feed-in tariffs reform package - Regensw

FEED-IN TARIFFS REFORM PACKAGE Rachel Solomon Williams, DECC 17 APRIL 2012

PURPOSE OF THE FITS SCHEME

• Provides support for small-scale solar PV, hydro, AD, wind, µCHP • Aims to drive uptake of decentralised energy and engage communities and individuals with the green agenda • Started up in April 2010, using powers established under 2008 Energy Act 2

HOW FITS ARE FUNDED

• Generators are paid by electricity suppliers • Generation tariff plus export tariff

• Suppliers recoup costs through bills • Cost is defined as “imputed tax” and DECC is responsible for managing budget 3

BACKGROUND TO REVIEW

• Launched in Feb 2011 • Aims: – Addressing short-term cost overruns in PV (fast-track + phase 1) – Putting in place more robust cost control systems for the future – Considering tariffs and administration for all technologies 4

9 FEB PACKAGE OF PUBLICATIONS

• Solar PV – confirmation of approach on tariffs and energy efficiency for 1 April • Consultation on PV cost control

• Separate consultation on tariffs for other technologies and on various scheme management issues

5

NEW PV TARIFFS

• Reduced on 1 August 2011 for >50kW • Reduced for 4-10kW >10-50kW >50-100kW >100-150kW >150-250kW >250kW-5MW stand alone

Current generation tariff (p/kWh) 37.8 43.3 37.8 32.9 19 19 15 8.5 8.5

Generation tariff from 1 April (p/kWh) 21.0 21.0 16.8 15.2 12.9 12.9 12.9 8.9 8.9

Multiinstallation tariff (p/kWh) 16.8 16.8 13.4 12.2 10.3 10.3 10.3 8.9 8.9 7

Phase 1 decisions: Energy efficiency requirement

1. Applies to domestic and non-domestic solar PV installations with an eligibility date from 1 April 2012 2. A valid EPC showing a rating of at least D must be submitted with the application for FITs payments in order to receive the standard tariffs (21p/kWh for 4-10kW

16.8

10.9

12.6

13.2

>10-50kW

15.2

9.9

11.4

11.9

>50-150kW

12.9

7.7

9.7

10.1

>150-250kW

12.9

5.8

8

10.1

>250-5000kW

8.9

4.7

6.8

7.1

Stand alone

8.9

4.7

6.8

7.1

13

Phase 2A: Degression proposals

• Proposes automatic ‘baseline’ degression of: – 5% in October 2012 – 10% every 6 months thereafter

• Plus a ‘contingent’ degression mechanism triggered by deployment: – if deployment exceeds 125% of the projected level – the next automatic degression step is applied 2 months later (unless it was due to come in within 2 months in any case) – based on published data, available to everyone 14

Phase 2A: Tariff lifetime, indexation, and export tariffs

The consultation also sought views on whether: – the tariff lifetime should be reduced from 25 to 20 years

– tariffs should remain index-linked – the level of the export tariff – the multi-installation tariff should remain at 80% of standard tariffs

– the tariff for installations that do not meet the energy efficiency requirement should be equivalent to the stand-alone rate 15

Phase 2B proposals: Basis for tariffs

• Revisit costs based on latest information • Generally no increase to tariffs • 21p cap proposed across all technologies

• Largest scale installations maintained at RO parity at 5 MW crossover (therefore subject to outcome of RO banding review)

16

OTHER TECHNOLOGIES – TARIFF PROPOSALS Technology

Current tariffs (p/kWh) from 1/4/12

Proposed tariffs (p/kWh) from 1/10/12

≤250

14.7

14.7

>250-≤500

13.7

13.7

>500-≤5000

9.9

9.0

≤15

22.0

21.0

>15-≤100

19.7

19.7

>100-≤2000

12.1

12.1

>2000-≤5000

4.9

4.5

Micro-CHP

≤2 kW

11.0

12.5

Wind

≤1.5

35.9

21.0

>1.5-≤15

28.1

21.0

>15-≤100

25.4

21.0

>100-≤500

20.7

17.5

>500-≤1500

10.4

9.5

>1500-≤5000

4.9

4.5

AD

Hydro

Capacity (kW)

17

Phase 2B proposals: Degression and cost control

All technologies should be subject to a tailored version of the cost control regime proposed for PV technologies, including annual automatic degression and capacity triggers: Minimum degression of 5% starting in April 2014 Capacity triggers for Hydro, Wind and AD installations No capacity triggers beyond 2014/15 18

Phase 2B proposals: Preliminary accreditation



Preliminary accreditation – Which projects should be eligible? – At what stage would projects be eligible? • Planning? • Permitting? • Grid? – Should tariffs be guaranteed? • How long the guarantee of tariffs should last • How do we discourage speculative applicants? – How close to the original application should it be to still qualify for benefits of pre-accreditation? Use it or lose it?

19

Phase 2B proposals: Accreditation and administrative issues

Accreditation issues: •

Definition of “site”



Accreditation of micro-hydro installations



Equivalent to MCS



Use of second hand equipment

Other issues including administration of scheme: •

Definition of “community” and ways of applying the definition



Should energy efficiency requirement be extended to other technologies?



Ofgem powers



Data management



Administration of scheme/issues around fraud

Phase 2 consultation closes 26 April 20

www.decc.gov.uk/FITS

[email protected]

21

THANK YOU