CRRMA BOARD PRESENTATION EP STREETCAR PROJECT – VEHICLE PROCUREMENT & SCORING CRITERIA Raymond L. Telles February 11, 2015
Camino Real Regional Mobility Authority El Paso Streetcar Project • • • •
Project Procurement Processes Proposed Procurement Timelines Proposed Vehicle Scoring Criteria Requested Board Action
2
El Paso Streetcar Project Project Procurement Process – General • Two Procurement Processes: Infrastructure and Vehicles • Infrastructure Procurement process will include a Request for Qualifications and a Request for Proposals • Vehicle Procurement process will include a Request for Proposal • CRRMA Board identifies the Selection Criteria and Scoring for each Procurement • Each Procurement will include an Evaluation Committee to develop a recommendation for Board Consideration • CRRMA Board will select the Infrastructure and Vehicle Contractors 3
El Paso Streetcar Project Proposed Infrastructure Procurement Timeline Proposed Infrastructure Procurement Timeline: • • • • • • • •
January 20, 2015 – RFQ was Issued February 19, 2015 – Proposals are Due to the CRRMA March, 2015 – CRRMA Board Identifies Contractor Shortlist April, 2015 – RFP to be Issued May, 2015 – Proposals are Due to the CRRMA June, 2015 – CRRMA Board Selects Infrastructure Contractor Mid/Late 2016 – Maintenance Facility is Substantially Complete Mid/Late 2017 – Rail & Guideway is Substantially Complete 4
El Paso Streetcar Project Proposed Vehicle Procurement Timeline Proposed Vehicle Procurement Timeline: • • • • • •
February, 2015 – RFP to be Issued April, 2015 – Proposals are Due to the CRRMA May, 2015 – CRRMA Board Selects Vehicle Contractor Mid-2017 – Contractor Begins Delivery of Completed Vehicles Early/Mid-2018 – All Vehicles are On-Site Mid/Late 2018 – Testing/Acceptance/Start-Up is Complete
5
El Paso Streetcar Project Proposed Vehicle RFP Scoring Criteria Financial Qualifications Technical Proposal
Pass/Fail 60%
• Proposed vehicle, as demonstrated by completeness, detail, responsiveness and adherence of the Technical Proposal to applicable provisions of the RFP • Management Approach and Schedule • System Assurance and Quality Assurance Plan • Testing and System Support Approach • Qualifications, Experience and References
Price Proposal • Schedule of Prices, per RFP
40% 6
El Paso Streetcar Project Requested Board Action Items 1) Motion to adopt the selection criteria and scoring enumerated within this presentation for the procurement of the vehicle component of the El Paso Streetcar Project. 2) Motion to authorize the Executive Director to issue the Request for Proposals, and associated documents and instruments, as they relate to the vehicle component of the El Paso Streetcar Project.
7
Questions?
Camino Real Regional Mobility Authority 300 N. Campbell, 2nd Floor El Paso, Texas 79902 (915) 212-1072
[email protected] www.crrma.org