$12 million/yr Chip Seals $44 million/yr Single lift Paving $32 million/yr Rehabilitation $23 million/yr Reconstruction $8 million/yr set aside for stand alone safety features and signs
Experiences with In-Place Recycling In the past 20 years – Cold in place & Hot in place We are finding that they only last one preservation cycle (approx. 15 years) before needed to be replaced.
ODOT has constructed 2 cold in place recycle projects
in the last 5 years (w/HMAC overlay) There are 3 full depth reclamation (cement stabilized)
jobs in design
Recycle Project Costs OR140: Modoc Billy Cr – Fish Hole Cr (2009) Total cost $5.5 million