Design Completion Issue Building Permit GC Pre-Construction Execute CM Contract Notice to Proceed Early Submittals Order Long Lead Material Install Tower Crane Demo & Utility Relocates Shoring & Excavation Slab on Grade Level 1 Concrete Level 2 Concrete Level 3 Concrete Level 4 Concrete Parapet Walls & Curbs Roofing Rooftop Equipment Waterproof Lower Lvls CMU Curtain Wall Stone Exterior Remove Tower Crane Sidewalks & Curbs Asphalt Landscape Deliver Elect Switchgear Energize Switchgear Deliver Elevator Install Elevator Lower-Floor Rough-Ins: Rough-In Fire Prot Overhead HVAC Overhead Plumbing Overhead Electrical Frame Walls MEP Rough-In Walls MEP Inspections Lower-Floor Finishes: Wall Insulation
NanoEngineeringDetail Date: Tue 4/12/16
130 days 1 day 95 days 30 days 1 day 60 days 90 days 20 days 40 days 97 days 20 days 30 days 20 days 20 days 20 days 17 days 18 days 60 days 60 days 15 days 60 days 90 days 5 days 20 days 15 days 35 days 100 days 60 days 180 days 90 days
Hang & Tape GWB Painting Doors, Trim, Specialties Laboratory Casework Set Lab Equipment Acoustical Ceiling Grid Fire Protection Heads HVAC Diffusers Plumbing Lab Connections Light Fixtures Electrical Trim & Conns Finish Floor Covering Startup Lab Equipment Drop Ceiling Tiles Level 1 Rough-Ins Level 2 Rough-Ins Level 3 Rough-Ins Level 4 Rough-Ins Level 1 Finishes Level 2 Finishes Level 3 Finishes Level 4 Finishes HVAC S/U & Balancing Commissioning Punchlist Certificate of Completion Certificate of Occupancy Turnover Balance of Close - Out
NanoEngineeringDetail Date: Tue 4/12/16
20 days 15 days 30 days 30 days 15 days 15 days 20 days 20 days 20 days 20 days 30 days 30 days 10 days 10 days 40 days 40 days 40 days 40 days 120 days 120 days 120 days 120 days 30 days 10 days 20 days 1 day 1 day 1 day 30 days