NANO Project AWS

Report 0 Downloads 27 Views
ID

Task Name

2014 Duration

Start

Finish Sep

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40

Design Completion Issue Building Permit GC Pre-Construction Execute CM Contract Notice to Proceed Early Submittals Order Long Lead Material Install Tower Crane Demo & Utility Relocates Shoring & Excavation Slab on Grade Level 1 Concrete Level 2 Concrete Level 3 Concrete Level 4 Concrete Parapet Walls & Curbs Roofing Rooftop Equipment Waterproof Lower Lvls CMU Curtain Wall Stone Exterior Remove Tower Crane Sidewalks & Curbs Asphalt Landscape Deliver Elect Switchgear Energize Switchgear Deliver Elevator Install Elevator Lower-Floor Rough-Ins: Rough-In Fire Prot Overhead HVAC Overhead Plumbing Overhead Electrical Frame Walls MEP Rough-In Walls MEP Inspections Lower-Floor Finishes: Wall Insulation

NanoEngineeringDetail Date: Tue 4/12/16

130 days 1 day 95 days 30 days 1 day 60 days 90 days 20 days 40 days 97 days 20 days 30 days 20 days 20 days 20 days 17 days 18 days 60 days 60 days 15 days 60 days 90 days 5 days 20 days 15 days 35 days 100 days 60 days 180 days 90 days

Mon 9/1/14 Fri 2/27/15 Mon 3/2/15 Mon 3/2/15 Mon 9/29/14 Fri 2/6/15 Wed 2/11/15 Tue 3/24/15 Wed 3/25/15 Wed 3/25/15 Mon 12/22/14Fri 3/13/15 Wed 3/25/15 Tue 7/28/15 Wed 7/29/15 Tue 8/25/15 Mon 3/30/15 Fri 5/22/15 Mon 5/25/15 Tue 10/6/15 Wed 10/7/15 Tue 11/3/15 Wed 11/4/15 Tue 12/15/15 Wed 12/16/15Tue 1/12/16 Wed 1/13/16 Tue 2/9/16 Wed 2/10/16 Tue 3/8/16 Wed 3/9/16 Thu 3/31/16 Fri 4/1/16 Tue 4/26/16 Wed 4/27/16 Tue 7/19/16 Wed 12/16/15Tue 3/8/16 Wed 4/27/16 Tue 5/17/16 Wed 5/18/16 Tue 8/9/16 Wed 6/15/16 Tue 10/18/16 Wed 8/10/16 Tue 8/16/16 Wed 8/17/16 Tue 9/13/16 Wed 9/14/16 Tue 10/4/16 Wed 10/19/16Tue 12/6/16 Wed 7/29/15 Tue 12/15/15 Wed 4/27/16 Tue 7/19/16 Wed 7/29/15 Tue 4/5/16 Wed 7/20/16 Tue 11/22/16

20 days 20 days 20 days 20 days 15 days 20 days 3 days

Wed 3/9/16 Wed 3/9/16 Wed 3/9/16 Wed 3/9/16 Wed 4/6/16 Wed 4/27/16 Wed 5/25/16

5 days

Mon 5/30/16 Fri 6/3/16

Oct

Nov

Dec

2015 Jan Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

2016 Jan Feb

Mar

Apr

May

Jun

Tue 4/5/16 Tue 4/5/16 Tue 4/5/16 Tue 4/5/16 Tue 4/26/16 Tue 5/24/16 Fri 5/27/16

Task

Project Summary

Inactive Milestone

Manual Summary Rollup

Deadline

Split

External Tasks

Inactive Summary

Manual Summary

Progress

Milestone

External Milestone

Manual Task

Start-only

Summary

Inactive Task

Duration-only

Finish-only

Northwest Construction Company

Jul

Aug

Sep

Oct

Nov

Dec

2017 Jan Feb

ID

Task Name

2014 Duration

Start

Finish Sep

41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69

Hang & Tape GWB Painting Doors, Trim, Specialties Laboratory Casework Set Lab Equipment Acoustical Ceiling Grid Fire Protection Heads HVAC Diffusers Plumbing Lab Connections Light Fixtures Electrical Trim & Conns Finish Floor Covering Startup Lab Equipment Drop Ceiling Tiles Level 1 Rough-Ins Level 2 Rough-Ins Level 3 Rough-Ins Level 4 Rough-Ins Level 1 Finishes Level 2 Finishes Level 3 Finishes Level 4 Finishes HVAC S/U & Balancing Commissioning Punchlist Certificate of Completion Certificate of Occupancy Turnover Balance of Close - Out

NanoEngineeringDetail Date: Tue 4/12/16

20 days 15 days 30 days 30 days 15 days 15 days 20 days 20 days 20 days 20 days 30 days 30 days 10 days 10 days 40 days 40 days 40 days 40 days 120 days 120 days 120 days 120 days 30 days 10 days 20 days 1 day 1 day 1 day 30 days

Oct

Nov

Dec

2015 Jan Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

2016 Jan Feb

Mar

Apr

May

Jun

Mon 6/6/16 Fri 7/1/16 Mon 7/4/16 Fri 7/22/16 Mon 7/25/16 Fri 9/2/16 Mon 7/25/16 Fri 9/2/16 Mon 7/25/16 Fri 8/12/16 Mon 9/5/16 Fri 9/23/16 Mon 9/26/16 Fri 10/21/16 Mon 9/26/16 Fri 10/21/16 Mon 8/15/16 Fri 9/9/16 Mon 9/26/16 Fri 10/21/16 Mon 8/15/16 Fri 9/23/16 Mon 8/15/16 Fri 9/23/16 Mon 9/26/16 Fri 10/7/16 Mon 10/24/16Fri 11/4/16 Wed 4/6/16 Tue 5/31/16 Wed 4/13/16 Tue 6/7/16 Wed 4/20/16 Tue 6/14/16 Wed 4/27/16 Tue 6/21/16 Mon 6/6/16 Fri 11/18/16 Mon 6/13/16 Fri 11/25/16 Mon 6/20/16 Fri 12/2/16 Mon 6/27/16 Fri 12/9/16 Mon 11/7/16 Fri 12/16/16 Mon 12/19/16Fri 12/30/16 Mon 12/12/16Fri 1/6/17 Mon 1/9/17 Mon 1/9/17 Mon 1/9/17 Mon 1/9/17 Tue 1/10/17 Tue 1/10/17 Wed 1/11/17 Tue 2/21/17

Task

Project Summary

Inactive Milestone

Manual Summary Rollup

Deadline

Split

External Tasks

Inactive Summary

Manual Summary

Progress

Milestone

External Milestone

Manual Task

Start-only

Summary

Inactive Task

Duration-only

Finish-only

Northwest Construction Company

Jul

Aug

Sep

Oct

Nov

Dec

2017 Jan Feb