Nkoranza North 2014 APR

Report 7 Downloads 47 Views
NKORANZA NORTH DISTRICT ASSEMBLY

IMPLEMENTATION OF DISTRICT MEDIUM-TERM DEVELOPMENT PLAN (2014-2017)

ANNUAL PROGRESS REPORT FOR 2014

PREPARED BY: DISTRICT PLANNING COORDINATING UNIT AUGUST 2015

Table of Contents CHAPTER ONE ....................................................................................................................................... 2 1.0 INTRODUCTION .......................................................................................................................... 2 1.1 KEY M& E OBJECTIVES FOR THE YEAR 2014 ...................................................................... 2 1.2 PROCESSES INVOLVED AND DIFFICULTIES ENCOUNTERED. ...................................... 3 1.3 MAJOR CHALLENGES IN THE M& E ACTIVITIES INCLUDE: ............................................ 4 1.4 STATUS OF IMPLEMENTATION OF DMTDP.......................................................................... 4 1.5 M&E ACTIVITIES OF THE YEAR 2014 ..................................................................................... 9 1.5.1 REPORT ON FUNDING BY SOURCES GH¢ .................................................................... 10 1.5.2 UPDATE ON DISBURSEMENT ......................................................................................... 10 1.5.3 IMPLEMENTATION OF M&E PLAN ................................................................................ 11 1.5.4 UPDATE ON CRITICAL DEVELOPMENT AND POVERTY ISSUES ............................ 11

CHAPTER ONE 1.0 INTRODUCTION A. Annual Progress Report (APR) covers the monitoring and evaluation of activities carried out in the District in 2014. The objectives of the monitoring and evaluation report are to : Provide information on the progress of activities of the district as planned in the DMTDP under the Ghana Shared Growth and Development Agenda and the Annual Action Plan for 2014.

B. The M&E plan has been prepared to assess the performance of the implementation of the DMTDP Objectives and targets. This will enable various stakeholders to monitor the implementation of programs and projects as contain in the AAP. It also allows stakeholders to identify the achievements, strategies and possible Challenges facing the implementation of the district plan, which provides information for effective implementation and co-ordination of the District development priorities at the Regional and National levels. 1.1 KEY M& E OBJECTIVES FOR THE YEAR 2014 1. Ensuring and Sustaining of Macroeconomic Stability •

Improve fiscal revenue mobilization and management



Improve public expenditure management

2. Enhancing Competitiveness of Ghana’s Private Sector • Improve private sector productivity and competitiveness domestically and globally. • Expand access to both domestic and international markets 3. Accelerated Agriculture Modernization & Natural resource Management •

Promote seed and planting material development



Increase access to extension services and re-orientation agriculture education

4. Infrastructure and human Settlements development •

Promote the application of science, technology and innovation in all sector of the economy.



Promote rapid development of the national ICT infrastructure

5. Human Development, Productivity and employment •

Improve quality of teaching and learning



Reduce under nutrition and malnutrition related disorders and deaths among infants and young children in their reproductive ages



Ensure effective application and inclusion of disability issues

5. Transparent and Accountable Governance •

Expand and sustained opportunity for effective citizen engagement



Ensure effective implementation of the decentralised policy and programme

1.2 PROCESSES INVOLVED AND DIFFICULTIES ENCOUNTERED. The M&E process involves tracking the progress of programs and projects implementation and the assessment of inputs, outcomes, outputs and impact using participatory approach with the involvement of stakeholders, such as community members, development partners and Assembly members. The M&E system has an institutionalized arrangement at District, Regional and National levels. The National Development Planning Committee (NDPC) represents the National body and the main activity is to provide guidelines for the preparation of development plans and budgets and also monitor the implementation of plans such as, the M&E & DMTDP Plan. The NDPC also receive data and monitor the implementation of DMTDP of various districts through APR and M&E reports and to ensure that districts perform in the realization of the National objectives as contained in the GSGDA II. Again the RPCU ensures that, the capacities and logistical support to Districts Assemblies are provided for effective monitoring activities. At the District level, the DPCU develop key indicators and targets and lead in the M&E activities. Beneficiary communities formed community Implementation Committees (CIC) and monitor the implementation processes of activities for specific projects such as the DACF, DDF and other projects. The team under take periodic project inspections and attend the monthly site meetings with contractors and consultants, quarterly and annual meetings. Also the DPCU members carry out quarterly monitoring visit to projects sites and to monitor the progress of work as contained in the AAP, led by The DPO. .Also representative of the user agencies and elected Assembly members of beneficiary communities are part of the M&E teams. .

1.3 MAJOR CHALLENGES IN THE M& E ACTIVITIES INCLUDE: •

Lack of commitment of M&E team members to M&E activities



Inadequate logistics, such as vehicles and motor bikes and funds for M&E activities



The GSOP project and DDF funds is the only reliable logistics for M&E in the district.



Participatory M&E is not encouraged as M&E of individual department is done in the district.



Tight schedules of department make it impossible for M & E in the district.



Also some members of the DPCU have little knowledge about M&E activities and report

1.4 STATUS OF IMPLEMENTATION OF DMTDP Nkoranza North District Assembly has implemented the DMTDP for 2014 activities. This was done through the annual Action Plan curved out from the development plan. However some projects which could not be implemented in 2013 due to inadequate funds and the delay in the release of DACF were rolled over to 2014. It is also important to note that, the bad nature of communities in the district delayed project completion. Sometimes delay

roads to beneficiary

on the part of contractors

delayed planned projects .Planned activities for educational infrastructure have been executed with funding from GETFUND , District Development Facility, GSOP and other donor support through CWSA for the provision of boreholes.. Sanitation projects have recorded implementation, but the performance for the environmental sanitation and health education has not been appreciable. The implementation of the DMTDP has received attention. However much needs to be done in the area of health, education and training of staff to achieve the GSGDA objectives. The table below shows the various projects implemented in 2014. NKORANZA NORTH DISTRICT ASSEMBLY,ANNUAL ACTION PLAN,2014

No. A

Sector/Project

1

Ensuring Macro Economic Stability Sensitize the public on the need to pay tax

2

procure 2 No. Motor bikes for revenue collectors

3

Strengthen the revenue task force to monitor revenue collectors

Location District Wide Revenue office Busunya, Kranka,Yefri and Dromankese

Source of funding

Remarks

IGF

Implemented

DACF

Implemented

IGF

Implemented

4

Prepare data base on ratable items in the district

District wide

DACF

0%

B

Sub total Accelerated Agricultural Modernisation and Sustainable Natural Resource Mnagement Support for National farmers’ day Celebrations .

Odumasi

5 6

Facilitate easy access to farming inputs by farmers

District Wide

7

Support agricultural extention services in the District

8 9

DACF

Implemented

IGF

Implemented

District wide

DACF

Implemented

Support for Women's groups/Association in the district

District wide

DACF

Implemented

Carry out Vaccination and treatment of animals

District wide

GOG

Implemented

10

Carry out HIV/AIDs programme for youth in agriculture

District wide

GOG

Implemented

C

Sub total Climate Change Activities

11

Support farmers(males and femalea) in afforestation programme

District Wide

GOG

Implemented

Engage vulnerable groups (males and females) in mango plantation

Bonte

12

GSOP

Implemented

13

Engage vulnerable groups (males and females) in mango plantation

Dromankuma GSOP

Implemented

14

Engage vulnerable groups (males and females) in mango plantation

bomini

GSOP

Implemented

15

Engage vulnerable groups (males and females) in Teak plantation

Timiabu

GSOP

Implemented

16

Engage vulnerable groups (males and females) in Teak plantation

konkrompe GSOP

Implemented

Engage youth in agriculture in afforestation project

Fiema

17

GSOP

Implemented

Establish Nursery

Timiabu

GSOP

Implemented

18

Sub total

D 19 20

Enhancing competitiveness of Ghana’s Private Sector Construcr 1 No. 10 market stalls Organize 1No training workshop for small scale business operators

Bono-Maaso

DACF

65%

Busunya IGF

Implemented

Sub total

Infrastructure and Human Settlement Development. Reshbilitation of 16 km feeder roads

21

Busunya boabeng,Asekpe sika Bonte -fiema

Rehabilitate feeder roads in the District

Dromankese-Dinkra

23

Construct 15km drains in Busunya and Kranka township

Busunya and Kranka

24

Supply electricity power extension and rehabilite street light

District Wide

25

Extend electricity to eight new communities

District Wide

Procure 200 No low tention poles and street bulbs Sub total

District Wide

22

26

F

DDF

100%

DDF

Implemented

DACF

50%

DDF

0%

DACF

0%

DDF

0%

DACF

100%

DACF

100%

DDF

90%

DDF

70%

GETFUND

80%

DACF

90%

DDF

100%

GPEG

100%

GPEG

100%

GPEG

100%

DACF

Implemented

DACF

Implemented

Human Development.Productivity and Employment Education

27

Construction of 1No.3Unit teachers quarters

Odumasi Dwenewoho

28

Construction of 1No. 3Unit Classroom Block, 4Seater KVIP & 2Unit Urinal

29

Rehabilitation of 1no 3Unit Classroom Pavillion

Amanda

30

Construction of 1No. 6Unit Classroom Block, computer lab

Busunya SHS Bodom

31

Construction of 1No. 6Unit Classroom Block with ancillary facilities

32

Rehabilitation of 1no 6Unit primary school block

Fiema

Rehabilitation of 1no 3Unit JHS block

Fiema

33

Rehabilitation of 1 No school block

Kranka

Rehabilitation of 1 No school block

Dromankuma

36

Provide 200No Desk and Cupboards for Basic schools

District Wide

37

Carry out sensitisation programme on road safety for staff

Kranka, Busunya

Organize annual district inter-school quiz

Busunya SHS

34 35

38

39 40

Train district level officers on professional management skills to improve education delivery.

DA

Establish 1No ICT center in the District

Busunya

Support Independence day celebrations

Busunya

41 42

Support teacher trainees in the district

Donors

Implemented

GOG

0%

DACF

Implemented

DACF

Implemented

DACF/MP

Implemented

GETFUND

15%

GETFUND

30%

GETFUND

20%

GETFUND

15%

GETFUND

30%

GETFUND

20%

GETFUND

80%

GETFUND

Implemented

GETFUND

Implemented

DDF

90%

DDF

90%

DACF

Implemented

DACF

Implemented

District wide

Support needy but brilliant students in the district

District wide

43

Construction of 1No storey administration block

Busunya SHS

44

Construction of 1No dormitary block for boys

Busunya SHS

45

Construction of 1No dinning hall with kitchen

Busunya SHS

46

Yafri SHS

47

Construction of 1No storey administration block Construction of 1No dormitary block for boys

Yafri SHS

48

Construction of 1No dinning hall with kitchen

Yafri SHS

49 50

Construction of 1No 2storey 12 Unit classroom block

Yafri SHS Senya

51

Construction of 6Unit Classroom block & 2Unit KG Block at Senya

Kranka

52

Construction of 6Unit Classroom block & 2Unit KG Block at Kranka

Sub-total Health 53

Construction of 1No CHPs Compound in the District

Dromankuma

Construction of 1No CHPs Compound

Boabeng

54 55

Supply of furniture to CHPs Compound Assembly hall in the District Support NID and Health related activites

56

District Wide

57

Support Malaria and Cholera Prevention Initiative

District Wide

58

Support Nursing trainees in the district

59

Provide equipments to CHPs compounds in the district

60

Support the formation of adolescent clubs in schools

61

Support the prevention,detection and management of diseases

62

carry out malaria prevention detection and management

63

Establishment of mental health services in the District

64

Support HIV/AIDS programmes

District Wide

Carry out sensitisation on adolescent sexual reproductive health in the district

District Wide

65

District Wide

DACF

Implemented

GOG

Implemented

GHS

Implemented

GHS

Implemented

GHS

Implemented

GHS

Implemented

GHS

Implemented

DACF

Implemented

DACF

Implemented

DACF

Implemented

District Wide District Wide

District Wide

District Wide

District wide

Sub total

H

Social Protection Programmes

66

support PWD in the District

67

Carry out sensitisation program on child abuse in the District

68

Carryout sensitisation programme on bush burning in communiries in the District

69

Carryout sensitisation programme on the implementation of projects & programmes Sensitize the public to report abuse cases

70

District Wide

DACF

Implemente d Implemente d

DACF

Implemente d

DACF Bonte and Senya District wide District Wide

DACF

Implemented

GOG/CWS A

Implemented

DACF

Implemented

GOG

Implemented

IGF

Implemented

Sub total Water , Sanitation & Hygiene Mechanization of 5 No. Boreholes

71 72

Construction of 1 No.12 Seater aqua privy toilet

73

Construct 4No Institutional latrines in the District

74

Sensitised communities on environmental hygiene and sanitation in the District

Adumasa,Taaho,Timiab u kokombaline,Tom,Adoe Bodom Asekye, Bonte, Sikaa and Yefri District Wide

75

Support for Fumigation programmes

District Wide

DACF

Implemented

Sub total J

Disaster Management and prevention

76 77 78

Sensitise communities prevention

on

disaster

Procure relief items for disaster victims

District wide District Wide

DACF

Implemented

DACF

Implemented

DDF

Implemented

DACF

70%

DACF

55%

DACF

Implemented

DDF

100%

DACF

Implemented

DACF

Implemented

DACF

0%

Busunya Provide 1No Fire Tender in the District

Sub-total K

Transparent and Accountable Governance

79

Construction of 1No bungalow for the DCE

80 81

Construction of 1No Bungalow for DCD Construction of 1No Office Annex Administration in the District

82

Construction of 1 No. 3 Bedroom Bungalow for MOFA

83

Carry out M&E in the District

Busunya Busunya Busuya

Busunya District Wide DA

84

Support the MTDP( 2014 -2017) preparation process

85

Carry out quarterly ,mid-year and Annual review of AAP

86

Procure Office Materials and Supplies

District Assembly

DACF

Implemented

87

Support the Street Naming & Property Exercise in the District

District Wide

GOG

Implemented

88

Support the capacity Building of DA staff in the District

District Wide

DDF

Implemented

89

Construction of 1No 20 bedroom Compound house in the District

Busunya

DDF

65%

90

Complete the construction of 1 No District Assembly Hall

DACF

55%

DA

Busunya

1.5 M&E ACTIVITIES OF THE YEAR 2014 This section covers the M&E activities for 2014.They include the following: Programme and projects status for the year 2014 •

Update disbursement from funding sources



Update on indicators and targets



Update on critical development and poverty issues

• Evaluation and participatory M&E. 1.5.1 REPORT ON FUNDING BY SOURCES GH¢ Sources DACF IGF DDF GSOP Disability Fund GSFP MP Fund Total

Funds 996,669.97 159,591.60 608,998.10 169,549.64 28,266,19 625,251.00 107,256.67 2,535,991.57

A) There is always delay in the release of funds, especially the DACF which subsequently delays planned projects and programmes in the District. The only reliable fund is DDF, GSOP and other donor funded projects which is also nonexistence in the district. B) The DA is making effort to generate resources locally through the IGF, which is sometimes difficult due to the inadequate data on ratable items in the District as compare to Nkoranza South and other places. The DA has targeted Ghc 217,994.00 to generate Internal Generated Fund for 2014 and and received Ghc 159,591.60 representing 73% of the target for the year. This achievement can be attributed to the efforts of the revenue task force as well as the commission collectors. B) Another challenge with regards to generating funds is the inadequate economic activities in the district. The revenue generation is very low in the area considering the vast nature of the district which is managed by few revenue collectors. The District has only 4 area councils, which is in charge of the entire district in terms of revenue mobilisation. More area councils are required in other parts of the District . 1.5.2 UPDATE ON DISBURSEMENT Expenditure Education (DACF) Health Governance PE Maintenance MP Miscellaneous

Funds

TOTAL

a) The DACF is inadequate in view of the numerous deductions made at source coupled with the delays in the release of the fund subsequently delays planned projects and programme, hence

the DA is unable to achieve its developmental objectives.

1.5.3 IMPLEMENTATION OF M&E PLAN The implementation of the M&E plan has received attention by various sectors in the District, as indicated in the quarterly report. However the M&E is faced with a lot of challenges in terms of logistics and funds for its implementation. 1.5.4 UPDATE ON CRITICAL DEVELOPMENT AND POVERTY ISSUES 1.5.4.1 THE CAPITATION GRANT IMPLEMENTATION IN THE DISTRICT The introduction of the capitation grant has brought about an increased in school enrolment, .Implies overcrowded and pressure on teachers .The implication is that the DA will invest in infrastructure both classroom block and teachers accommodation. 1.5.4.2 THE SCHOOL FEEDING PROGRAMME There are 28 beneficiary schools under the school feeding programme is in 2014

resulting in an

increased in the enrolment of children. The implication is that, the DA needs to provide KG blocks in the district The achievement of the project includes the following: 1. Increased enrolment of both boys and girls 2. Improved retention of school children and nutrition/feeding The major challenges are as follows: 1. Pilfering of food items 2.

lack of funds for monitoring

3. Inadequate kitchen for caterers. 4.

Delay for payments to caterers

5. Ghc0.50 per child a day is inadequate and also taxed making worse for caterers.

1.5.4.3 NON PHYSICALLY PROJECTS (a) ACDI/VOCA Under the ACi, 300 farmers and 6 staffs have been trained on scion selection, grafting for reproductive tree in the district. Also FBOs were also trained under the ACDI/VOCA support with 40 farmers participated ie 16males and 24 female. (b) Animal Production A total of 115 animals were supplied to 21 farmers under the credit parkage.18 males and 3 females benefited the facility. The agricultural sector has also carried out vaccination and prophylactic treatment of various kinds of animals and pets. A total of 2540 of animals have been vaccinated, (c) Waste Management There has been regular supply of logistics from Zoom lion Ghana to improve hygiene and sanitation in the District. The district is able to acquire a waste disposal site at Busunya, Yefri and Kranka.

The DA has organized a sensitization programme in Kranka on the dangers associated with indiscriminate disposal of waste. The EHU has also organized a cleaning up exercise in the district. The DA also carried out house to house inspection of 8511 houses, 9 health centers ,80 basic schools, 6No industries ,market and lorry stations in the district. Again, the unit inspected various sanitation sites in the district to ensure effective and conducive atmosphere for the citizens of the district 1.5.4.4 SOCIAL INTERVENTION PROGRAMMES a. Person’s With Disability. The DA has recorded 25No of person’s with disability with various forms of disability in the district. The DA has also assisted these vulnerable individual with funds to enable them engage in income generating activities such as farming, medical bills and payment of fees. The DA has also taken

a policy to incorporate disability friendly facilities in all its development

projects in the District. This is to enable PWD to have access to all institution in the District. These facilities are designed and well labeled to meet the gender needs of both males and females. b. Kinds of Disability Kind of Disability

Number

Percentage (%)

Blindness Cripple

4 1

16 4

Death and Dumb 6 Physically impaired 9 Others 5 Total 25 Source: Nkoranza North District Baseline Survey, 2014

24 36 20 100.0

c. Child Maintenance Programme Sensitization programmes was also carried out in the district on the domestic. 4No cases on child maintenance was registered and successful handled d. Climate Change Activities The district Assembly has embarked on climate change activities in mango and teak plantations in the following communities; Bomini, Bonte, Timiabu, Konkrompe and Asekye under the Ghana Social Opportunity Project (GSOP). About 590 (males 164 and female 426) people were engaged in the plantation activities as a source of income earnings to the vulnerable under the social protection programmes in the district.

e.

Natural Resource Management

A total of 492 males and 120 females benefited from the afforestation project under the herbicide, mango, cashew and fire belt creation in the district. f. HIV /AIDS The MOFA had carried out sensitization program on HIV/AIDs to farmer youth in the district on Behavioral Change. A total of 764 people benefited from the program ie 373 males and 391 females. The programme was to discuss with farmers on how to reduce HIV/AID epidemic and its associated risk in the district and to promote better lives among the youth. The programme was successful and farmers participated actively.

People living with HIV/AIDS as at the end of 2013

Source: DHD, 2013 The figure clearly shows an improvement in policy measures of the district to curb the pandemic. In 2010, 20 people were affected. The situation dropped in 2011 but rose unexpectedly in 2012. With many efforts from the DHMT, the situation reduced convincingly to 8 in the whole district by the end of 2013.

g. CARMMA Projects The District Assembly has initiated projects and programmes to reduce Maternal Morbidity in the District by providing a number of CHPs compounds with equipment in the area thereby improving the health status of citizen especially. Again sensitisation programmes were carried out under the adolescent reproductive health and also immunised children under five against several diseases. h. Gender Activities As part of the activities in the AAP, the DA has organized a sensitization programme on adolescent sexual reproductive health for women in the district. The DA has also taken a policy to incorporate the provision of KVIP Toilets and Urinals for boys and girls at all basic schools in the District. These facilities are designed and well labeled to meet the gender needs of both boys and girls. (a) Population figures Age Cohort 0-5 6-17 18-64 65+

Male 2,886 11,797 21,980 978

Female 4,709 7,865 17,983 2,784

Total 7,595 19,662 39,963 3,762

Total 37,641 Source: DPCU .NNDA , 2014

33,341

70982

The population distribution indicates that there is a higher active population (56.3 per cent) figure than inactive population (43.7 per cent) in the District; therefore a strong economically active population in the district. This indicates an active population in the district which is the potential factor for development. However, the district has also recorded a dependency population. i. Educational Enrolments Enrolment at the pre-school level increased from 4,177 in 2010 to 4,813 in 2013, representing 15.2% percentage change. All the educational levels experienced an increased in educational levels as seen from the table below. Table Enrolment Level 2: Enrolment Figures at all levels 2010/2011

Total

2011/2012

Total

boys

girls

Year

boys

girls

KG

2101

2076

4177

2197

2207

Primary

4354

4118

8472

4745

JHS

1188

930

2118

SHS

448

320

Sub total

8091

7444

Grand

15,535

2012/2013

Total

boys

girls

4404

2168

2163

4331

4371

9116

4827

4354

8481

1355

1067

2422

1505

1146

2651

768

575

428

1003

528

437

965

15,535

8872

8073

16,945

9028

8100

17,128

16,945

17,128

total Source: NNDA GES,2013 The enrolment figures keeps increasing at both KG and primary levels from 12,649 in 2011, 13,520 in 2012 and decreased by 708 students (12,812) in 2013. The decreased in the primary level has affected the enrolment in the JHS leading to a low number of candidate presented for BECE .However the increased in the enrolment at the pre-school and primary in first and second years can be attributed to the introduction of the Ghana School feeding programme in the District of which 28 basic schools benefiting.

BECE Performance The table below shows the trend of BECE performance by candidate during the period under review. The BECE performance has been wonderful as the performance of students keeps increasing from 51% to 85% and decreased by 1.58% in 2012. Meanwhile, in 2013 the district was ranked first in the

Country with 98.61% of students with aggregate between 6 and 30. The achievement of the District can be attributed to the efforts by the education directorate in the delivery of services and the provision of educational infrastructure by the district Assembly.

Table …. Trend of BECE Performance by Gender

Year

Number of

Number of

Number of

Qualified to

Candidates registered

Candidates

Candidates Qualified

SHS (%)

Presented

Boys

Girl

Total

Boys

s

Girl

Total

Boys

s

Girl

Total

s

2009/10

268

152

420

264

150

414

140

75

215

51.93

2010/11

329

234

563

327

232

559

270

198

468

85.40

2011/12

353

296

649

352

294

646

311

233

544

83.82

2012/13

368

279

647

367

276

643

355

269

624

98.61

Source: GES, 2013 NNDA Breakdown of District Finance 2010 2011 Insured 253,122.51 273,080.25 Non- Insured 15,808.08 18,843.53 Drugs 171,180.76 185,643.36 Non-Drugs 97,749.83 10628.22 Source: NNDA Annual Progress Report, 2013

2012 327,105.55 19,069.05 196,909.25 148,815.35

2013 502,532.60 20,229.96 231,180.00 291.582.56

j. Rural Electrification The district has extended the rural electrification coverage to 91% in 2014.Out of the 99 communities in the district only 8 communities in the Nkoranza North District are yet to be connected to the National Grid in 2015. The electricity has assisted a lot of agro-processing industries in the district as almost all the grinding mills are hooked to the National grid. k. Roads The road networks in the district needs improvement, however the major road from Asekye had been tarred and other feeder roads received attention of rehabilitation and reshaping. The construction of drainage in the district capital is on-going as work is progressing steadily on the tiring of 30Km road from Asekye to Jema Nkwanta.

1.5.5 UPDATE ON INDICATORS AND TARGETS

DMTDP Goal: THEMATIC AREA: ACCELERATED AGRICULTURAL MODERNISATION AND SUSTAINABLE NATURAL RESOURCES GSGDA Objective: Promote the development of selected staple and horticultural crops :Promote livestock and poultry development for food security and income generation Focus Area1: Crop development food security, exports and industry : livestock and poultry development Indicators 2014 target 2013 indicator 2012 indicator level 2014 indicator level level 20 % increase in yield of selected crops by 2014. Sorghum 342 285 95 290 81,862 68218 30356 52922 Maize Yam 250,590 208825 132342 153874 Groundnut 8,921 7434 850 8100 Cassava 128,822 107352 150133 101993 Cow pea 5,122 4268 664 5180 10% increase in production of livestock by 2014. Cattle 319 290 551 629 Sheep 4013 36482 5170 5219 Goats 1376 1251 3947 2685 Pigs 337 306 660 556 Local Poultry 32800 29818 29004 31516 Guinea Fowl 2221 2064 2019 3319 Exotic fowls 13692 12447 11085 13312 THEMATIC AREA: INFRASTRUCTURE & HUMAN SETTLEMENT DEVELOPMENT GSGDA:Objective: Provide adequate and reliable power to meet the needs of Ghana and for export FOCUS AREA; Energy supply to support industries and households Proportion of length of roads maintained/rehabilitated 2012 Target 2011 indicator 2010 indicator level level Trunk roads Feeder roads 12km

2012 indicator level

0

Tarred road Number of communities with access to electricity Percentage increase in tourists arrivals

6km 8

5km 91

4km 87

0 0

THEMATIC AREA: HUMAN DEVELOPMENT EMPLOYMENT & PRODUCTIVITY GSGDA: Objective: Increased equitable access to and participation in education at all levels FOCUS AREA: EDUCATION,HEALTH,HIV,AIDS,STIs and TB 2014 2013 indicator 2012 indicator level indicator level level HIV/AIDS prevalence rate (% of adult population, 15-49 yrs. 0 8/1115 23/1301 HIV positive) Sickle Cell diseases 0 3 4 Underweight children 5.2 0.9 Maternal Mortality ratio (Number of deaths due to 0 0 0 pregnancy and childbirth per 100,000 live births) Malaria treatment at OPD 2882 9640 1259 Under-five mortality rate (Number of deaths occurring 0 0 0 between birth and exact age five per 1000 live births) Malaria case fatality in children under five years per 10,000 0 0 0 population Percent of population with sustainable access to safe water source % of population with access to improved sanitation (flush toilets, KVIP, household latrine) Gross Enrolment Rate:(Indicates the number of pupils/students at a given level of schooling-regardless of age- as proportion of the number children in the relevant age Schools: Primary: JHS: KG Net Admission Rate in Primary Schools (Indicates Primary One enrolment of pupils aged 6 years)

2014 Target 77.6% 56.3% 109.10%

2013 indicator 79.8% 51.2% 111.5%

2012 indicator 79.62% 54.0% 78.1%

2014 indicator level 9/1066 44 144 0 10,928 0 0

2014 indicator 78.0% 62.5% 125.0%

Gross Admission Rate ¤ Primary Gender Parity Index (Ratio between girls’ and boys’ enrolment rates, the balance of parity is 1.00) KG: Primary JHS Percentage of BECE Performance Teacher/ Pupil Ratio KG: Primary JHS Completion rate for Girls KG: Primary JHS Number of Classroom KG: Primary JHS

73.1% 83.3%

68.7% 69%

69.2% 67.1%

36.8% 84.9%

1.02% 0.94% 0.92% 85.8%

1.01% 0.95% 0.90% 83.4%

1.05% 0.96% 0.89% 87.10%

0.98% 0.97% 1.05% 96.4%

1:22 1:27 1:15

1:20 1:25 1:12

1:27 1:32 1:20

1:20 1:37 1:11

99.7% 75.5% 38.3%

99.6% 74.5% 31.1%

107.3% 69.3% 38.0%

99.3% 71.7% 51.3%

92 282 90

87 271 81

81 266 68

80 269 94

THEMATIC AREA: TRANSPARENT & ACCOUNTABLE GOVERNANCE GSGDA :Objective Ensure effective implementation of the local Government Service FOCUS AREA: Local Governance and Decentralisation Creation of additional area Council 6 4 Total amount of internally generated revenue 217,994.00 Amount of Development partner& NGO funds contribution to DMTDP Implementation % of DA Expenditure within the DMTDP Budget Number of reported cases of abuse Children Women Men Police Citizen Ratio

1:500

4

4 159591.60

1:10,140