August 13, 2012 ADDENDUM ONE INVITATION FOR BID (IFB) NUMBER 11A2029 Installation and Removal of Caltrans owned Safe-Span Decking System in Span 14 and Span 22 of the Coronado Bay Bridge Addendum 1 is being issued to Add the Safe Span Plan as Attachment 3 to the Attachment 12 - Proposed Form of Agreement, STD 213, Correct the Term “Quick Deck” used in Bid Proposal – Attachment 1 to “Safe-Span”, Modify Section A, In Exhibit A - Scope Of Work, Item 1 of Proposed Form of Agreement, Std 213 – Attachment 12, and Address Questions and Answers: 1) Question:
Answer:
Will training records for Contractor employees installing or removing the Safe Span and Quick Deck scaffolding need to be available for review by Caltrans. Yes.
Please see the attached Safe-Span Plan – Attachment 3. Please use the attached revised Bid Proposal – Attachment 1 to submit your bid. Exhibit A – Scope of Work, Item 1, Section A of the Attachment 12 – Proposed Form of Agreement, Std 213 has been modified as follows: A. There is currently suspended scaffolding (Safe-Span) installed in Span 22 of the Coronado Bay Bridge (CBB) which must be removed. The Contractor shall install suspended scaffolding in Span 14 of the CBB which is a new installation. Bids Installation and Removal of Caltrans owned Safe-Span Decking System in Span 14 and Span 22 of the Coronado Bay Bridge Services shall be submitted with the full understanding of this Addendum. The revision declared in this addendum, is an essential part of the IFB package. All other terms and conditions of this IFB dated July 30, 2012 remain the same. The due date for Bid August 28, 2012 is unchanged.
“Caltrans improves mobility across California”
Safe Span Plan
Agreement Number 11A2029 Attachment 3 Page 1 of 5
Safe Span Plan
Agreement Number 11A2029 Attachment 3 Page 2 of 5
Safe Span Plan
Agreement Number 11A2029 Attachment 3 Page 3 of 5
Safe Span Plan
Agreement Number 11A2029 Attachment 3 Page 4 of 5
Safe Span Plan
Agreement Number 11A2029 Attachment 3 Page 5 of 5
Invitation For Bid IFB Number 11A2029 Page 1 of 1 STATE OF CALIFORNIA · DEPARTMENT OF TRANSPORTATION
BID PROPOSAL
ATTACHMENT 1
ADM-1412 (REV. 06/06)
CONTRACTOR’S NAME (Please Print):
CONTRACT NO.
Page 1
11A2029 ITEM NO.
ITEM
1
HOURS ON SITE LABOR
Installation of Safe Span estimated at 15,000 Square Feet at San Diego / Coronado Bay Bridge – Span 14,
Of 1 LABOR COST PER HOUR (In Figures)
TOTAL LABOR COST (Labor Cost Per Hour X Hours On Site Labor)
$
$
$
$
TOTAL THIS PROPOSAL
$________________
Estimated One (1) Deck Move.
2
Removal of Safe Span estimated at 20,000 Square Feet at San Diego / Coronado Bay Bridge – Span 22, Estimated One (1) Deck Move.
(1) THE ABOVE QUANTITIES ARE ESTIMATES ONLY AND ARE GIVEN AS A BASIS FOR COMPARISON OF BIDS. NO GUARANTEE IS MADE OR IMPLIED AS TO THE EXACT QUANTITY THAT WILL BE NEEDED. (2) IN CASE OF DISCREPANCY BETWEEN THE UNIT PRICE AND THE TOTAL SET FORTH FOR A UNIT BASIS ITEM, THE UNIT PRICE SHALL PREVAIL.