

87.77

0.73

Clay Street

995.25

50 YR

2453.00

1855.00

1864.89

1863.33

1866.80

0.003954

11.10

220.98

57.06

0.72

Clay Street

967.25

Clay Street Clay Street

939.25 939.25

100 YR 50 YR

2852.00 2453.00

1854.50 1854.50

1863.85 1863.10

1863.85 1863.10

1867.17 1866.21

0.008068 0.008266

14.63 14.15

194.90 173.37

50.22 47.75

1.00 1.01

Clay Street Clay Street

921.25 921.25

100 YR 50 YR

3219.00 2782.00

1854.00 1854.00

1863.53 1863.41

1865.67 1865.06

0.003878 0.003046

11.73 10.29

274.49 270.36

46.64 46.27

0.74 0.65

Clay Street Clay Street

861 861

100 YR 50 YR

3219.00 2782.00

1852.08 1852.08

1864.26 1863.89

1865.07 1864.61

0.002850 0.002649

7.66 7.17

479.25 438.25

112.40 107.15

0.46 0.44

Clay Street Clay Street

674 674

100 YR 50 YR

3219.00 2782.00

1850.42 1850.42

1863.98 1863.63

1862.14 1859.44

1864.56 1864.14

0.002002 0.001829

6.81 6.38

558.35 520.12

108.91 108.91

0.36 0.34

Clay Street

659.5

Clay Street Clay Street

645 645

100 YR 50 YR

3219.00 2782.00

1850.42 1850.42

1862.14 1860.64

1862.14 1859.44

1863.74 1863.30

0.005943 0.010464

10.85 13.10

357.76 214.22

108.91 81.01

0.62 0.81

Clay Street Clay Street

500 500

100 YR 50 YR

3219.00 2782.00

1847.91 1847.91

1860.32 1859.86

1860.32 1859.86

1861.87 1861.42

0.007719 0.008063

10.75 10.59

358.30 308.77

108.90 103.30

0.65 0.66

Clay Street Clay Street

0 0

100 YR 50 YR

3219.00 2782.00

1837.91 1837.91

1850.32 1849.86

1850.32 1849.86

1851.87 1851.42

0.007719 0.008063

10.75 10.59

358.30 308.77

108.90 103.30

0.65 0.66

Bridge

Bridge

Bridge

1

A P P E N D I X D - H E C - R A S O U T P U T F O R C E D A R R AV I N E

Clay Street Bridge H & H Analysis

HEC-RAS Plan: Existing River: Cedar Ravine Reach: Cedar Ravine Reach

River Sta

Profile

Q Total

Min Ch El

W.S. Elev

Crit W.S.

E.G. Elev

E.G. Slope

Vel Chnl

Flow Area

Top Width

Froude # Chl

(cfs) 450.00

(ft) 1870.16

(ft) 1878.05

(ft) 1875.34

(ft) 1878.28

(ft/ft) 0.001029

(ft/s) 4.40

(sq ft) 129.87

(ft) 50.18

0.29

381.00

1870.16

1876.38

1874.78

1877.16

0.004098

7.32

59.29

28.43

0.56

1876.94 1876.48

0.001673 0.002130

5.36 5.71

106.74 80.94

50.18 40.46

0.37 0.41

Cedar Ravine

1536

100YR

Cedar Ravine

1536

50YR

Cedar Ravine

1521

Cedar Ravine Cedar Ravine

1506 1506

100YR 50YR

450.00 381.00

1869.16 1869.16

1876.59 1876.04

Cedar Ravine

1466

100YR

450.00

1868.66

1876.65

1873.40

1876.85

0.000939

4.07

137.11

50.18

0.27

Cedar Ravine

1466

50YR

381.00

1868.66

1876.13

1872.86

1876.36

0.001157

4.30

110.82

50.18

0.29

Cedar Ravine

1345.25

Cedar Ravine Cedar Ravine

1224.5 1224.5

1864.17 1864.17

1874.11 1873.10

1870.09 1869.46

1874.94 1873.88

0.002390 0.002453

7.29 7.08

61.74 53.78

7.83 7.83

0.46 0.48

Cedar Ravine

1077.75

Cedar Ravine Cedar Ravine

931 931

100YR 50YR

450.00 381.00

1853.20 1853.20

1863.42 1863.27

1865.14 1864.55

0.002918 0.002237

10.51 9.08

42.84 41.98

46.53 46.08

0.66 0.58

Cedar Ravine Cedar Ravine

861 861

100YR 50YR

450.00 381.00

1852.08 1852.08

1864.26 1863.89

1864.28 1863.90

0.000056 0.000050

1.07 0.98

479.39 438.76

112.41 107.22

0.06 0.06

Bridge

Culvert 100YR 50YR

450.00 381.00 Culvert

1855.31 1855.05

1