Completed to Date • Phase 1 – Field renovation – Backstop netting – Dugout expansion
• Phase 2A – ADA path of travel, parking lot renovation – Landscape berm
Proposed Phase 2B
Proposed Phase 3
Proposed Phase 4
Proposed Phase 5
Potential Costs PHASE 2B: Approximately $420,000 • New dugouts • Temporary covered picnic areas on left and right field lines • Temporary fencing PHASE 3 Approximately $3.8 Million • Replacement center grandstand with concession beneath and press box above • Replacement left and right side grandstands with restrooms beneath • New entry plaza with donor pavers • New donor wall PHASE 4 Approximately $2.5 Million • New left and right side grandstands above dugouts • New permanent cover for picnic areas on left and right field lines • New dual access restrooms on left and right side of entry • New permanent ornamental fencing and gates • New entry element and gates PHASE 5 Approximately $420,000 • New locker room building on left side • Re-worked outfield fence
Next Steps • • • • • • •
Council Approval of Project Vision Gladding/Pac Coast Commitment Other Major Commitments Friends of McBean Campaign Launch Retain Project Architect Complete Project Design Construct Project as Funding Permits